ROAD TRAFFIC REGULATION ACT 1984
What is happening?
Warwickshire County Council has made the following Temporary Traffic Orders:
SCHOOL LANE, PRIORS MARSTON
Order Effect: Road closed to vehicular traffic.
Reason for Order: To enable new gas connection works.
Order Commences: 1 September 2025 for up to 18 months
Anticipated Completion: 5 September 2025
Access & Diversion: School Lane, Holly Bush Lane, Hellidon Road, The Green, The Holloway and vice versa.
Contractor: Cadent Gas, Tel: 08000 111 999.
For all of the above temporary orders, pedestrian access to and egress from properties and land situated adjacent to the length of road to be closed will be maintained at all times. Vehicular access will be maintained where possible.
To report any problems with these works or for further details of our current & planned roadworks visit our website warwickshire.gov.uk/roadworksmap or call us 01926 412515.
S Duxbury, Director of Strategy,
Planning & Governance,
Shire Hall, Warwick CV34 4RL
Date 29 Aug 2025