Redbridge - Multiple Temporary Road Closures Due To Gas & Sewer Works
What is happening?
THE LONDON BOROUGH OF REDBRIDGE
Road Traffic Regulation Act 1984 Section 14(1)- Hamilton Avenue Temporary Prohibition of Traffic
1. THE COUNCIL OF THE LONDON BOROUGH OF REDBRIDGE hereby gives notice that in order to facilitate new gas connections works, it intends to make an Order the effect of which would temporarily prohibit traffic in Hamilton Avenue.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, Hamilton Avenue will be closed between a point 15 meters east of the junction with South Cross Road and a point 30 meters east of that junction.
3. Whilst the prohibition remains in force, an alternative route for traffic would be provided via: Hamilton Avenue, South Cross Road, Campbell Avenue, Ashurst Drive, and Bute Road.
4. Exemptions would be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
5. The Order would come into operation on the 2nd of November 2026 and would be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
6. Works would be expected to commence on Monday the 2nd of November and finish on Friday the 6th of November. The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Road Traffic Regulation Act 1984 Section 14(1) - High View Road Temporary Prohibition of Traffic
1. THE COUNCIL OF THE LONDON BOROUGH OF REDBRIDGE hereby gives notice that in order to facilitate sewer repair works, it intends to make an order the effect of which would temporarily prohibit traffic in High View Road.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, High View Road will be closed outside No. 32.
3. Whilst the prohibition remains in force, an alternative route for traffic would be provided via: High View Road, Bressey Grove, Byron Avenue, and Broadwalk.
4. Exemptions would be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
5. The Order would come into operation on the 4th of November 2026 and would be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
6. Works would be expected to commence on the 4th of November and finish on that day. The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Road Traffic Regulation Act 1984 Section 14(1) - Denehurst Gardens Temporary Prohibition of Traffic
1. THE COUNCIL OF THE LONDON BOROUGH OF REDBRIDGE hereby gives notice that in order to facilitate sewer maintenance works, it intends to make an Order the effect of which would temporarily prohibit traffic in Denehurst Gardens.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, Denehurst Gardens would be closed outside No. 17.
3. Whilst the prohibition remains in force an alternative route for traffic would be provided via: Denehurst Gardens, Dale Gardens, Knighton Drive.
4. Exemptions would be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
5. The Order would come into operation on the 5th of November 2026 and would be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
6. Works would be expected to commence on Thursday 5th of November 2026 and finish on that day. The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Lee Currie Group Manager,
Street Works and Network Management Neighbourhood and Environmental Services Department, Place, Communities and Enterprise Directorate
Dated this 15th of October 2026