Friary Road, Temporary Road Closure For Various Works
What is happening?
LONDON BOROUGH OF BARNET
Road Traffic Regulation Act 1984 - As Amended By The Road Traffic - (Temporary Restrictions) Act 1991 - Section 14(1) - Temporary Road Closure - Friary Road N12
The BARNET LONDON BOROUGH COUNCIL HEREBY GIVE NOTICE that owing for the need to facilitate the installation of a pedestrian crossing with a raised table, drainage works, the installation of speed cushions and footway reconstruction works, they have made an Order which will close Friary Road N12, outside Nos. 8 to 10 Friary Road, while the works take place.
The works will commence on Monday 17th November 2025 at 8:00am and is expected to last for 6 days.
The alternative route for motorists will be via: Torrington Park, Ravensdale Ave, High Road and vice versa.
Nothing in the above paragraphs shall apply to anything done with the permission of or at the direction of a Police Officer in uniform or other uniformed personnel authorised by the Commissioner of the Metropolis.
Further information may be obtained by contacting the NRSWA Team, London Borough of Barnet, Tel: 020 8359 3555.
Ian Edser Director of Highways and Transportation,
Environment Directorate, 2 Bristol Avenue, London, NW9 4EWDated this 6th November 2025
How long will it take?
Planned start
17-Nov-2025
Estimated end
22-Nov-2025
Need to publish a public notice?
If you need to publish a public notice, please contact Barnet Borough Times directly at: