Try our AI Explainer
This notice is long. Get a simplified view of the most important information, including key dates and locations is seconds.
Hove - Temporary Cycle Lane Closure Due To Electricity Supply Installation
What is happening?
BRIGHTON AND HOVE CITY COUNCIL
ROAD TRAFFIC REGULATION ACT 1984
TEMPORARY TRAFFIC ORDER – WESTERN ESPLANADE, HOVE
1. NOTICE is hereby given that Brighton & Hove City Council intend not less than seven days from the date of this notice to make an Order pursuant to powers in Section 14 of the Road Traffic Regulation Act 1984 as amended which when it comes into force will have the following effect: -
(a) The temporary closure of the cycle lane on Western Esplanade, Hove from the western edge of the King Alfred Leisure Centre building to the junction of Hove Street, a distance of approximately 200 metres.
(b) For the duration of this closure it will be necessary to make the adjacent footway a shared space for pedestrians and cycles
2. The Order is necessary to allow contractors to carry out the Installation of a new electricity supply.
3. This Order comes into force on 7 September 2026 for eighteen months or until such sooner time as the works are completed, which is anticipated to be 14 October 2026.
Dated: 26 August 2026.
Corporate Director, City Operations, Brighton & Hove City Council, Hove Town Hall, Norton Road, Hove, BN3 3BQ.
Brighton & Hove City Council
How long will it take?
Planned start
7-Sept-2026
Estimated end
14-Oct-2026
Need to publish a public notice?
If you need to publish a public notice, please contact Brighton Argus directly at: