Acacia Grove, Temporary Road Closure Due To Electricity Cable Installation
What is happening?
Public Notice
ST. HELENS BOROUGH COUNCIL
ROAD TRAFFIC REGULATION ACT 1984
(as Amended) – SECTION 14(1)
THE COUNCIL OF THE BOROUGH OF ST. HELENS
(ACACIA GROVE, ECCLESTON) (TEMPORARY PROHIBITION OF DRIVING) ORDER 2025
NOTICE IS HEREBY GIVEN that the St. Helens Borough Council propose not less than seven days from the date of this notice to make an order under the provisions of Section 14(1) of the Road Traffic Regulation Act 1984 (as Amended), the effect of which will be that no person shall cause or permit any vehicle to proceed in either direction along Acacia Grove, as and when directed by road traffic signs on-site.
The Order will come into force on Friday 24th October, 2025, and will have a maximum duration of eighteen months, but will terminate on completion of the works, which is expected to be 10 days. The alternative route will be via Springfield Lane, Howards Lane, Brooklands Road and vice versa.
The reason for making this Order is to facilitate the installation of a new electricity cable.
Dated this 11th day of September, 2025.
S. Walker, Head of Highways and Infrastructure, Place Services.
Traffic Engineering, 4?? Floor, Wesley House, Corporation Street, St. Helens, WA10 1HF
How long will it take?
Planned start
24-Oct-2025
Estimated end
2-Nov-2025