Redbridge - Multiple Temporary Road Closures for Utility and Highway Works
What is happening?
London Borough of Redbridge
Road Traffic Regulation Act 1984 Section 14(1)
Benton Road – Temporary Prohibition of Traffic
1. The Council of the London Borough of Redbridge hereby gives notice that in order to facilitate gas mains replacement works, it intends to make an Order the effect of which would temporarily prohibit traffic in Benton Road.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, Benton Road would be closed from a point outside the western boundary of No. 1A Colenso Road to the western kerb-line of Aldborough Road South.
3. Whilst the prohibition remains in force an alternative route for traffic would be provided via: Benton Road, Aldborough Road South, Ley Street, Wards Road and Durban Road.
4. Exemptions would be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
5. The Order would come into operation on the 16th of November 2026 and will be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
6. Works would be expected to commence on Monday the 16th of November 2026 and finish on Sunday the 13th of December. The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Eton Road – Temporary Prohibition of Traffic
1. The Council of the London Borough of Redbridge hereby gives notice that in order to facilitate highway maintenance works, has made an Order the effect of which will temporarily prohibit traffic in Eton Road.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, Eton Road will be closed between its junction with Harrow Road and its junction with Richmond Road.
3. Whilst the prohibition remains in force an alternative route for traffic will be provided via: Eton Road, Woodlands Road, Traktle Road, and Richmond Road.
4. Exemptions will be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
5. The Order will come into operation on the 23rd of November 2026 and will be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
6. Works will be expected to commence on Monday the 23rd of November 2026 and finish on Friday the 27th of November. The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Abbey Road – Temporary Prohibition of Traffic
1. The Council of the London Borough of Redbridge hereby gives notice that in order to facilitate gas mains replacement works, has made an Order the effect of which will temporarily prohibit traffic in Abbey Road.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, Abbey Road will be closed from its junction with Perrymans Farm Road to No. 54 Abbey Road.
3. Whilst the prohibition remains in force an alternative route for traffic will be provided via: Abbey Road, Birkbeck Road, Buntingbridge Road, Perrymans Farm Road.
4. Exemptions will be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
5. The Order will come into operation on the 23rd of November 2026 and will be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
6. Works will be expected to commence on Monday the 23rd of November 2026 and finish on Sunday the 6th of December. The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Starch House Lane – Temporary Prohibition of Traffic
1. The Council of the London Borough of Redbridge hereby gives notice that in order to facilitate a telecommunication works, it intends to make an Order the effect of which would temporarily prohibit traffic in Starch House Lane.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, Starch House Lane would be closed from its junction with Forest Road, to a point halfway between its junction with Forest Road and a point outside the north-western boundary of No. 43.
3. Whilst the prohibition remains in force an alternative route for traffic would be provided via: Virginia Gardens and Craven Gardens Forest Road.
4. Whilst works are in progress, or whilst the authorised traffic signs are displayed, the one way system on Starch House Lane would be suspended to allow for two way traffic.
5. Exemptions would be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
6. The Order would come into operation on the 29th of November 2026 and would be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
7. Works would be expected to commence on Sunday the 29th of November 2026 and finish on Monday the 30th of November. The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Perkins Road – Temporary Prohibition of Traffic
1. The Council of the London Borough of Redbridge hereby gives notice that in order to facilitate gas mains replacement works, it intends to make an Order the effect of which would temporarily prohibit traffic in Perkins Road.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, Perkins Road would be closed outside Nos. 2 to 10.
3. Whilst the prohibition remains in force an alternative route for traffic would be provided via: Perkins Road, Birkbeck Road, Buntingbridge Road, and Perrymans Farm Road.
4. Exemptions would be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
5. The Order would come into operation on the 30th of November 2026 and would be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
6. Works would be expected to commence on Monday the 30th of November 2026 and finish on Sunday the 13th of December. The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Wensleydale Avenue – Temporary Prohibition of Traffic
1. The Council of the London Borough of Redbridge hereby gives notice that in order to facilitate the Thames Water works, it intends to make an Order the effect of which would temporarily prohibit traffic in Wensleydale Avenue.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, Wensleydale Avenue would be closed between its junction with Clayhall Avenue and the northern boundary of No. 67 Clayhall Avenue.
3. Whilst the prohibition remains in force, an alternative route for traffic would be provided via Clayhall Avenue, Couchmore Avenue and Ewelhurst Road.
4. Exemptions would be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
5. The Order would come into operation on the 30th of November 2026 and would be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
6. Works would be expected to commence on Monday the 30th of November 2026 and would last for 7 days. The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Dated this 12th of November 2026
Lee Currie, Group Manager Street Works and Network Management
Neighbourhood and Environmental Services Department, Place, Communities and Enterprise Directorate