ROAD TRAFFIC REGULATION ACT 1984 -
SECTION 14(1)(a) AND (7)
THE A45 TRUNK ROAD (RUSHDEN TO
WELLINGBOROUGH, NORTHAMPTONSHIRE)
(TEMPORARY PROHIBITION OF TRAFFIC IN LAYBYS) ORDER 2025
NOTICE IS HEREBY GIVEN that National Highways Limited (Company no. 9346363) has made an order on the A45 Trunk Road, between Rushden and Wellingborough in Northamptonshire, to enable resurfacing works to be carried out.
The effect of the Order will be to close any layby adjacent to the southbound carriageway of the A45 from its roundabout junction with the B645 Northampton Road, the A5001 and Southway, at Rushden, to its roundabout junction with the A509 Wilby Way and Bourton Way, at Wellingborough
The closures are expected to start at 13:00 hours on Monday 8 September 2025 and continue for twelve days. The Order will come into force on 1 September 2025.
Vehicles being used for police, fire and rescue authority or ambulance purposes and vehicles being used in connection with the works will be exempt from the closures.
For further information please contact Samantha Bellanoff, a Project Manager on behalf of National Highways Limited, on 07808 395 769.
Karen Eustace, an Officer in National Highways Limited.
National Highways Limited (Company no.
9346363) registered office: Bridge House, Walnut Tree Close, Guildford, GU1 4LZ. A Company registered in England and Wales.
ROAD TRAFFIC REGULATION ACT 1984 -
SECTION 14(1)(a)
THE A43 TRUNK ROAD (TOWCESTER, NORTHAMPTONSHIRE) (TEMPORARY
PROHIBITION OF TRAFFIC) ORDER 2025
NOTICE IS HEREBY GIVEN that National Highways Limited (Company no. 9346363) has made an Order on the A43 Trunk Road, at Towcester, in Northamptonshire, because works to construct a new roundabout are being carried out.
The effect of the Order will be to prohibit any vehicle with an overall length exceeding 18.65 metres from entering or proceeding on –
(a) the eastbound carriageway of the A43 from its roundabout junction with Brackley Road (Abthorpe Roundabout), to its junction with the link road leading from the A413, at Towcester); or
(b) the westbound carriageway of the A43 from its junction with the link road leading to the A413, at Towcester, to its junction with Abthorpe Roundabout.
The work started on Monday 6 January 2025 and is expected to continue until summer 2026. The Order will come into force at 20:00 hours on Friday 5 September 2025.
For further information, please contact Richard Tansley, on 07718 236 669. Karen Eustace, an officer in the National Highways Limited.
National Highways Limited (Company no.
9346363) registered office: Bridge House, Walnut Tree Close, Guildford, GU1 4LZ. A Company registered in England and Wales.
Need to publish a public notice?
If you need to publish a public notice, please contact Northampton Chron & Echo directly at: