Acacia Grove, Eccleston - Temporary Road Closure due to Electricity Cable Installation
What is happening?
ST. HELENS BOROUGH COUNCIL
Public Notice
ST. HELENS BOROUGH COUNCIL
ROAD TRAFFIC REGULATION ACT 1984 (as Amended) – SECTION 14(1)
THE COUNCIL OF THE BOROUGH OF ST. HELENS
(ACACIA GROVE, ECCLESTON)
(TEMPORARY PROHIBITION OF DRIVING, ORDER 2025)
NOTICE IS HEREBY GIVEN that on the 24th day of September, 2025, the St. Helens Borough Council made an Order under Section 14(1) of the Road Traffic Regulation Act 1984 (as Amended), the effect of which will be that no person shall cause or permit a vehicle proceed in either direction along Acacia Grove, as and when directed by road traffic signs on-site.
The Order will come into force on Friday 24th October 2022, and will have a maximum duration of eighteen months, but will terminate on completion of the works, which is expected to take 10 days. The alternative route will be via Springfield Lane, Howards Lane, Brooklands Road and vice versa.
The reason for making this Order is to facilitate the installation of a new electricity cable.
Dated this 9th day of October, 2025.
S Walker, Head of Highways and Infrastructure,
Place Services.
Traffic Engineering, 4th Floor, Wesley House, Corporation Street, St. Helens. WA10 1HF
How long will it take?
Planned start
24-Oct-2025
Estimated end
3-Nov-2025