Wrexham - Temporary Lane Closure due to Cable Installation Works
What is happening?
Mae Cyngor Bwrdeistref Sirol Wrecsam yn bwriadu gwneud
GORCHYMYN (GWAHARDD TRAFFIG TRWODD) DROS DRO dan
Adran 14(1) Deddf Rheoleiddio Traffig Ffyrdd 1984
o 29/09/2026 a fydd yn gwahardd unrhyw gerbyd rhag defnyddio lôn allanol Cylchfan Kingsley Circle i alluogi O’Connor Utilities, ar ran Scottish Power, i gloddio a gosod ceblau newydd yn y droedffordd ac yn y lôn gerbydau.
Nid oes gwyriad ar waith ar gyfer cau Kingsley Circle, fodd bynnag mae’r gwaith yn cael ei wneud ar y cyd â chau ffyrdd ar Rodfa Eaton a’r Ffordd Fynediad i gefn 103 Ffordd y Tywysog Siarl. Bydd mynediad i gerddwyr yn cael ei gynnal trwy gydol y cyfnod cau.
Disgwylir i’r gwaharddiad bara am 9 wythnos (04/12/26), neu nes y caiff y gwaith ei gwblhau os yn gynt, a gallai bara hyd at 18 mis.
Dyddiedig: 16/09/26
Darren Williams - Prif Swyddog, Amgylcheddol a Thechnegol
Rydym yn croesawu gohebiaeth yn Gymraeg. Byddwn yn ymateb i unrhyw ohebiaeth yn Gymraeg ac ni fydd hyn yn arwain at unrhyw oedi.
Wrexham County Borough Council intends to make a
TEMPORARY (PROHIBITION OF THROUGH TRAFFIC) ORDER
under Section 14(1) of the Road Traffic Regulation Act 1984
effective from 29/09/2026 prohibiting any vehicle from using the outer lane of Kingsley Circle Roundabout to enable O’Connor Utilities on behalf of Scottish Power to excavate and install new cables in the footway and carriageway.
There is no diversion for the lane closure of Kingsley Circle, however works are in conjunction with road closures on Eaton Drive and Access Road to the Rear of 103 Prince Charles Road. Pedestrian access will be maintained throughout the period of closure. The prohibition is expected to last for 9 weeks (04/12/26), or until completion of the works if earlier, with a maximum duration of 18 months.
Dated:16/09/26
Darren Williams – Chief Officer, Environment & Technical
We welcome correspondence in Welsh. We will respond to any correspondence in Welsh which will not lead to a delay.
How long will it take?
Planned start
29-Sept-2026
Estimated end
4-Dec-2026