Ealing - Multiple Road Traffic Notices
What is happening?
LONDON BOROUGH OF EALING
NOTICE OF INTENT TO CREATE A TEMPORARY TRAFFIC ORDER FOR
PLANNED WORKS AFFECTING: VARIOUS ROADS, ACTON.
Ealing Council intends to make the following temporary traffic order under section 14(1)(a) of the Road Traffic Regulation Act 1984:
Title of order
This order can be referred to as: Temporary traffic order for planned works - TT 5193 Various Roads, Acton - 2026.
Reason for order
This order is needed to allow for works taking place on or near the road.
These works involve Clancy Group on behalf of (SSE) Scottish & Southern Energy laying new power cables.
Effect of order
1. This order will implement temporary road closures and will be carried out in works phases as outlined in page 2 “Schedule to this order”.
2. The following temporary restrictions on vehicle movements will take effect from 13th June 2026.
(a) No entry into the fully closed section(s) where scheduled restrictions are implemented.
(b) No waiting, loading, or unloading on either side of the carriageway within the fully closed section.
3. The above temporary restrictions and prohibitions will only apply at specified locations where appropriate traffic signs are provided and displayed in accordance with Chapter 8 of the Traffic Signs Manual.
4. While the temporary restrictions are in place, displaced vehicles should follow the diversions displayed in place to reach their destinations and comply with any traffic management measures.
5. This Order does not apply to:
(a) anything done at the direction of a police officer in uniform or a police community support officer (PCSO).
(b) any vehicle being used for police, fire brigade or ambulance.
Date order will come into force.
13th June 2026
Maximum duration of order
This order will expire on 12th January 2028 or, on completion of the works, which is expected to be 27th November 2026, whichever is sooner. These works are indicative and subject to weather and unforeseen works delays.
Date: 11th June 2026
Satnam Sahota
Chief Highways Engineer
Schedule
| Date | Location | |
|---|---|---|
| Phase 1 | 13/07/2026 to 31/07/2026 | This phase will close St Dunstans Avenue from its junction with Friary Road to Western Avenue junction. Access only will be maintained. |
| Phase 2 | 27/07/2026 to 21/08/2026 | Friary Road will be closed between its junctions with St Dunstans Avenue to Friary Way junction. |
| Phase 3 | 17/08/2026 to 28/08/2026 | Crane Avenue will be closed at its junction with Baldwyn Gardens. Access only will be provided. |
| Phase 4 | 17/08/2026 to 11/09/2026 | Baldwyn Gardens will be closed at its junction with Crane Avenue to Grafton Road. |
| Phase 5 | 7/09/2026 to 25/09/2026 | Grafton Road will be closed at its junction with Baldwyn Gardens to junction of Messaline Avenue. |
| Phase 6 | 19/10/2026 to 16/11/2026 | Grasmere Avenue will be closed between its junctions with Messaline Avenue through to Eastern extremity of the Westbourne Avenue junction. |
| Phase 7 | 2/11/2026 to 27/11/2026 | Westbourne Avenue will be closed from its junction with Grasmere Avenue to the junction with Emanuel Avenue. |