Norfolk, Multiple Temporary Road Closures & Traffic Restrictions Due To Various Works
What is happening?
NORFOLK COUNTY COUNCIL
Temporary Traffic Regulation Orders 2026 - Road Traffic Regulation Act, 1984
Norfolk County Council in exercise of its powers under Section 14(1) of the Road Traffic Regulation Act 1984, hereby give notice that:
i) THEY PROPOSE TO MAKE Temporary Traffic Regulation Orders in respect of the following roads:
Aylsham – C556 Millgate/Gasthouse Hill from its junction with Sir Williams Lane for 553m northwards.
To facilitate carriageway repairs and surface dressing prep works from 26th to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: Banningham Road, Drabblegate, A140 Aylsham Bypass, Norwich Road, Red Lion Street, White Hart Street, Gasthouse Hill.
The works promoter is Norfolk County Council.
Barsham – Farm Road from its junction with C325 Barsham Road to its junction with C586 Rakenham Road.
To facilitate carriageway repair works on 24th March 2026 (may continue until 5th May 2026).
Alternative route is via: C586 Rakenham Road, Gray’s Lane, C325 Barsham Road.
The works promoter is Norfolk County Council.
Cantley, Limpenhoe And Southwood – Church Road from 35m northwest of Hobbs Lane for 35m north-westwards.
To facilitate rebuilding of a water chamber from 27th to 31st March 2026 (may continue until 12th May 2026).
Alternative route is via: Cantley Road, Limpenhoe Road, Hall Road, Cove Meadow Road, Grove Road, The Common, Chapelfield, The Green, Reedham Road, Freethorpe Road, Sandy Lane (Cantley, Limpenhoe and Southwood, Freethorpe, Reedham).
The works promoter is Anglian Water.
Cley-Next-The-Sea – Town Yard from its junction with Church Lane to its junction with C306 Holt Road.
To facilitate carriageway patching works from 23rd to 24th March 2026 (may continue until 5th May 2026).
Alternative route is via: Church Lane, Newgate Green, C306 Holt Road.
The works promoter is Norfolk County Council.
Edgefield – B1149 Holt Road from its junction with U143247 Hempstead Road for 360m north-westwards.
To facilitate new electric connection works between 08:00 and 18:00 on 24th March 2026 (may continue until 5th May 2026).
Alternative route is via: B1149 Holt Road, A148 Norwich Road, B1110 Thornage Road/The Street/Dereham Road, B1354 Briston Road/Fakenham Road, B1149 Edgefield Road/The Green (Briningham, Thornage, Corpusty and Saxthorpe, Brinton, Melton Constable, Holt, Briston, Stody, Edgefield).
The works promoter is UK Power Networks.
Felbrigg – Metton Road from its junction with Hall Road to its junction with B1436 Cromer Road.
To facilitate carriageway patching for surface dressing preparation works from 23rd to 25th March 2026 (may continue until 6th May 2026).
Alternative route is via: Dick Bucks Burrows, B1436 Cromer Road, Hall Road (Cromer, Felbrigg).
The works promoter is Norfolk County Council.
Great Witchingham – U557017 The Street from 70m west of its junction with Ladys Row for 30m westwards.
To facilitate common pipe repair works from 23rd to 25th March 2026 (may continue until 6th May 2026).
Alternative route is via: The Street, A1067 Fakenham Road.
The works promoter is Anglian Water.
Gunthorpe With Bale – Bale Road from its junction with A148 Holt Road to its junction with Bulfer Lane.
To facilitate carriageway repair works on 25th March 2026 (may continue until 6th May 2026).
Alternative route is via: A148 Holt Road, Hall Lane, Bale Road.
The works promoter is Norfolk County Council.
Horning – C398 Letherings Lane from its junction with A1062 Ropes Hill to its junction with C398 Long Lane.
To facilitate telecommunication pole works on 23rd March 2026 (may continue until 4th May 2026).
Alternative route is via: Long Lane, Neatishead Road, A1062 Ropes Hill.
The works promoter is CityFibre Metro Networks.
Knapton – Footpath 7 from its joining with C421 Hall Lane for 215m north-eastwards.
To facilitate levelling of the footpath from 25th to 27th March 2026 (may continue until 6th May 2026).
Alternative route is via: N/A.
The works promoter is Norfolk County Council.
Mundesley – Links Road from its junction with Heath Lane for 348m north-westwards.
To facilitate carriageway repairs on 26th March 2026 (may continue until 7th May 2026).
Alternative route is via: Mundesley Byway Open To All Traffic 24, Gimingham Byway Open To All Traffic 17, Trunch Byway Open To All Traffic 14, Trunch Road, High Street, Back Street, Station Road, Links Road (Trunch, Mundesley, Gimingham).
The works promoter is Norfolk County Council.
Lingwood And Burlingham – Lodge Road from its junction with Elm Road for 430m north-eastwards.
To facilitate cabling works for network infrastructure from 23rd to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: Station Road, Norwich Road, High Road, Coxhill Road, Acle Road (Beighton, Lingwood and Burlingham).
The works promoter is CityFibre Metro Networks Limited.
Reepham – U57043 Back Street from its junction with Church Street for 70m westwards.
To facilitate provision of a pole and duct laying from 25th to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: Church Street, Church Hill, Market Place, School Road.
The works promoter is BT.
Sheringham – Cremer Street from its junction with Salisbury Road for 50m northwards.
To facilitate carriageway repairs between 07:30 and 20:00 on 24th March 2026 (may continue until 5th May 2026).
Alternative route is via: Cremer Street, Co-operative Street, Beeston Road, Salisbury Road, New Road, Station Road, High Street.
The works promoter is Anglian Water.
Sheringham – Church Street from its junction with Station Approach to its junction with The Boulevard.
To facilitate carriageway and footway repairs on the 23rd March 2026 (may continue until 4th May 2026).
Alternative route is via: Church Street, High Street, C507 Wyndham Street/Beeston Road, A149 Cromer Road.
The works promoter is Norfolk County Council.
South Walsham – C875 The Street from 45m east of C428 Burlingham Road for 60m eastwards.
To facilitate the installation of a new sewer connection from 23rd to 29th March 2026 (may continue until 10th May 2026).
Alternative route is via: The Street, Acle Road, South Walsham Road, Bridewell Lane, Old Road, A1064 Main Road, B1152 Main Road, Heath Road, Mill Road, A149 High Road/Yarmouth Road, A1062 Station Road/Ludham Road/Yarmouth Road/Norwich Road/Johnson Street/Ludham Bridge/Upper Street/Norwich Road/Ropes Hill/Horning Road, A1151 Stalham Road/Norwich Road, B1140 Salhouse Road/Bell Lane/Low Road/Salhouse Road, Panxworth Road (South Walsham, Ludham, Salhouse, Woodbastwick, Ashby with Oby, Hoveton, Repps with Bastwick, Fleggburgh, Potter Heigham, Wroxham, Horning, Upton with Fishley, Acle).
The works promoter is Bells and Brooks Drainage Specialists.
Taverham – U51157 Orchard Bank from its junction with Taverham Road to its junction with Sylvan Way.
To facilitate carriageway repairs and surface dressing preparation from 24th to 25th March 2026 (may continue until 6th May 2026).
Alternative route is via: U51157 Orchard Bank, Shakespeare Way, Taverham Road (Drayton, Taverham).
The works promoter is Norfolk County Council.
Walshingham – C318 Thursford Road from its junction with C317 Snoring Road to its junction with 319 Thursford Road.
To facilitate carriageway repairs on the 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: C318 Thursford Road, C319 Dildas Lane, C317 The Street, C317 Walsingham Road, C317 Snoring Road (Great Snoring, Walsingham). The works promoter is Norfolk County Council.
The team dealing with enquiries at Norfolk County Council is North Streetworks.
Brettenham And Kilverstone – Brettenham Road from its junction with Kilverstone Road for 50m southwards, from 24th to 26th March 2026 (may continue until 7th May 2026).
Alternative route is via: C148 Kilverstone Road/Brettenham Road, A1075 Norwich Road, A1066 Hurth Way/Thetford Road (Kilverstone, Brettenham, Thetford).
The works promoter is Anglian Water.
Carleton Rode – C139 Bunwell Street from its junction with C351 Hall Road for 780m eastwards.
To facilitate carriageway repairs from 23rd to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: Bunwell Street, The Turnpike, Uggate Street, Mile Road (Bunwell, Carleton Rode).
The works promoter is Norfolk County Council.
Dereham – C214 Theatre Street from its junction with U30118 Trinity Close to its junction with U30109 Ems Close.
To facilitate a stop gap replacement from 23rd to 25th March 2026 (may continue until 6th May 2026).
Alternative route is via: Westwards – U30113 Kings Road, C553 Neatherd Road/Wellington Road, C214 Theatre Street. Eastwards – C214 Theatre Street, U30115 St Nicholas Street, C553 Wellington Road/Neatherd Road, U30113 Kings Road.
The works promoter is Anglian Water.
Flordon – C180 The Street from its junction with U78032 Long Lane for 480m westwards.
To facilitate a water meter exchange between 08:30 and 15:00 on 24th March 2026 (may continue until 5th May 2026).
Alternative route is via: The Street, Norwich Road, Flordon Road, Main Road, Mulbarton Road, Ipswich Road, Station Road (Flordon, Swaffham, Mulbarton, Bracon Ash, Keswick and Intwood, Stoke Holy Cross, Swardeston, Caister St. Edmund and Bixley, Newton Flotman).
The works promoter is Anglian Water.
Fransham – U35187 Lyons Green from its junction with C126 Hulver Street to its junction with U35308 Haggards Way.
To facilitate carriageway patching from 27th to 30th March 2026 (may continue until 11th May 2026).
Alternative route is via: C126 Hulver Street/Bradenham Lane, B5300 Haggards Way and vice versa (Bradenham, Fransham).
The works promoter is Norfolk County Council.
Great Melton – C169 Market Lane from its junction with U78005 Hall Road for 650m eastwards.
To facilitate cabling works from 23rd March to 3rd April 2026 (may continue until 15th May 2026).
Alternative route is via: Hall Road, Market Lane, Rectory Lane, Watton Road, Landlow Lane, Mill Road, Burdock Lane (Bawburgh, Little Melton, Great Melton).
The works promoter is BT.
Great Melton – C185 Hethersett Road from its junction with C169 High Green for 1120m eastwards.
To facilitate cabling works from 23rd March to 10th April 2026 (may continue until 22nd May 2026).
Alternative route is via: Hethersett Road, Great Melton Road, Queens Road, Norwich Road, Ketts Oak, Norwich Common, Tuttles Lane East, Tuttles Lane West, Melton Road, High Green (Great Melton, Hethersett, Wymondham).
The works promoter is BT.
Horningtoft And Brisley – B1146 Fakenham Road from 300m south of its junction with 3R0509 Horningtoft Footpath 5 for 1600m northwards.
To facilitate the repair of a gas leak, the road will be temporarily subject to a 40mph speed restriction from 23rd March to 3rd April 2026 (may continue until 15th May 2026). Alternative route is via: N/A.
The works promoter is Norfolk County Council.
Litcham – C123 Church Street from its junction with B1145 Front Street for 40m southwards.
To facilitate a gully replacement between 09:00 and 15:00 on 23rd March 2026 (may continue until 4th May 2026).
Alternative route is via: C123 Church Street, B1145 Mileham Road/Litcham Road/The Street/Stanfied Road, B1146 Fakenham Road, C222 Litcham Road/Dereham Road/Litcham Road (Longham, Gressenhall, Litcham, Beetley, Beeston with Bittering, Bilsby, Stanfield, Mileham).
The works promoter is Norfolk County Council.
Lyng – C198 Heath Road from 100m south-west of its junction with U31046 Bakery Lane for 100m south-westwards.
To facilitate 5278 works including new footways and gully replacements from 23rd to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: C198, C123 Heath Road, C212 Rectory Road/Mill Street, C216 Lime Kiln Road, A1067 Main Road, C198 Lyng Road/The Street/The Common and vice versa (Sparham, Bylaugh, Lyng, Elsing).
The works promoter is Strand Developments.
Marlingford And Colton – C162 Barford Road from its junction with C174A Colton Road for 30m eastwards.
To facilitate water pipe repairs from 23rd to 25th March 2026 (may continue until 6th May 2026).
Alternative route is via: Barford Road, Church Road.
The works promoter is Anglian Water.
Raynham (And Tittleshall) –
A) C234 Pollywiggle Lane from its junction with A1065 Swaffham Road to its junction with 1R1063 Raynham RB6.
B) C234 Road from Fakenham Road to South Raynham from its junction with 1R1063 Raynham RB6 to its junction with C123 Fakenham Road.
To facilitate carriageway repairs from 24th to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: A1065 Swaffham Road/Gravelpit Hill, C123 Fakenham Road and vice versa (Tittleshall, Pudding Norton, Raynham, Colkirk, Hempton, Dunton).
The works promoter is Norfolk County Council.
Redenhall With Harleston – C565 Spriketts Lane from 320m east of its junction with B1116 Shorford Road for 60m westwards.
To facilitate the upgrading of a gas main from 25th March to 9th April 2026 (may continue until 21st May 2026).
Alternative route is via: C565 Spriketts Lane, Mendham Lane, A143 Harleston Bypass, High Road, Needham Road, Shorford Road (Redenhall with Harleston, Needham).
The works promoter is Cadent.
Shotesham – C203 Heath Road/Honeyspot Lane from its junction with U78033 Baxter Lane to its junction with C371 Woodton Road.
To facilitate installation of new fibre network from 23rd March to 1st April 2026 (may continue until 13th May 2026).
Alternative route is via: Brooke Road, Chapel Lane, Shotesham Road, B1332 Bungay Road, B1332 Norwich Road, High Green, Access for Backwood Lane from The Green up to the points of closure (Poringland, Brooke, Shotesham, Howe).
The works promoter is Norfolk County Council.
Swaffham – Sporle Road from 150m north-east of its junction with Orford Road for 300m north-eastwards.
To facilitate pole testing and tree cutting between 09:30 and 15:30 on 23rd March 2026 (may continue until 4th May 2026).
Alternative route is via: C123 Sporle Road, 33356 New Sporle Road, C562 Norwich Road, A47, C123 Sporle Road.
The works promoter is BT.
Wymondham – U78013 Silfield Street from its junction with U78288 Burnthouse Lane for 50m westwards.
To facilitate pole replacement from 25th to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: Silfield Street, Compass Road, Burnthouse Lane.
The works promoter is BT.
The team dealing with enquiries at Norfolk County Council is South Streetworks.
Burnham Market
– U22168 Friars Lane from its junction with B1155 Overy Road for 40m northwards.To facilitate tree felling works between 07:00 and 23:59 on 23rd March 2026 (may continue until 4th May 2026).
Alternative route is via: Friars Lane, Bellmays Lane, Overy Road (Burnham Norton, Burnham Market).
The works promoter is Norfolk County Council.
Congham – B1153 Grimston Road from its junction with C761 St Andrews Lane for 312m southwards.
To facilitate HRA patching works from 23rd to 26th March 2026 (may continue until 7th May 2026).
Alternative route is via: Grimston Road, Station Road, Lynn Road, Hillington Road, Queen Elizabeth Way, Gayton Road, Congham Road (Hillington, Roydon, Congham, Castle Rising, Gayton, Leziate, Bawsey, Grimston).
The works promoter is Norfolk County Council.
Downham Market – A1122 Western Bypass from its junction with A1122–S2326 St Johns Roundabout for 452m northwards.
To facilitate carriageway resurfacing from 23rd to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: Station Road, Bridge Road, Downham Road, Outwell Road, Well Creek Road, Wisbech Road, Elm High Road, Wisbech Bypass, A47 From J B198 East Of Wisbech To J A1101/A1122, Walton Highway Bypass A47, A47 From Roundabout At Tilney All Saints To J B198 East Of Wisbech W, A47 From J B198 East Of Wisbech To Roundabout At Tilney All Saints E, Walpole Highway Bypass A47, Terrington St John Bypass A47, Tilney All Saints Bypass A47, Pullover Road, A47 From J A17 To Roundabout At Tilney All Saints, A47 Trunk Road From The Pullover Roundabout To The Hardwick Roundabout, A47 From J A17 To J A148 W, A47 Through J A148 W, A47 J A148 Join W, A47 Through J A148 E, A47 From J A10/A149 Larger Roundabout To J A148 W, A47 From J A148 To J A10/A149 Larger Roundabout E, A47 J A10/A149 Overbridge E, West Winch Road, Main Road, Lynn Road, Stow Bardolph Bypass A10, Downham – Wimbotsham Bypass A10, Downham Eastern Bypass A10, Southern Bypass A1122 (Watlington, Downham West, Tilney All Saints, Stow Bardolph, Nordelph, Denver, Terrington St. John, Walsoken, Downham Market, Walpole Highway, North Runcton, Elm, Emneth, Wimbotsham, West Walton, Ryston, West Winch, Tilney St. Lawrence, Wormegay, Outwell, Tottenhill, Runcton Holme).
The works promoter is Norfolk County Council.
Wiggenhall St. Germans – C8 High Road from 460m west of its junction with U21426 Low Road for 400m southwards.
To facilitate cabling works between 09:30 and 15:30 from the 23rd to 24th March 2026 (may continue until 5th May 2026).
Alternative route is via: High Road, Saddlebow Road, A47 Through J A148 W, A47 Trunk Road From The Pullover Roundabout To The Hardwick Roundabout, A47 From J A17 To J A148 W, A47 From J A17 To Roundabout At Tilney All Saints, Pullover Road, A47 From J B198 East Of Wisbech To Roundabout At Tilney All Saints E, Tilney All Saints Bypass A47, A47 From Roundabout At Tilney All Saints To J B198 East Of Wisbech W, Islington Road, The Avenue, Sluice Road, School Road, Lynn Road (Tilney All Saints, Wiggenhall St. Germans, Tilney St. Lawrence).
The works promoter is BT.
The team dealing with enquiries at Norfolk County Council is West Streetworks.
ii)
THEY HAVE MADE Temporary Traffic Regulation Orders in respect of the following roads:Barsham – C325 Burnham Lane from its junction with B1105 Wells Road to its junction with B1355 Burnham Market Road.
To facilitate carriageway repairs from 18th to 19th March 2026 (may continue until 30th April 2026).
Alternative route is via: B1355 Creake Road/Burnham Market Road, C326 Barsham Road, B1105 Wells Road (Barsham, Sculthorpe).
The works promoter is Norfolk County Council.
Edgefield – U14272 Ramsgate Street from its junction with U14272 Chapel Hill for 150m north-westwards.
To facilitate electrical pole and cable replacements between 16:00 and 23:59 on the 19th March 2026 (may continue until 30th April 2026).
Alternative route is via: Chapel Hill, B1149 Norwich Road, Church Lane, Briston Road, Ramsgate Street.
The works promoter is UK Power Networks.
Great Yarmouth – Osborne Avenue from its junction with Barnard Crescent for 145m southwards.
To facilitate water pipe works from 16th to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: Barnard Crescent, Caister Road, Hamilton Road, Osborne Avenue.
The works promoter is Essex and Suffolk Water.
Holt – C311 Kelling Road from 630m north-east of its junction with C488 Cromer Road for 30m north-eastwards.
To facilitate a new water pipe connection from 19th to 20th March 2026 (may continue until 1st May 2026).
Alternative route is via: C311 Kelling Road, C488 Cromer Road, A148 Cromer Road, C308 Bridge Road (High Kelling, Kelling, Holt).
The works promoter is Anglian Water.
Knapton – B1145 Mundesley Road from its junction with C421 Hall Lane to its junction with C426 Knapton Road.
To facilitate telegraph pole testing between 15:30 and 23:59 on 20th March 2026 (may continue until 1st May 2026).
Alternative route is via: B1145 Mundesley Road/Knapton Road, C635 Water Lane/C635 Paston Road, B1159 Bacton Road/Coast Road/Beach Road/Walkcott Road/Stalham Road/Stalham Road, B1149 Wayford Road/Norwich Road, Yarmouth Road, North Walsham By-pass, B1145 The Street/North Walsham Road/Knapton Green (East Ruston, Stalham, Dilham, Swafield, Paston, Smallburgh, Bacton, Brumstead, Mundesley, Worstead, Walcott, North Walsham, Knapton).
The works promoter is BT.
Neatishead – U19071 Common Road from its junction with U19119 Church Lane to its junction with U19076 Kings Street.
To facilitate broadband network infrastructure upgrades from 18th March to 2nd April 2026 (may continue until 14th May 2026).
Alternative route is via: School Road, Horning Road, Irstead St Axa Birds Lane, Common Road (Horning, Neatishead).
The works promoter is CityFibre Metro Networks.
Northrepps – Hall Road from its junction with C291 New Road for 56m northwards.
To facilitate carriageway patching from 19th to 20th March 2026 (may continue until 1st May 2026).
Alternative route is via: Hall Road, C292 Northrepps Road/Cromer Road/Nut Lane, C291 School Lane/New Road.
The works promoter is Norfolk County Council.
Sculthorpe – C424 New Road from its junction with A148 Lynn Road for 1500m north-westwards.
To facilitate carriageway repairs on the 17th March 2026 (may continue until 28th April 2026).
Alternative route is via: C424 New Road, B1355 Creake Road, B1355 Burnham Market Road, C326 Moor Lane, C326 The Street, A148 Lynn Road (Barsham, Sculthorpe).
The works promoter is Norfolk County Council.
Somerton –
A) U69358 Cottage Road from its junction with C640 Martham Road to its junction with U69490 Common Road and;
B) U69490 Common Road from its junction with U69358 Cottage Road to 80m southwest of its junction with C643 Horsey Road.
To facilitate replacement of overhead power lines and poles on 20th March 2026 (may continue until 1st May 2026).
Alternative route is via: Cottage Road, Sandy Lane, Martham Road, Horsey Road, Common Road.
The works promoter is UK Power Networks.
Strumpshaw – Buckenham Road from its junction with Norwich Road for 370m south-eastwards.
To facilitate duct installation and cabling works from 16th to 27th March 2026 (may continue until 8th May 2026).
Alternative route is via: Norwich Road, Long Lane, Stone Road, Low Road, Wood Lane, Hassingham Road, Strumpshaw Road, Buckenham Road (Strumpshaw, Lingwood and Burlingham).
The works promoter is CityFibre Metro Networks Ltd.
Walsingham – C586 Fakenham Road from 150m southwest from its junction with U14092 Church Street for 50m south-westwards.
To facilitate replacement chamber, cover and frame works from 18th to 20th March 2026 (may continue until 1st May 2026).
Alternative route is via: C586 Fakenham Road/High Street, C597 Common Place/Holt Road, C317 Snoring Road, Walsingham Road, C478 Barsham Road/Water Lane (Great Snoring, Barsham, Walsingham).
The works promoter is Anglian Water.
Wells-Next-The-Sea – Theatre Road from its junction with Blackhorse Yard for 30m eastwards.
To facilitate stopgap replacement works from 17th to 19th March 2026 (may continue until 30th April 2026).
Alternative route is via: Theatre Road, Clubbs Lane, Mill Road, Park Road.
The works promoter is Anglian Water.
The team dealing with enquiries at Norfolk County Council is North Streetworks.
Bergh Apton –
C373 White Heath Road from 316m northeast of its junction with C377 School Road for 130m northwards.To facilitate pole safety check works between 09:30 and 15:30 on 17th March 2026 (may continue until 28th April 2026).
Alternative route is via: White Heath Road, School Road, Church Road, The Street, Cokes Road, White Heath Road (Thurton, Bergh Apton).
The works promoter is Openreach.
Carleton St. Peter – C381 Ferry Road from its junction with C202 The Street for 16m metres southwards.
To facilitate the installation of a new fibre network for BDUK from 16th to 20th March 2026 (may continue until 1st May 2026).
Alternative route is via: The Street, Claxton Corner, Church Lane, Claxton Church Road, Hall Road, Church Road, Chapel Road, Chapel Lane, Spong Lane, Ferry Road (Claxton, Rockland St. Mary, Ashby St. Mary, Carleton St. Peter).
The works promoter is CityFibre Metro Networks Ltd.
Chedgrave – U76332 Rectory Lane from 35m west of its junction with C202 Langley Road for 40m westwards.
To facilitate gas service disconnection and excavation works from 16th to 20th March 2026 (may continue until 1st May 2026).
Alternative route is via: Rectory Lane, Langley Road, Norwich Road.
The works promoter is Cadent.
Easton – C168 Marlingford Road from its junction with U78085 Hall Road for 489m southwards.
To facilitate highways civil engineering works from 16th March to 20th July 2026 (may continue until 15th September 2027).
Alternative route is via: Marlingford Road, Easton Road, Bawburgh Road, Long Lane, Dereham Road (Bawburgh, Marlingford and Colton, Costessey, Easton).
The works promoter is Core Highways.
Griston – C546 Thompson Road from 275m east of its junction with A1075 Thetford Road for 150m eastwards.
To facilitate carriageway surfacing between 20:00 and 06:00 from 17th to 19th March 2026 (may continue until 30th April 2026).
Alternative route is via: C546 Thompson Road, A1075 Thetford Road/Memorial Way, B1108 Norwich Road, B1077 Caston Road/Carbrooke Road, C546 Attleborough Road/The Street/Griston Road, 33192 Thompson Road and vice versa (Carbrooke, Watton, Caston, Griston).
The works promoter is Norfolk County Council.
Hoe And Worthing – B1110 Holt Road from 435m south of its junction with U35128 Green Lane for 40m southwards.
To facilitate tree trimming between 09:00 and 15:00 on 15th March 2026 (may continue until 30th April 2026).
Alternative route is via: B1110 Holt Road/Dereham Road, B1145 Brisley Road/Elmham Road/Church Street/Starfield Road, B1146 Fakenham Road and vice versa (Gressenhall, North Elmham, Beetley, Brisley, Stanfield, Hoe and Worthing).
The works promoter is UK Power Networks.
Kenninghall – Lopham Road from 250m north of its junction with Heath Road for 140m northwards. To facilitate pole testing between 09:30 and 15:30 on 16th March 2026 (may continue until 27th April 2026).
Alternative route is via: A1066 The Street/Thetford Road/Diss Road, B1111 The Street/Manor Road, C142 Kenninghall Road/Garboldisham Road (South Lopham, Kenninghall, Garboldisham, North Lopham, Harling).
The works promoter is BT.
Kenninghall – Banham Road from 730m north-east of its junction with Back Lane for 100m north-eastwards.
To facilitate pole testing between 09:30 and 15:30 on 19th March 2026 (may continue until 30th April 2026).
Alternative route is via: C142 Kenninghall Road, B1111 Manor Road/The Street, A1066 Diss Road/Thetford Road/The Street/Diss Road/Low Road/High Road/Stanley Road, B1077 Denmark Street/Shelfang Road/Diss Road/Church Road/Winfarthing Road/Mill Road/The Street/Short Green/Mile Road/Haugh Road, C142 Dam Brigg (New Buckenham, Roydon, Diss, South Lopham, Old Buckenham, Garboldisham, Heywood, Winfarthing, Shelfanger, Banham, North Lopham, Bressingham).
The works promoter is BT.
Lyng – C198 Heath Road from its junction with Hill Paddocks for 30m eastwards to facilitate electrical connections from 17th to 25th March 2026 (may continue until 6th May 2026).
Alternative route is via: C198, C123 Heath Road, C212 Rectory Road/Mill Street, C216 Lime Kiln Road, A1067 Main Road, C198 Lyng Road/The Street/The Common and vice versa (Sparham, Bylaugh, Lyng, Elsing).
The works promoter is UK Power Networks.
Mattishall – U35014 Garvestone Road from 347m north of its junction with U35139 Old Hall Road for 75m northwards.
To facilitate the replacement of a parapet fence between 07:30 and 16:00 on 18th March 2026 (may continue until 29th April 2026).
Alternative route is via: U35139 Old Hall Road, C200 Dereham Road, U35013 Welgate, U35013 Thynnes Lane, U35014 Garvestone Road and vice versa.
The works promoter is Norfolk County Council.
Old Buckenham – U33042 Stackyard Lane from 540m west of its junction with Mill Road for 50m westwards.
To facilitate replacement of tap from 16th to 18th March 2026 (may continue until 29th April 2026).
Alternative route is via: U33042 Stackford Lane, C138 Hargham Road, U33135 Road From Stacksford Lane To Hargham Road, U33042 Stacksford Lane.
The works promoter is Anglian Water.
Riddlesworth – A1066 Thetford Road from 55m west of its junction with The Street for 750m westwards.
To facilitate electricity supply installation works, the Road will be temporarily subject to a 30mph speed restriction between 08:00 on 16th March and 18:00 on 18th March 2026 (may continue until 29th April 2026).
Alternative route is via: N/A.
The works promoter is UK Power Networks.
Scole – C468 Low Road from 262m south of its junction with A143 Bungay Road for 180m southwards.
To facilitate BT pole testing between 09:30 and 15:30 on 16th March 2026 (may continue until 27th April 2026).
Alternative route is via: A143 Bungay Road/Scole Stuston Bypass, A140 Roman Road, B1118 Lower Oakley, C468 Low Road.
The works promoter is BT.
Starston – C877 The Street from 13m north of its junction with C201 Railway Hill for 50m northwards.
To facilitate brickwork repair works from 16th to 25th March 2026 (may continue until 6th May 2026).
Alternative route is via: Harleston Road, The Street, Rushall Road, Harleston Road, Pulham Road, Station Road, Mill Lane, The Street, Harleston Road, Pulham Road, The Street.
The works promoter is Norfolk County Council.
Stockton –
A) A146 Norwich Road from its junction with C392 Bungay Road for 115m southwards. B) C392 Bungay Road from its junction with A146 Norwich Road for 150m westwards. C) U76301 Rectory Road from its junction with A146 Norwich Road for 140m eastwards.
To facilitate new supply works for telecoms infrastructure from 16th to 29th March 2026 (may continue until 10th May 2026).
Alternative routes are via:
A: A146 Norwich Road, A146 Beccles Road/Loddon Bypass/Loddon Road, B1332 Bungay Road/The Street/Norwich Road, A143 Yarmouth Road/Broome Bypass/A143 Yarmouth Road.
B: School Road, Loddon Road, Walsh Road, A146 Beccles Road/Norwich Road.
C: Raveningham Road, A143 Yarmouth Road, A146 Norwich Road (Framingham Pigot, Poringland, Kirstead, Ellingham, Framingham Earl, Ditchingham, Chedgrave, Kirby Bedon, Brooke, Yelverton, Broome, Hellington, Hales, Woodton, Gillingham, Ashby St. Mary, Loddon, Sisland, Thurton, Caister St. Edmund and Bixley, Kirby Cane, Hoveton, Bedingham, Stockton).
The works promoter is UK Power Networks.
NB: please note that the works affecting the Road A are anticipated to take place between 20:00 and 06:00 from 23rd to 25th March 2026. The works affecting the Road B are anticipated to take place from 16th to 18th March 2026. The works affecting the Road C are anticipated to take place from 19th to 29th March 2026.
Weasenham –
A) U35197 The Green from its junction with C72 Massingham Road to its junction with U35280 Lamberts Close.
B) U35197 Lamberts Lane from its junction with U35280 Lamberts Close for 179m north-westwards.
To facilitate carriageway repairs from 16th to 20th March 2026 (may continue until 1st May 2026).
Alternative route is via: C72 Massingham Road, C101 Harpley Road, U35197 Lamberts Lane and vice versa (Weasenham All Saints, Weasenham St. Peter).
The works promoter is Norfolk County Council.