Bolton - Temporary Road Closures Due To Electricity Works
What is happening?
THE BOROUGH COUNCIL OF BOLTON
Road Traffic Regulation Act 1984 S.14 - Spa Road / New Holder Street Temporary Closures
The Council has made an order, operative from 10 August 2026 for 2 weeks approx.
The effect of which will be to prohibit all traffic from proceeding on Spa Road from Queensbrook to New Holder Street and on New Holder Street from Spa Road to Garstang Street, to allow electricity works to take place.
Alternative route is via Moor Lane, Deane Road, College Way, Mayor Street.
The Order will end after 18 months or on completion of the works whichever first occurs.
BOLTON COUNCIL
Dated: 3 August 2026
How long will it take?
Planned start
10-Aug-2026
Estimated end
24-Aug-2026
Open to feedback
From
3-Aug-2026
To
24-Aug-2026