York, Multiple Roads, Temporary Closures Due To Various Works
What is happening?
TEMPORARY TRAFFIC RESTRICTIONS
Notice is hereby given that City of York Council (the Council), in exercise of powers under Sections 14(1) & 15(8) of the Road Traffic Regulation Act 1984 (the Act), made an Order on Thursday, 11 September 2025 in respect of the locations numbered (1), (2), (3), (4), (5), (6), (7), (8) & (9). Furthermore, the Council, not less than 7 days from the publication of this Notice, intends to make an Order under Section 14(1) of the Act in respect of the locations numbered (10), (11), (12), (13), (14) & (15).
(1) BACK LANE BETWEEN 93 AND 119 HUNTINGTON ROAD, YORK
This Order prohibits vehicles & pedestrians from proceeding and waiting in that length of road on Back Lane Between 93 and 119 Huntington Road, York between its junction with Kitchener Street and a location 26 metres south of said junction (closed road) during the period when telecoms works are being undertaken thereon, commencing at 0800hrs on Monday, 15 September 2025 and ending at 1800hrs on Tuesday, 16 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. It is envisaged that the road will only be closed between 0800hrs and 1800hrs each day of the works period. An alternative route for diverted vehicles will be signed during the works period via Kitchener Street, Huntington Road, Ashville Street.
(2) ALLEN CLOSE, YORK
This Order prohibits vehicles from proceeding and waiting in that length of road on Allen Close, York between locations 10 metres and 43 metres south of its junction with Alcuin Avenue (closed road) during the period whereby highway maintenance works are being undertaken thereon, commencing at 0900hrs on Monday, 15 September 2025 and ending at 1500hrs on Tuesday, 16 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. It is envisaged that the road will only be closed between 0900hrs and 1500hrs each day of the works period. An alternative route for diverted vehicles will not be signed during the works period. Access for emergency vehicles will be maintained.
(3) BACK LANE BETWEEN HANOVER STREET WEST AND STAMFORD STREET EAST, YORK
This Order prohibits vehicles from proceeding and waiting in that length of road on Back Lane Between Hanover Street West And Stamford Street East, York between the projected western boundaries of property no’s 32 & 41 Hanover Street West (closed road) during the period when sewer repair works are being undertaken thereon, commencing at 0800hrs on Monday, 15 September 2025 and ending at 1800hrs on Friday, 19 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely.
(4) NABURN LANE, DEIGHTON, YORK
This Order prohibits vehicles from proceeding and waiting in that length of road on Naburn Lane, Deighton, York between its junction with A19 York Road and a location 476 metres west of said junction (closed road) during the period when telecoms works are being undertaken thereon, commencing at 0800hrs on Monday, 15 September 2025 and ending at 1800hrs on Friday, 19 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. An alternative route for diverted vehicles will be signed during the works period via A19 York Road, Howden Lane, Naburn Lane, York Road, Moor Lane.
(5) WHELDRAKE LANE, CROCKEY HILL
This Order restricts vehicles to a 30 miles per hour (mph) speed limit in that length of road on Wheldrake Lane, Crockey Hill between the projected western boundary of the property named South View and a location 165 metres east of said projected boundary (restricted road) during the period when water supply works are being undertaken thereon, commencing at 0800hrs on Monday, 15 September 2025 and ending at 2000hrs on Friday, 19 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely.
(6) HULL ROAD, YORK
This Order prohibits vehicles from proceeding and waiting in that length of road on Hull Road, York between its junctions with A64 (Grimston Bar) and Derwent Dykes Lane (closed road) during the period when carriageway resurfacing works are being undertaken thereon, commencing at 2000hrs on Monday, 15 September 2025 and ending at 0600hrs on Saturday, 25 October 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. It is envisaged that the works will only take place between 2000hrs and 0600hrs each night of the works period. An alternative route for diverted vehicles will be signed during the works period via Foss Islands Road, Heworth Green, Malton Road, A64.
(7) ST PAULS SQUARE, YORK
This Order prohibits vehicles from proceeding and waiting in that length of road on St Pauls Square, York between the projected northern boundary of property no’s 9 & 12 (closed road) during the period when crane works are being undertaken thereon, commencing at 0800hrs on Tuesday, 16 September 2025 and ending at 1700hrs on Friday, 19 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. Additionally, all on-street parking spaces are suspended on both sides of St Paul’s Square between the projected south-western boundaries of property no’s 1 and 10 and on both side of Watson Terrace between its junctions with Watson Street and St Pauls Square (restricted roads). R60 residential parking permit holders will need to park elsewhere in zone R60.
(8) PROW 11-10-10 (CONTINUATION), SKELTON
This Order prohibits pedestrians from proceeding and waiting in that length of public right of way on PROW 11-10-10, Skelton (closed public right of way) due to danger arising from an unsafe bridge thereon, commencing at 1201hrs on Wednesday, 17 September 2025 and ending at 2359hrs on Friday, 27 February 2026 (danger period) or at a time when the danger has been remedied whichever is the earlier. This is to ensure public safety. This Order continues the temporary road closure Notice which had an end date of 1200hrs on Wednesday, 17 September 2025.
(9) FIELD VIEW (AMENDMENT), YORK
This Order amends The York (Field View) (Temporary Traffic Restriction) Order 2024 (original Order). The effect of which is to extend the works area to include that length of road on Field View, York between locations 25 metres and 129 metres south-west of its junction with Wigginton Road and shall come into effect from 0001hrs on Monday, 22 September 2025 and expire at 2359hrs on Tuesday, 25 November 2025 or when the works have been completed whichever is the earlier. An alternative route for vehicles and pedestrians will not be signed during the works period.
(10) CHARLTON STREET, YORK
This Order will prohibit vehicles from proceeding and waiting in that length of road on Charlton Street, York between its junctions with Bishopthorpe Road and Fenwick Street (closed road) during the period when sewer maintenance works are being undertaken thereon, commencing at 0800hrs on Monday, 22 September 2025 and ending at 1800hrs on Friday, 26 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. An alternative route for diverted vehicles will not be signed during the works period. Access will be maintained for residents and emergency services.
(11) SHERIFF HUTTON ROAD, STRENSALL
This Order will restrict vehicles to a 30 miles per hour (mph) speed limit in that length of road on Sheriff Hutton Road, Strensall between its junction with Fossview Close and a location 45 metres north of its junction with New Road (restricted road) during the period when water supply works are being undertaken thereon, commencing at 0800hrs on Monday, 22 September 2025 and ending at 2000hrs on Friday, 26 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely.
(12) MAIN STREET, WHELDRAKE
This Order will prohibit vehicles from proceeding and waiting in that length of road on Main Street, Wheldrake between its junctions with Millfield Industrial Estate and Millfield Court (closed road) during the period when highway development works are being undertaken thereon, commencing at 0800hrs on Monday, 22 September 2025 and ending at 2300hrs on Sunday, 28 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. An alternative route for diverted vehicles will be signed during the works period via Church Lane, Church Lane To The Park, Road From Thorganby To County Boundary; Main Street, Thorganby; Road From Thorganby Lodge To Woodhouse Road; Bonby Lane; York Road; Wheldrake Lane.
(13) KINGS SQUARE, YORK
This Order will prohibit vehicles from proceeding and waiting in that length of road on Kings Square, York between its junction with Goodramgate and a location 15 metres south-east of said junction (closed road) during the period when sewer maintenance works are being undertaken thereon, commencing at 0800hrs on Monday, 22 September 2025 and ending at 1800hrs on Monday, 13 October 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. Additionally, the ‘ONE WAY’ direction of traffic flow in Colliergate and Kings Square are suspended during the period of physical closure to allow two-way traffic flow in the said roads. An alternative route for diverted vehicles will be signed during the works period via Church Street, Parliament Street, Pavement.
(14) SHIRLEY AVENUE, YORK
This Order will prohibit vehicles from proceeding and waiting in that length of road on Shirley Avenue, York between its junctions with Wheatlands Grove and Boroughbridge Road (closed road) during the period when footway reconstruction works are being undertaken thereon, commencing at 0730hrs on Monday, 22 September 2025 and ending at 1600hrs on Friday, 17 October 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. It is envisaged that the works will take place in three separate phases during the works period. An alternative route for diverted vehicles will be signed during the works period via Wheatlands Grove, Ouseburn Avenue, Boroughbridge Road.
(15) HESSAY LEVEL CROSSING, HESSAY
This Order will prohibit vehicles from proceeding and waiting in that length of road on Hessay Level Crossing, New Road, Hessay (closed road) during the period when railway works are being undertaken thereon, commencing at 2305hrs on Thursday, 25 September 2025 and ending at 0625hrs on Friday, 26 September 2025 (works period) or at a time when the works have been completed whichever is the earlier. This is to ensure that the said works can be carried out safely. An alternative route for diverted vehicles will be signed during the works period via Main Street, Atterwith Lane, Marston Lane & A59.
These temporary Orders will not prohibit works or emergency access nor prevent vehicular access to premises provided that access is not prevented by on-going works or safety concerns. Traffic signs/barriers will indicate the extent of the prohibitions/restrictions.
For further information please contact highway.regulation@york.gov.uk