Public Bridleway No. 7/1, Denham - Temporary Closure due to Surface Erosion Repair Works
What is happening?
BUCKINGHAMSHIRE COUNCIL
(Public Bridleway No. 7, Parish of Denham) (Temporary Bridleway Closure) Order 2025 made on 26 April 2025, under Section 14(1) of the Road Traffic Regulation Act 1984, has with the approval of the Secretary of State for Transport been continued in force and will so continue until 28 October 2026. The effect of the Order is to temporarily prohibit any person from proceeding, except for access, in Public Bridleway No. 7/1, Denham, from the junction of Public Bridleway No. 7/1 & Broken Gate Lane and continues east, then north for the length of approx. 275M, whilst works take place to fix the erosion of the surface of the Bridleway. There is no alternative route.
How long will it take?
Planned start
26-Apr-2025
Estimated end
28-Oct-2026