Norfolk - Multiple Temporary Road Closures & Parking/Loading Restrictions Due To Various Works
What is happening?
NORFOLK COUNTY COUNCIL
Temporary Traffic Regulation Orders 2026 - Road Traffic Regulation Act, 1984
Norfolk County Council in exercise of its powers under Section 14(1) of the Road Traffic Regulation Act 1984 ("RTRA 1984"), hereby give notice that:
i) They Propose To Make Temporary Traffic Regulation Orders in respect of the following roads:
Aylsham – C228 Heydon Road from 1260m west of its junction with Aylsham Road for 160m westwards.
To facilitate electrical pole repair works between 09:00 and 16:00 on 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: Aylsham Road, New Road, The Street, Oulton Street (Blickling, Cawston, Oulton, Aylsham).
The works promoter is UK Power Networks.
Beighton – Kittles Road from its junction with Southwood Road for 475m north-eastwards.
To facilitate pole testing works between 09:00 and 15:30 on 18th May 2026 (may continue until 29th June 2026).
Alternative route is via: Southwood Road, Grove Road, Porters Road, Reedham Road, Ash Tree Road (Cantley, Limpenhoe and Southwood, Freethorpe, Beighton).
The works promoter is BT.
Bodham – C308 Church Road from 300m west of its junction with Manor House Road for 220m westwards.
To facilitate overhead cabling works between 09:00 and 15:30 on 18th May 2026 (may continue until 29th June 2026).
Alternative route is via: C308 Church Road/Rectory Road/Osier Lane, C309 Long Lane, C528 The Street, A148 Cromer Road, C308 Selbrigg Road (High Kelling, West Beckham, Holt, Bodham).
The works promoter is BT.
Cley-Next-The-Sea – Old Womans Lane from 440m south of its junction with A149 Coast Road for 70m southwards.
To facilitate tree cutting works between 08:00 and 18:00 on 21st May 2026 (may continue until 2nd July 2026).
Alternative route is via: Old Womans Lane, A149 Coast Road/High Street, C306 Holt Road/Newgate Green.
The works promoter is UK Power Networks.
Cromer – A) Bond Street from 30m south of its junction with A149 Church Street for 30m southwards and;
B) Bond Street from its junction with A149 Church Street to its junction with A149 Mount Street to facilitate new electrical service connection works.
The Road A will be temporarily closed and; Road B shall be temporarily subject to the suspension of a one-way system (northbound) to allow vehicles to travel in both a southbound and northbound direction, and traffic over the Road B shall be temporarily prohibited to park, stop, load, and/or unload including in pre-existing parking bays from 18th to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: A149 Mount Street/Louden Road, A148 Prince of Wales Road, A149 Hamilton Road/Church Street.
The works promoter is UK Power Networks.
Frettenham – Well Green from its junction with School Road for 35m westwards.
To facilitate drainage works from 18th to 29th May 2026 (may continue until 10th July 2026).
Alternative route is via: Post Office Road, Mill Road, School Road.
The works promoter is Norfolk County Council.
Gorleston-On-Sea – Cliff Avenue from its junction with Marine Parade for 55m north-westwards.
To facilitate new electrical service connection works from 18th to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: Marine Parade, Park Road, Victoria Road, Cliff Avenue.
The works promoter is UK Power Networks.
Gorleston-On-Sea – Avondale Road from its junction with Victoria Road for 285m eastwards.
To facilitate carriageway repair works from 19th to 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: Victoria Road, Clarence Road, Park Road, Marine Parade (Gorleston-on-Sea, Great Yarmouth).
The works promoter is Norfolk County Council.
Great Yarmouth –A) Standard Road from its junction with Apsley Road for 30m eastwards and;
B) Standard Road from 30m east of its junction with Apsley Road to its junction with Marine Parade.
To facilitate new electrical connection works.
Road A will be temporarily closed (except for pedestrian access) and;
Road B shall be temporarily subject to the suspension of the one-way system (westbound) to allow vehicles to travel in both an easterly and westerly direction from 21st to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: Apsley Road, Trafalgar Road, Marine Parade.
The works promoter is UK Power Networks.
Itteringham – C287 Church Road from 275m northeast of its junction with C287 The Street for 130m north-eastwards.
To facilitate telegraph pole tests between 09:30 and 15:30 on 21st May 2026 (may continue until 2nd July 2026).
Alternative route is via: C287 Church Road/Oulton Road, C593 Blickling Road/Aylsham Road, B1149 Link Road Roundabout, C288 Matlaske Road, C287 Itteringham Road (Matlaske, Little Barningham, Plumstead, Corpusty and Saxthorpe, Itteringham, Wickmere, Oulton).
The works promoter is BT.
Itteringham – C287 The Common from its junction with Wolterton Road to its junction with C287 Oulton Road.
To facilitate carriageway patching works from 18th to 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: The Street, C287 Church Road/Itteringham Road, C624 Mannington Hall Road, C288 Matlaske Road/Saxthorpe Road, C593 Aylsham Road/C593 Blickling Road, C287 Oulton Road.
The works promoter is Norfolk County Council.
Mundesley – A) Mundesley Footpath 17 from its joining with Meadow Drive for 80m eastwards and;
B) Mundesley Footpath 20 from its joining with Mundesley Footpath 17 to its joining with Beckmeadow Way.
To facilitate gas main upgrade works from 18th to 29th May 2026 (may continue until 10th July 2026).
Alternative route is via: N/A.
The works promoter is Cadent.
North Walsham – U19071 School Road from its junction with U19076 King Street for 410m north-westwards.
To facilitate duct installation and cabling works from 19th May to 2nd June 2026 (may continue until 14th July 2026).
Alternative route is via: School Road, School Lane, Norwich Road, Horning Road, Chapel Road, Church Road.
The works promoter is CityFibre Metro Networks Ltd.
Oulton – U57268 Hall Road from its junction with Church Lane for 430m northwards.
To facilitate pole testing works between 09:30 and 15:30 on 21st May 2026 (may continue until 2nd July 2026).
Alternative route is via: Church Lane, Spinks Lane, B1149 Holt Road/Norwich Road/Link Road/Link Road Roundabout, Aylsham Road, Blickling Road, Hall Road.
The works promoter is BT.
Smallburgh – U11475 Knowles Lane from 90m west of its junction with C399 Church Road to its junction with U19167 Workhouse Road.
To facilitate pole testing works on 21st May 2026 (may continue until 2nd July 2026).
Alternative route is via: Knowles Lane, Church Road, A149 Yarmouth Road, Union Road, Workhouse Road.
The works promoter is Openreach.
Sprowston – A1151 Wroxham Road from its junction with Blenheim Road to its junction with Blue Boar Lane.
To facilitate surface dressing works between 19:00 and 23:00 from 18th to 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: A1151 Wroxham Road, A1042 Mousehold Lane/Heartsease Lane/St Williams Way/Saint Williams Way/Ring Road/Pound Lane/Yarmouth Road, A1194 Broadland Way/Poppy Way, A1270 Broadland Northway, A1151 Wroxham Road (Rackheath, Thorpe St. Andrew, Postwick with Witton, Great and Little Plumstead, Sprowston).
The works promoter is Norfolk County Council.
NB: works are anticipated to take place between 19:00 and 23:00 on 18th May 2026, with 19th and 20th May as contingency dates if required.
Strumpshaw – Norwich Road from 50m west of its junction with Buckenham Road for 755m eastwards.
To facilitate duct installations from 21st May to 11th June 2026 (may continue until 11th December 2026).
Alternative route is via: Long Lane, Strumpshaw Road, Blofield Road, Brundall Road, Stocks Lane, Yarmouth Road, Danesbower Lane, Lingwood Road, Chapel Road, Norwich Road (Brundall, Strumpshaw, Lingwood and Burlingham, Blofield).
The works promoter is CityFibre Metro Networks Ltd.
Swafield With Bradfield – C295 Trunch Road from 638m north of its junction with B1145 The Street for 300m northwards.
To facilitate overhead cabling works between 09:30 and 15:30 on 18th May 2026 (may continue until 29th June 2026).
Alternative route is via: C295 North Walsham Road/Gimingham Road, C289 Mundesley Road/Trunch Road, B1145 Knapton Road/Knapton Green/The Street (Trunch, Mundesley, Gimingham, Knapton, Swafield with Bradfield).
The works promoter is BT.
Swannington With Alderford And Little Witchingham – C260 Alderford Common from 175m southeast of its junction with Hall Road for 130m south-eastwards.
To facilitate pole testing works between 09:30 and 15:30 on 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: Reepham Road, Norwich Road, Church Road, Easton Way, Buxton Road, B1149 Holt Road/Brewery Lane, A1270 Broadland Northway, Reepham Road (Felthorpe, Brandiston, Hevingham, Horsford, Stratton Strawless, Drayton, Booton, Cawston, Haveringland, Attlebridge, Swannington with Alderford and Little Witchingham).
The works promoter is BT.
Swanton Novers –A) C637 The Street from its junction with C704 Holt Road for 115m southwards,
B) C637 The Street from 3m south of its junction with The Croft for 14m southwards, and;
C) U14199 The Croft from its junction with C637 The Street for 15m westwards.
To facilitate electrical cable laying works. The Roads A and C will be temporarily closed (except for pedestrian access) and traffic (constituting any class of vehicle) over Road B shall be temporarily prohibited to park, stop, load, and/or unload in the parking bay on the westside of the carriageway from 18th to 29th May 2026 (may continue until 10th July 2026).
Alternative route is via: C637 The Street, C704 Holt Road, B1110 Dereham Road (Melton Constable, Swanton Novers).
The works promoter is UK Power Networks.
Taverham And Drayton – A1067 Fakenham Road from its junction with Cypress Close to its junction with Drayton Grove.
To facilitate carriageway surface dressing works from 16th May to 2nd June 2026 (may continue until 14th July 2026).
Alternative route is via: A1067 Fakenham Road, A1270 Broadland Northway, A140 Holt Road/Cromer Road/Boundary Road, A1067 Drayton High Road/Fakenham Road (Horsham St. Faith and Newton St. Faith, Attlebridge, Hellesdon, Horsford, Taverham, Drayton).
The works promoter is Norfolk County Council.
NB: Please note the works will be carried out in 2 phases:
Phase 1 is anticipated to be closed between 06:00 on 16th May and 13:00 on 17th May 2026 (Contingency days of between 06:00 on 23rd May and 13:00 on 24th May 2026 and between 06:00 on 30th May and 13:00 on 31st May 2026).
Phase 2 is anticipated to be closed between 19:00 on 28th May and 00:00 on 29th May 2026 (Contingency days of between 19:00 on 29th May and 00:00 on 30th May 2026 and between 19:00 on 1st June and 00:00 on 2nd June 2026).
Trunch – Brick Kiln Road from its junction with C289 Trunch Road for 45m south-westwards.
To facilitate gas pipe repair works from 19th to 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: C289 Trunch Road/Mundesley Road, C295 Gimingham Road, Brick Kiln Road (Gimingham, Trunch).
The works promoter is Cadent.
Weston Longville – C172 Morton Lane from its junction with B1535 Weston Hall Road for 600m eastwards.
To facilitate overhead cabling works between 09:00 and 15:00 on 21st May 2026 (may continue until 2nd July 2026).
Alternative route is via: B1535 Weston Hall Road, Rectory Road, Honingham Road, Woodforde Close, Church Street, Marl Hill Road, Marl Hill, Morton Lane (Morton on the Hill, Weston Longville).
The works promoter is CityFibre Metro Networks Ltd.
Wood Dalling –A) C228 Heydon Road from its junction with Crabgate Lane to its junction with Front Road and;
B) U57014 Prospect Lane from its junction with Heydon Road for 92m northwards.
To facilitate pole tests between 09:30 and 15:30 on 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via:
Road A) Heydon Road, Briston Road, Wood Dalling Road, Reepham Road, Hall Street, Church Street, B1354 Holt Road/Norwich Road/Briston Road, B1149 Aylsham Road/Link Road Roundabout/Link Road/Norwich Road/Holt Road, Heydon Road.
Road B) Prospect Lane, Front Road. (Thurning, Salle, Corpusty and Saxthorpe, Heydon, Wood Dalling, Cawston, Briston, Oulton).
The works promoter is BT.
Wood Dalling – A) C477 Corpusty Road from its junction with Crabgate Lane to its junction with Blackwater Lane and;
B) U57159 Blackwater Lane from its junction with Corpusty Road to its junction with Heath Road.
To facilitate carriageway patching works from 18th to 19th May 2026 (may continue until 30th June 2026).
Alternative route is via:
Road A) C477 Corpusty Road/Wood Dalling Road/Horseshoe Lane/Valley Road, B1149 Holt Road, C228 Heydon Road, C267 Briston Road, C477 Crow Hill;
Road B) U14258 Heath Road, U14256 Town Close Lane (Salle, Corpusty and Saxthorpe, Heydon, Wood Dalling, Cawston, Oulton).
The works promoter is Norfolk County Council.
The team dealing with enquiries at Norfolk County Council is North Streetworks.
Aldeby – U76289 Church Lane from its junction with U76434 Burrows Green for 45m northwards.
To facilitate verge repair works from 20th to 21st May 2026 (may continue until 2nd July 2026).
Alternative route is via: Burrows Green, Church Road, Station Road, Church Lane.
The works promoter is Norfolk County Council.
Aldeby – U76394 Lily Lane from its junction with U76366 Common Road for 258m westwards.
To facilitate fibre network installation works from 18th to 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: St Marys Road, Common Road.
The works promoter is CityFibre Holdings Ltd.
Alpington – U76373 Reeders Lane from its junction with U76372 Burgate Lane for 50m southwards.
To facilitate stop tap replacement works from 19th to 21st May 2026 (may continue until 2nd July 2026).
Alternative route is via: Wheel Road, Nichols Road, Church Meadow Lane, Green Lane, Reeders Lane.
The works promoter is Anglian Water.
Chedgrave – U76342 Big Back Lane from its junction with C554 Norwich Road for 782m northwards.
To facilitate housing development construction works, the Road will be temporarily subject to the imposition of a one-way system (northbound) and the effect of this is that vehicles will only be allowed to travel in a northwards direction from 1st June 2026 to 31st May 2030.
Alternative route is via: N/A.
The works promoter is Norfolk County Council and this Order is made under s14(1) and s15(2) of the RTRA 1984.
Chedgrave – U76332 Rectory Lane from its junction with C202 Langley Road to its junction with C554 Norwich Road.
To facilitate housing development construction works, the Road will be temporarily subject to the imposition of a one-way system (westbound) and the effect of this is that vehicles will only be allowed to travel in a westwards direction from 1st June 2026 to 31st May 2030.
Alternative route is via: N/A.
The works promoter is Norfolk County Council and this Order is made under s14(1) and s15(2) of the RTRA 1984.
Chedgrave – A) C384 Hardley Road/Lower Hardley Road from its junction with C202 Langley Road to its junction with U76331 Cross Stone Road;
B) U76331 Cross Stone Road from its junction with C384 Lower Hardley Road to its junction with C384 Hardley Road.
To facilitate fibre network installation works from 19th to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: Langley Road, Salthire Road, Langley Street, Hardley Road.
The works promoter is CityFibre Metro Networks Ltd.
NB: Access to be given to Church Close and Pitts Lane throughout the closure with Gatemen on site to facilitate.
Costessey – U78082 The Croft from its junction with C162 The Street for 188m south-eastwards.
To facilitate gas leak repairs from 19th to 26th May 2026 (may continue until 7th July 2026).
Alternative route is via: The Croft, Folgate Lane, The Street.
The works promoter is Cadent.
Great Ellingham – U33106 Stalland Common from its junction with C136 Hingham Road to its junction with U33107 Old Runway Lane.
To facilitate carriageway repairs from 18th to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: C136 Hingham Road, B1077 Attleborough Road, U33114 Deopham Road, U33106 Bush Green/Stalland Common and vice versa.
The works promoter is Norfolk County Council.
Holme Hale – Lower Road from 290m east of its junction with Cook Road for 50m eastwards.
To facilitate stop tap replacement works from 18th to 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: C117 Cook Road/School Road, C116 Bradenham Road.
The works promoter is Anglian Water.
Kirby Bedon – A) C202 Kirby Road from 60m west of its junction with U78106 Sallow Lane for 220m eastwards and;
B) U78106 Sallow Lane from its junction with C202 Kirby Road for 110m southwards.
To facilitate new electrical service connection works from 18th to 24th May 2026 (may continue until 5th July 2026).
Alternative route is via: Kirby Road, A146 Loddon Road, Norwich Road, Langley Road, Staithe Road, Langley Green, Ferry Road, The Street, Claxton Corner, Lower Road, New Inn Hill, Rookery Hill, Bramerton Lane, Rockland Road (Framingham Pigot, Claxton, Rockland St. Mary, Chedgrave, Trowse with Newton, Kirby Bedon, Yelverton, Langley with Hardley, Hellington, Bramerton, Ashby St. Mary, Thurton, Caistor St. Edmund and Bixley, Hoveton, Carleton St. Peter).
The works promoter is UK Power Networks.
Kirkstead – U76380 Church Road from its junction with C203 Brooke Road for 170m southwards.
To facilitate installation of new fibre network from 18th to 21st May 2026 (may continue until 2nd July 2026).
Alternative route is via: Brooke Road, Hunstead Lane, The Street, B1332 Norwich Road, Church Road (Kirstead, Brooke).
The works promoter is CityFibre Holdings Limited.
Long Stratton – A140 Norwich Road from its junction with B1527 Hempnall Road Roundabout to its junction with A140 Long Stratton Bypass.
To facilitate carriageway resurfacing between 20:00 and 06:00 from 18th to 23rd May 2026 (may continue until 4th July 2026).
Alternative route is via: A140 Ipswich Road/Norwich Road/Ipswich Road, A47 Trunk Road, A146 Loddon Road/Norwich Road/Loddon Bypass/Beccles Road/Norwich Road, A143 Yarmouth Road/Kirby Cane Bypass/Broome Bypass/Bungay Road/Old Railway Road/Bungay Road/Harleston Bypass/Brockdish/Needham Bypass/Scole Road/Bungay Road/Lower Street/Bungay Road/Scole Stuston Bypass, A140 Scole Bypass/Dickleburgh Bypass/Ipswich Road/Long Stratton Bypass (Brome and Oakley, Stockton, Framingham Pigot, Brockdish, Pulham Market, Swainsthorpe, Redenhall with Harleston, Bungay, Earsham, Ellingham, Ditchingham, Stuston, Chedgrave, Trowse with Newton, Kirby Bedon, Denton, Dickleburgh and Rushall, Yelverton, Keswick and Intwood, Broome, Stoke Holy Cross, Needham, Hellington, Hales, Scole, Tivetshall, Wacton, Gillingham, Tasburgh, Saxlingham Nethergate, Ashby St. Mary, Loddon, Long Stratton, Sisland, Thurton, Caistor St. Edmund and Bixley, Wortwell, Kirby Cane, Alburgh, Burston and Shimpling, Hoveton, Newton Flotman).
The works promoter is Norfolk County Council.
Old Buckenham – U33135 Road from Stacksford Lane to Hargham Road from 405m south of its junction with C138 Hargham Road for 30m southwards.
To facilitate new water connection installation works from 20th to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: U33135 Road From Stacksford Lane To Hargham Road, U33042 Stacksford Lane, C138 Hargham Road, U33135 Road From Stacksford Lane To Hargham Road.
The works promoter is Anglian Water.
Old Buckenham – Attleborough Road from 240m north of Bunns Bank for 900m southwards.
To facilitate installation of a substation from 18th to 21st May 2026 (may continue until 2nd July 2026).
Alternative route is via: N/A.
The works promoter is UK Power Networks.
Old Buckenham – Hargham Road from 500m east of its junction with Church Road for 140m eastwards.
To facilitate pole testing works between 09:30 and 15:30 on 19th May 2026 (may continue until 30th June 2026).
Alternative route is via: Clockwise: C138 Road from Snetterton to Old Buckenham, A11 Northbound, C572 London Road/High Street, B1077 Exchange Street/Queens Square/Church Street/Norwich Road/Surrogate Street/Station Road/Buckenham Road/Attleborough Road/The Green, C138 The Green.
Anti Clockwise: C138 The Green, B1077 The Green/Attleborough Road/Buckenham Road/Station Road/Surrogate Street/Connaught Road, C572 High Street/London Road, A11 Southbound, C138 Road from Snetterton to Old Buckenham (Quidenham, Old Buckenham, Attleborough).
The works promoter is BT.
Oxborough – Oxborough Restricted Byway 8 from its joining with C44 Swaffham Road for 295m northwards.
To facilitate installation of a new water main on 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: N/A.
The works promoter is Anglian Water.
Oxborough – A) Oxborough Restricted Byway 2 from its junction with Eastmoor Road for 1430m north-eastwards and;
B) Oxborough FP1 from its junction with Eastmoor Road for 1170m north-eastwards and;
C) Oxborough FP3 from its junction with Eastmoor Road for 565m northwards.
To facilitate installation of a new water main from 21st to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: N/A.
The works promoter is Anglian Water.
Spooner Row – C140 Bunwell Road from its junction with U73094 Slutshole Lane for 150m northwards.
To facilitate new electrical cabling from 18th to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: Bunwell Road, Station Road, London Road, Norwich Road, Silver Street, Besthorpe Road (Morley, Besthorpe, Attleborough, Spooner Row).
The works promoter is UK Power Networks.
Spooner Row – U76006 Wattlefield Road from its junction with C594 Silfield Road for 80m south-westwards.
To facilitate surface dressing preparation works from 18th to 19th May 2026 (may continue until 30th June 2026).
Alternative route is via: Silfield Road, Wattlefield Road, Broom Road, Traice Road, New Road, Wymondham Road (Wymondham, Ashwellthorpe and Fundenhall, Tacolneston, Spooner Row).
The works promoter is Norfolk County Council.
Whinburgh And Westfield – U35024 Shop Street from 120m west of its junction with B1135 Dereham Road for 40m westwards.
To facilitate passing bay installations from 18th to 31st May 2026 (may continue until 12th July 2026).
Alternative route is via: B1135 Dereham Road, U35024 Church Road/Shop Street and vice versa.
The works promoter is MW Surfacing.
Wymondham – U78310 Orchard Way from its junction with U78301 Back Lane for 510m north-eastwards.
To facilitate footway maintenance from 18th May to 3rd August 2026 (may continue until 3rd February 2027).
Alternative route is via: Orchard Way, Rothbury Road, Pople Street, Back Lane.
The works promoter is Norfolk County Council.
The team dealing with enquiries at Norfolk County Council is South Streetworks.
Barton Bendish – Barton Bendish Footpath 8 from its joining with C45 Stoke Ferry Road for 1330m northwards.
To facilitate installation of a new water main on 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: N/A.
The works promoter is Anglian Water.
Barton Bendish – Stoke Ferry Road from 530m west of its junction with Eastmoor Road for 120m westwards.
To facilitate pipe laying works, the Road will be temporarily subject to a 30mph speed restriction from 18th May to 4th September 2026 (may continue until 17th November 2027).
Alternative route is via: N/A.
The works promoter is Anglian Water.
Boughton – Oxborough Road from 795m east of its junction with Chapel Road for 285m eastwards.
To facilitate pipe laying works from 18th May to 28th August 2026 (may continue until 17th November 2027).
Alternative route is via: N/A.
The works promoter is Anglian Water.
Burnham Thorpe – A) U22174 Creake Road from its junction with U22244 Blacksmith’s Lane to its junction with C96 Rectory Lane and;
B) U22245 Garner’s Row from its junction with U22174 Creake Road to its junction with C97 Walsingham Road.
To facilitate trench repairs and ducting works from 18th to 29th May 2026 may continue until 10th July 2026).
Alternative route is via: Burnham Thorpe Road, Burnham Road, Creake Road, Joan Shorts Lane, Walsingham Road (Burnham Market, North Creake, Burnham Thorpe).
The works promoter is Highways Assurance.
Crimplesham – C543 Main Road from its junction with U21293 Market Lane for 100m north-westwards.
To facilitate underground cabling works between 09:30 and 15:30 on 18th May 2026 (may continue until 29th June 2026).
Alternative route is via: Main Road, Lynn Road, Downham Road (Stradsett, West Dereham, Crimplesham).
The works promoter is BT.
Marham – C47 The Street from 10m north of its junction with U21520 Villebois Road for 30m northwards.
To facilitate a new water connection from 18th to 20th May 2026 (may continue until 1st July 2026).
Alternative route is via: The Street, Burnthouse Drove, Squires Hill.
The works promoter is Anglian Water.
Northwold And Whittington – C59 High Street from 70m north of its junction with U21341 Hall Lane for 50m north-westwards.
To facilitate stop tap replacements from 22nd to 28th May 2026 (may continue until 9th July 2026).
Alternative route is via: High Street, Little London Road, Little London Lane, Foulden Road, Thetford Road, West End.
The works promoter is Anglian Water.
Runcton Holme – U21304 Common Road at its intersection with the level crossing for 20m eastwards and 20m westwards.
To facilitate track repairs from 20th to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: Common Road, Silt Road, Bells Drove, Station Road, School Road, Downham Road, Watlington Road (Watlington, Runcton Holme).
The works promoter is Network Rail.
Stradsett And Crimplesham – A1122 Downham Road from its junction with U21290 New Road for 2615m eastwards.
To facilitate surface dressing and lining works between 19:00 and 05:00 from 19th May to 17th June 2026 (may continue until 17th December 2026).
Alternative route is via: Lynn Road, Stoke Road, A10 Stow Bardolph Bypass/Downham-Wimbotsham Bypass, Bexwell Road. (Watlington, Stow Bardolph, Stradsett, Downham Market, Wimbotsham, Ryston, Crimplesham, Wormegay, Tottenhill, Shouldham Thorpe, Runcton Holme).
The works promoter is Norfolk County Council.
The anticipated phases are:
Phase 1: stud removal between 19:00 and 05:00 from 19th to 23rd May 2026.
Phase 2: Main dressing between 19:00 and 05:00 on 10th June 2026, Phase 3: Lining and studs between 19:00 and 05:00 from 16th to 17th June 2026.
Upwell – U21019 Baptist Road from its junction with C766 School Road for 40m eastwards.
To facilitate fire hydrant repairs from 18th to 22nd May 2026 (may continue until 3rd July 2026).
Alternative route is via: Baptist Road, New Bridge Road, School Road.
The works promoter is Anglian Water.
The team dealing with enquiries at Norfolk County Council is West Streetworks.
ii) They Have Made Temporary Traffic Regulation Orders in respect of the following roads:
Aldborough And Thurgarton – C293 The Street from its junction with C293 Thurgarton Road to its junction with U14392 School Road.
To facilitate carriageway patching works from 11th to 12th May 2026 (may continue until 23rd June 2026).
Alternative route is via: The Street, Sustead Road, Mill Road, The Common, A140 Norwich Road, Aldborough Road, Church Road, Town Green, Thwaite Hill, Thwaite Road, The Green, Thurgarton Road (Aldborough & Thurgarton, Alby with Thwaite, Hanworth).
The works promoter is Norfolk County Council.
Blakeney – High Street from 75m south of its junction with The Quay for 35m southwards.
To facilitate access to substation and electrical works from 11th to 22nd May (may continue until 3rd July 2026).
Alternative route is via: High Street, Back Lane, A149 New Road.
The works promoter is UK Power Distribution Ltd.
NB: These works will take place in phases.
Phase 1 from 11th to 13th May 2026.
Phase 2 from 18th to 22nd May 2026.
Caister-On-Sea – A149 Caister Bypass (Southbound Carriageway Only) from its junction with A149 Norwich Road to its junction with A149 Caister Road.
To facilitate surface dressing from 11th May to 13th June 2026 (may continue until 13th December 2026).
Alternative route is via A149 Norwich Road, A1064 Norwich Road/Main Road/The Heath/Main Road/Old Road/Acle Link Road, A47, A149 Acle New Road/North Quay/Lawn Avenue/Caister Road.
The works promoter is Norfolk County Council.
NB: these works will take place in phases.
Phase 1 between 19:00 and 05:00 from 11th to 16th May 2026.
Phase 2 between 19:00 and 05:00 from 1st to 4th June 2026 and;
Phase 3 between 19:00 and 05:00 from 9th to 13th June 2026.
Fakenham – Petticoat Lane/Fakenham FP13 from 23m north of its junction with Norwich Road for 15m northwards.
To facilitate electrical service connection works on 15th May 2026 (may continue until 26th June 2026).
Alternative route is via: Fakenham Footpath 13, Holt Road, Norwich Road, Petticoat Lane.
The works promoter is UK Power Networks.
Great Yarmouth – Footpath fronting 257 to 311 Lowestoft Road from its junction with Kennedy Avenue for 400m southwards.
To facilitate highway drainage remedial works between 20:00 and 06:00 from 11th to 15th May 2026 (may continue until 26th June 2026).
Alternative route is via: Lowestoft Road, A47 Gorleston on Sea from Dalling to J B1370 Including Roundabout (Gorleston-on-Sea, Great Yarmouth).
The works promoter is National Highways.
Hellesdon – U51524 Holt Road Layby from its junction with A140 Holt Road for 150m northwards.
To facilitate construction works in conjunction with the PEA039 Yellow Pedalway from 11th May to 22nd July 2026 (may continue until 22nd January 2027).
Alternative route is via: A140 Holt Road.
The works promoter is Norfolk County Council.
Langham – C598 Holt Road from its junction with C314 North Street for 65m eastwards. To facilitate electrical supply installation works from 11th to 14th May 2026 (may continue until 25th June 2026).
Alternative route is via: C314 North Street, B1156 Langham Road, C328 Wiveton Road, C598 Holt Road.
The works promoter is UK Power Networks.
Ludham – U19064 How Hill Road from 645m southwest of its junction with U19675 Sharpe Street for 50m south-westwards.
To facilitate frame and cover replacement works from 11th to 13th May 2026 (may continue until 24th June 2026).
Alternative route is via: How Hill Road, Sharp Street, Ludham Road, Catfield Road, High Street, A1062 Norwich Road, School Lane, Whitegates, School Road, How Hill Road (Ludham, Catfield).
The works promoter is Anglian Water.
Ormesby St. Margaret With Scratby – C460 Station Road from its junction with U69811 Claymore Gardens for 30m westwards.
To facilitate relaying of a lead pipe works from 11th to 15th May 2026 (may continue until 26th June 2026).
Alternative route is via: Station Road, Scratby Road, Yarmouth Road, Cromer Road, Station Road.
The works promoter is Essex and Suffolk Water.
Somerton – A) C640 Martham Road from its junction with U69359 Sandy Lane for 30m north-eastwards and;
B) U69359 Sandy Lane from its junction with C640 Martham Road for 10m northwards. To facilitate new water connection works from 13th to 15th May 2026 (may continue until 26th June 2026).
Alternative route is via:
Road A: Somerton Road, White Street, Hemsby Road, Martham Road, Collis Lane, Dark Lane, Horsey Road, Martham Road.
Road B: Sandy Lane, Cottage Road, Martham Road. (Hemsby, Somerton, Martham).
The works promoter is Anglian Water.
South Walsham – C875 The Street from 45m east of its junction with C428 Burlingham Road for 60m eastwards.
To facilitate new sewer connection works from 11th to 15th May 2026 (may continue until 26th June 2026).
Alternative route is via: The Street Acle Road, South Walsham Road, Bridewell Lane, Old Road, A1064 Main Road, B1152 Main Road, Heath Road, Mill Road, A149 High Road/Yarmouth Road, A1062 Station Road/Ludham Road/Yarmouth Road/Norwich Road/Johnson Street/Ludham Bridge/Upper Street/Norwich Road/Ropes Hill/Horning Road, A1151 Stalham Road/Norwich Road, B1140 Salhouse Road/Bell Lane/Low Road/Salhouse Road, Panxworth Road (Ludham, Salhouse, Woodbastwick, Ashby with Oby, Hoveton, Repps with Bastwick, Fleggburgh, Potter Heigham, Wroxham, Horning, Upton with Fishley, Acle, South Walsham).
The works promoter is Bells and Bowers Drainage Specialists Ltd.
Stalham – A149 Yarmouth Road from 200m northwest of its junction with Moor Road for 800m north-westwards owing to barrier repair works from 27th April to 18th May 2026 (previously 14th to 27th April 2026) (may continue until 18th November 2026).
Alternative route is via: N/A.
The works promoter is Anglian Water.
Suffield – C298 The Street from its junction with C298 Long Lane to its junction with C288 White Post Road.
To facilitate carriageway repair works from 13th to 14th May 2026 (may continue until 25th June 2026).
Alternative route is via: The Street, White Post Road, A140 Norwich Road/Cromer Road, High Noon Road, Long Lane (Erpingham, Alby with Thwaite, Suffield, Colby, Hanworth).
The works promoter is Norfolk County Council.
The team dealing with enquiries at Norfolk County Council is North Streetworks.