Chatsworth Road, Sutton - Temporary Road Closure due to Gas Mains Replacement
What is happening?
London Borough of Sutton
Public Notice
LONDON BOROUGH OF SUTTON
ROAD TRAFFIC REGULATION ACT 1984 - SECTION 14(1)
1. The Council of the London Borough of Sutton hereby gives notice that in order to facilitate a gas mains replacement and because these works are being executed on or near the carriageway it intends to make an Order the effect of which is summarised in paragraph 3 below.
2. The Order will come into effect on Monday 21st July 2025 and is expected to take 3 weeks to complete, however the Order will remain in force for 18 months to be re-introduced should further works be required.
3. When the works are taking place and the appropriate traffic signs are displayed the Order will temporarily prohibit all vehicular traffic including pedal cycles from entering, exiting, stopping or proceeding in Chatsworth Road between its junctions with Malden Road and Church Hill Road.
4. An alternative route for vehicular traffic when the prohibition is in place will be via either;-
• Malden Road, Lumley Road, St Dunstans Hill, Church Hill Road and vice versa; or
• Malden Road, Priory Road, Church Hill Road and vice versa.
5. Vehicles access to properties adjacent to the prohibited length of road will be maintained at all times insofar as access is reasonably practicable without interference with the said works.
6. The prohibitions specified above apply only during such times and to such extent as indicated by traffic signs prescribed by the Traffic Signs Regulations and General Directions 2016.
Dated 23rd July 2025
Ali Ataie
Corporate Head of Highways and Transport (Interim)
Note: Persons responding to the proposed Orders should be aware that the Council may be legally obliged to disclose the information provided to third parties.
How long will it take?
Planned start
21-Jul-2025
Estimated end
11-Aug-2025