Try our AI Explainer
This notice is long. Get a simplified view of the most important information, including key dates and locations is seconds.
Essex - Multiple Road Traffic Notices
What is happening?
Essex County Council
Proposed relocation and upgrade of Zebra Crossing to Toucan Crossing on Eagle Way, Brentwood
(Brentwood Borough) (Prohibition of Waiting, Loading and Stopping) and (On-Street Parking Places) (Civil Enforcement Area) (Amendment No.32) Order 202*
Notice is hereby given that Under Section 23 of the Road Traffic Regulations Act 1984 (as amended) the Essex County Council proposes to relocate and upgrade a Pedestrian Crossing on Eagle Way, Brentwood.
1. To Remove: ‘Zebra Crossing’
The centre line of the Crossing is located approximately 39 metres west of the extended centre line of Peregrine Drive.
2. To Implement: ‘Toucan Crossing’.
The centre line of the Crossing is located approximately 32 metres west of the extended centre line of Peregrine Drive.
The width between give way lines is approximately 7 metres.
Zigzags are located as follows:
North Side: Approximately 17 metres either side of the Toucan Crossing.
South Side: Approximately 9 metres west, and 17 metres east of the Toucan Crossing.
Notice is also hereby given that the Essex County Council proposes to make the above Order under sections 1(1), 2(1) to (3), 3(2), 4(1), 4(2), 32(1), 35(1), 45, 46, 47, 49, 53, and Parts IV and III of Schedule 9 of the Road Traffic Regulation Act 1984 (as amended),
Effect of the order:
3. To Implement: ‘No Waiting at Any Time’ Restrictions
| Road | Description |
|---|---|
| Eagle Way | North Side: From a point approximately 10 metres east of its junction with The Drive, east for approximately 22 metres. |
| South Side: From its junction with Falcon Drive, west for approximately 13 metres. | |
| Falcon Drive | Both Sides: From its junction with Eagle Way, south for approximately 5.5 metres. |
| 4. To Implement: ‘No Waiting Mon-Sat 8am-6pm’ Restrictions | |
| Road | Description |
| Eagle Way | North Side: From its junction with Peregrine Drive, west for approximately 6 metres. South Side: From the extended centre line of Peregrine Drive, west for approximately 11 metres. |
| 5. To Realign: ‘No Waiting Mon-Sat 8am-6pm’ Restrictions | |
| Road | Description |
| Peregrine Drive | West Side: From its junction with Eagle Way, north for approximately 5.5 metres. |
This Order will be incorporated into ‘The Essex County Council (Brentwood Borough) (Prohibition of Waiting, Loading and Stopping) and (On-Street Parking Places) (Civil Enforcement Area) Consolidation Order 2019’ by substituting map tile: TL590 915 Revision 1 to Revision 2.
Further details: All associated documents for the proposed scheme are available on the Essex Highways website: www.essexhighways.org/traffic-regulation-orders
If you need to view a hard copy of these documents, please call (or text) 07761 758317 to arrange a suitable time to inspect the documents quoting the below reference number. Documents can be made available for inspection 8.30am-5.30pm Mon-Thurs and 8.30am-5pm on Friday at Essex County Council, County Hall E block main reception, Market Road, Chelmsford. Alternatively, documents can be posted to you upon request.
Objections: Anyone who wishes to make an objection to the proposed scheme should send the grounds for their objection to the above address or via e-mail to TrafficRegulation.Order@essexhighways.org quoting reference TRAF/8758 by 06 August 2026
(Ashwells Road, Pilgrims Hatch) (Temporary Prohibition of Traffic) Order 2026
Notice is hereby given that the Essex County Council intends, not less than seven days from the date of this notice, to make the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order: To temporarily close that length of Ashwells Road, Pilgrims Hatch in the Borough of Brentwood, from a point approximately 225m north west of its junction with Well Lane for a distance of approximately 270m in a north westerly direction. The closure is scheduled to commence on 11th August 2026 for 3 days, or where stated on a valid permit (EC30080853119 – UK Power Networks).
The scheduled dates may vary for these works with appropriate signs showing and/or displayed on one.network. The closure is required for the safety of the public and workforce while cabling works are undertaken by UK Power Networks.
An alternative route is available via Ongar Road and vice versa (with access only into Ashwells Road and Crow Green Road).
The Order will come into effect on 22nd July 2026 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
(Church Lane, Doddinghurst) (Temporary Prohibition of Traffic) Order 2026
Notice is hereby given that the Essex County Council intends, not less than seven days from the date of this notice, to make the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order: To temporarily close that length of Church Lane, Doddinghurst in the Borough of Brentwood, from a point approximately 15m north east of its junction with Warren Lane for a distance of approximately 45m in a north easterly direction. The closure is scheduled to commence on 11th August 2026 for 4 days, or where stated on a valid permit (MX06162593JB – Affinity Water).
The scheduled
dates may vary for these works with appropriate signs showing and/or displayed on one.network.
The closure is required for the safety of the public and workforce while new connection works are undertaken by Affinity Water.
An alternative route is available via Church Lane, Place Farm Lane, Blackmore Road, Stocks Lane and vice versa.
The Order will come into effect on 22nd July 2026 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
(Docklands Avenue, Ingatestone)
(Temporary Prohibition of Traffic) Order 2026
Notice is hereby given that the Essex County Council intends, not less than seven days from the date o this notice, to make the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order: To temporarily close that length of Docklands Avenue, Ingatestone in the Borough of Brentwood, from its junction with High Street for a distance of approximately 60m in a south easterly direction.
The closure is scheduled to commence on 3rd August 2026 for 5 days, or where stated on a valid permit (EN013348999 – Essex And Suffolk Water).
The scheduled dates may vary for these works with appropriate signs showing and/or displayed on one.network.
The closure is required for the safety of the public and workforce while interim to permanent reinstatement works are undertaken by Essex And Suffolk Water.
An alternative route is available via Docklands Avenue, Pine Close, Park Drive, High Street and vice versa.
The Order will come into effect on 22nd July 2026 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
(Little Warley Hall Lane, Little Warley) (Temporary Prohibition of Traffic) Order 2026
Notice is hereby given that the Essex County Council intends, not less than seven days from the date of this notice, to make the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order: To temporarily close that length of Little Warley Hall Lane, Little Warley in the Borough of Brentwood, from a point approximately 235m south of its junction with Magpie Lane for a distance of approximately 545m in a south westerly direction.
The closure is scheduled to commence on 12th August 2026 for 2 days, or where stated on a valid permit (BC411001WGSNMR6J – Openreach Ltd). The scheduled dates may vary for these works with appropriate signs showing and/or displayed on one.network.
The closure is required for the safety of the public and workforce while pole replacement works are undertaken by Openreach Ltd.
An alternative route is available via (Northbound) Little Warley Hall Lane, Magpie Lane, Bird Lane, Warley Street, A127, Little Warley Hall Lane or (Southbound) Little Warley Hall Lane, A127, Childerditch Lane, Magpie Lane and Little Warley Hall Lane.
The Order will come into effect on 22nd July 2026 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
(Various Roads, Ingatestone) (Temporary Introduction of a Clearway) Order 2026
Notice is hereby given that the Essex County Council intends, not less than seven days from the date of this notice, to make the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order: To temporarily introduce a ‘No Waiting’ No Loading and No Stopping’ restriction in those lengths of road in the Borough of Brentwood as per the schedule.
Schedule
| Road Name | Extents | Permit number |
|---|---|---|
| The Furlongs, Ingatestone |
From a point approximately 120m north west of its junction with High Street for a distance of approximately 255m in a north westerly then north easterly direction | EP02228427829 |
| Pemberton Avenue, Ingatestone |
From its junction with Fryerning Lane for a distance of approximately 320m in a south westerly direction |
EP02295328315 |
| Fryerning Lane, Ingatestone |
From its junction with Pemberton Avenue to its junction with Haslers Court a distance of approximately 500m | EP02218549805 |
| Willows Green, Ingatestone |
From its junction with Fryerning Lane for a distance of approximately 250m in a north easterly direction |
EP02209257981 |
“The Essex County Council (Brentwood Borough) (Prohibition of Waiting, Loading and Stopping) and (On Street Parking Places) (Civil Enforcement Area) Consolidation Order 2019” will be temporarily amended to include the temporary ‘No Waiting, No Loading and No Stopping at Any Time” restriction and suspend any existing parking and waiting restrictions on the above length of road only. All other restrictions and exemptions contained in the aforementioned Order and Amendments to that Order shall remain in force.
The clearways are scheduled to commence on 11th August 2026 for 21 days (08:00-17:00 Monday to Friday only), or where stated on a valid permit. The scheduled dates may vary for these works with appropriate signs showing and/or displayed on one.network. The clearways are required for the safety of≈the public and workforce while portakabin deliveries works are undertaken by Portakabin.
The Order will come into effect on 22nd July 2026 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
(Various Roads, Borough of Brentwood) (Temporary Prohibition of Traffic & Temporary Introduction of a Clearway) (No.6) Order 2026
Notice is hereby given that the Essex County Council intends, not less than seven days from the date of this notice to make the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order:
6. To temporarily close that length of road in the Borough of Brentwood as specified in the schedule.
7. A temporary ‘No Waiting, No Loading and No Stopping’ restriction will be introduced on both sides of carriageway on that length of road as specified in the schedule. Signs will be installed indicating when the No Waiting, No Loading and No Stopping restriction will be in force.
“The Essex County Council (Brentwood Borough) (Prohibition of Waiting, Loading and Stopping) and (On Street Parking Places) (Civil Enforcement Area) Consolidation Order 2019” will be temporarily amended to include the temporary ‘No Waiting, No Loading and No Stopping at Any Time’ restriction and suspend any existing parking and waiting restrictions on the above length of road only. All other restrictions and exemptions contained in the aforementioned Order and Amendments to that Order shall remain in force.
The works being undertaken will take place within an 18-month period from 22nd July 2026 exact dates will be specified on one.network. The roads will be closed to facilitate each phase of works and then re-opened to the public. Access will be maintained for emergency services. Residents will be informed of the dates of each phase via letter / leaflet drop and advanced warning signs on the roads.
For all enquiries, please contact our Contact Centre on 0345 603 7631.
The Order will come into effect on 22nd July 2026 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
Schedule
| Road | Description | Alternative Route |
|---|---|---|
| Weald Road, South Weald/Brentwood |
From the junction with Chequers Road tothe junction with Park Road a distance ofapproximately 4580m | Chequers Road, Coxtie Green Road, A128, Western Avenue, Weald Road and vice versa |
(Various Roads, Borough of Brentwood)
(Temporary introduction of 30 MPH Speed Restriction) & Temporary Introduction of a Clearway) (No.7) Order 2026
Notice is hereby given that the Essex County Council intends, not less than seven days from the date of this notice to make the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order:
1. To temporarily introduce a 30mph speed restriction in that length of road in the Borough of Brentwood as specified in the schedule.
2. A temporary ‘No Waiting, No Loading and No Stopping’ restriction will be introduced on both sides of carriageway on that length of road as specified in the schedule. Signs will be installed indicating when the No Waiting, No Loading and No Stopping restriction will be in force.
“The Essex County Council (Brentwood Borough) (Prohibition of Waiting, Loading and Stopping) and (On Street Parking Places) (Civil Enforcement Area) Consolidation Order 2019” will be temporarily amended to include the temporary ‘No Waiting, No Loading and No Stopping at Any Time’ restriction and suspend any existing parking and waiting restrictions on the above length of road only. All other restrictions and exemptions contained in the aforementioned Order and Amendments to that Order shall remain in force.
The works being undertaken will take place within an 18-month period from 22nd July 2026 exact dates will be specified on one.network.
The roads will be closed to facilitate each phase of works and then re-opened to the public. Access will be maintained for emergency services.
Residents will be informed of the dates of each phase via letter / leaflet drop and advanced warning signs on the roads.
For all enquiries, please contact our Contact Centre on 0345 603 7631.
The Order will come into effect on 22nd July 2026 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
Schedule
| Road | Description |
|---|---|
| A128 Tilbury Road, East Horndon |
From Halfway House Roundabout to Thurrock border a distance of approximately 1475m |
(Church Lane, Doddinghurst)
(Temporary Prohibition of Traffic) Order 2026
Notice is hereby given that the Essex County Council has made the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order: To temporarily close that length of Church Lane, Doddinghurst in the Borough of Brentwood, from a point approximately 10m south west of its junction with Dagwood Lane for a distance of approximately 40m in a south westerly direction.
The closure is scheduled to commence on 28th July 2026 for 3 days, or where stated on a valid permit (MX04410265449 – Affinity Water Ltd). The scheduled dates may vary for these works with appropriate signs showing and/or displayed on one.network.
The closure is required for the safety of the public and workforce while chamber replacement works are undertaken by Affinity Water Ltd.
An alternative route is available via Church Lane, Stocks Lane, Blackmore Road, Place Farm Lane and vice versa.
The Order came into effect on 8th July 2026 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
(Little Warley Hall Lane, West Horndon)
(Temporary Prohibition of Traffic) Order 2026
Notice is hereby given that the Essex County Council has made the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order: To temporarily close that length of Little Warley Hall Lane, West Horndon in the Borough of Brentwood, from a point approximately 1000m south of the junction with A127 for a distance of approximately 20m in a southerly direction.
The closure is scheduled to commence on 28th July 2026 for 1 night (23:00-06:00) or where stated on a valid permit (KL701FSS2-18-0-280726 – Network Rail Infrastructure Ltd).
The scheduled dates may vary for these works with appropriate signs showing and/ or displayed on one.network. The closure is required for the safety of the public and workforce while retaining wall inspection works are undertaken by Network Rail Infrastructure Ltd.
An alternative route is available via (Northbound) Little Warley Hall Lane, Magpie Lane, Bird Lane, Warley Street, A127, Little Warley Hall Lane or (Southbound) Little Warley Hall Lane, A127, Childerditch Lane, Magpie Lane and Little Warley Hall Lane.
The Order came into effect on 8th July 2026 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
DATED: 15TH JULY 2026
Need to publish a public notice?