Various Roads, Acton - Temporary Traffic Order for Planned Works
What is happening?
LONDON BOROUGH OF EALING
NOTICE OF MAKING OF TEMPORARY TRAFFIC ORDER FOR PLANNED WORKS AFFECTING: VARIOUS ROADS, ACTON.
Ealing Council has made the following temporary traffic order under sections 14(1)(a) of the Road Traffic Regulation Act 1984:
Title of order
This order can be referred to as: Temporary traffic order for planned works - TT 4759 Various Roads, Acton - 2025.
Reason for order
This order is needed to allow for works taking place on or near the road. These works involve (SSE) Scottish & Southern Energy laying new power cables.
Effect of order
1. This order will impose turning bans, road closures and the use of a bus lane, see schedule on page 2 attached to this order for each work phase and dates.
2. The following temporary restrictions will apply at the locations specified in the Schedule (page 2) (a) Road closures banned turns, and a bus lane suspension will be imposed for vehicular traffic.
3. The temporary restrictions and prohibitions will only apply at specified locations where appropriate traffic signs are provided and displayed in accordance with Chapter 8 of the Traffic Signs Manual. Refer to schedule below.
4. While the temporary restrictions are in place, displaced vehicles should follow the diversions displayed in place to reach their destinations and comply with any traffic management measures.
5. This Order does not apply to:
(a) anything done at the direction of a police officer in uniform or a police community support officer (PCSO).
(b) any vehicle being used for police, fire brigade or ambulance.
Date order will come into force. 14th July 2025
Maximum duration of order
This order will expire on 13th January 2027, or, on completion of the works, which is expected to be 12th September 2025, whichever is sooner.
Date: 10th July 2025
Tony Singh Chief Highways Engineer
Schedule
Date |
Location |
|
Phase 1 |
26/07/2025 TO 12/08/2025 |
NOEL ROAD WILL BE CLOSED AT ITS JUNCTION WITH HORN LANE. |
Phase 2 |
13/8/25 TO 22/8/25 |
HORN LANE WILL HAVE ITS BUS LANE SUSPENDED SO ALL TRAFFIC CAN USE IT FROM ITS JUNCTION WITH NOEL ROAD TO PROPERTY NUMBER 359 HORN LANE (80 metres in length). |
Phase 3 |
25/08/2025 to 29/08/2025 |
LEAMINGTON PARK WITH PROHIBIT THE RIGHT TURN ONTO HORN LANE. |
Phase 4 |
08/09/2025 to 12/09/2025 |
LEAMINGTON PARK WITH PROHIBIT THE RIGHT TURN ONTO HORN LANE. |
Phase 5 |
14/7/25 TO 23/7/25 |
ROAD CLOSURE OF LUCY CRESCENT AT ITS JUNCTION WITH WILFRED GARDENS. |
Phase 6 |
24/7/25 TO 1/8/25 |
ROAD CLOSURE OF LUCY GARDENS AT ITS JUNCTION WITH KATHLEEN AVENUE. |
Phase 7 |
14/8/25 TO 25/8/25 |
ROAD CLOSURE OF THE LINK AT ITS JUNCTION WITH HOWARD CLOSE. |