Ranelagh Road, Southall - Temporary Traffic Restrictions For New Cable Ducts And Inspection Chambers
What is happening?
LONDON BOROUGH OF EALING
NOTICE OF MAKING OF TEMPORARY TRAFFIC
ORDER FOR PLANNED WORKS
AFFECTING: RANELAGH ROAD, SOUTHALL.
Ealing Council has made the following temporary traffic order under sections 14(1)(a) of the Road Traffic Regulation Act 1984:
Title of order
This order can be referred to as: Temporary traffic order for planned works – TT 5229 Ranelagh Road, Southall – 2026.
Reason for order
This order is needed to allow for works taking place on or near the road. These works involve JSM Construction laying new cable ducts and inspection chambers.
Effect of order
1. Waiting, loading and unloading restrictions will be applied on Ranelagh Road and these works will be carried out in 4 phases as outlined in page 2 “Schedule to this order”.
2. From 6th July 2026 to 22nd July 2026, the waiting, loading or unloading restrictions will apply at the locations specified in the Schedule to this order and will be enforced with the issue of a Penalty Charge Notice.
3. These restrictions and prohibitions will apply at the specified locations where appropriate “no-waiting cones” are placed along the length of the affected public highway.
4. While the temporary restrictions are in place, displaced vehicles must comply with any traffic management measures.
5. This Order does not apply to:
Date order will come into force. 6th July 2026
Maximum duration of order
This order will expire on 5th January 2028 or, on completion of the works, which is expected to be 22nd July 2026, whichever is sooner.
Date: 7th July 2026
Satnam Sahota
Chief Highways Engineer
| Schedule | Date | Location |
|---|---|---|
| Phase 1 | 06/07/2026 to 11/07/2026 |
Both kerb lines from the junction with Beaconsfield Road to 85 Ranelagh Road |
| Phase 2 | 10/07/2026 to 15/07/2026 |
Both kerb lines from 85 to 51 Ranelagh Road. |
| Phase 3 | 14/07/2026 to 19/07/2026 |
Both kerb lines from outside 51 to 21 Ranelagh Road. |
| Phase 4 | 17/07/2026 to 22/07/2026 |
Both kerb lines from 21 Ranelagh Road to its junction with Uxbridge Road. |