Winchester Way - Temporary Footpath Closure Due To Electricity Works
What is happening?
DARLINGTON BOROUGH COUNCIL
ROAD TRAFFIC REGULATION ACT 1984
(TEMPORARY FOOTPATH CLOSURE) ORDER 2026
WINCHESTER WAY, DARLINGTON
Darlington Borough Council intend, not less than seven days from the date of this notice, to make an Order under the provisions of Section 14(1) of the Road Traffic Regulation Act, 1984, as amended, the effect of which will be to close:
WINCHESTER WAY
Footpath leading from Winchester Way to Portsmouth Place and also the footpath to Wells Close at the side of 38
The Order is necessary to allow works by Northern Powergrid to install an electricity cable.
The maximum duration of the temporary closure under this Order is 6 months commencing from 17th August 2026, it is anticipated that it will be effective for approximately 6 weeks.
Dated: 31st July 2026
D. Winstanley Executive Director Environment, Highways & Community Services Group Town Hall Darlington, DL1 5QT
How long will it take?
Planned start
17-Aug-2026
Estimated end
28-Sept-2026