Mulgrave Road,Temporary Road Closure Due To Gas Main Works
What is happening?
LONDON BOROUGH OF SUTTON
PUBLIC NOTICE: - ROAD TRAFFIC REGULATION ACT 1984 - SECTION 14(1)
1. The Council of the London Borough of Sutton hereby gives notice that in order to facilitate a gas mains replacement and because these works are being executed on or near the carriageway it intends to make an Order the effect of which is summarised in paragraph 3 below.
2. The Order will come into effect on Monday 30th June 2025 and is expected to take 3 weeks to complete, however the Order will remain in force for 18 months to be re-introduced should further works be required.
3. When the works are taking place and the appropriate traffic signs are displayed the Order will temporarily prohibit all vehicular traffic including pedal cycles from entering, exiting, stopping or proceeding in Mulgrave Road between its junctions with Upper Mulgrave Road and Beresford Road.
4. An alternative route for vehicular traffic when the prohibition is in place will be via either:- Station Way, High Street, Cheam Road, York Road, Mulgrave Road and vice versa; or - Beresford Road, Belmont Rise, Northey Avenue, Burdon Lane, Sandy Lane and vice versa.
5. Vehicles access to properties adjacent to the prohibited length of road will be maintained at all times in so far as access is reasonably practicable without interference with the said works.
6. The prohibitions specified above apply only during such times and to such extent as indicated by traffic signs prescribed by the Traffic Signs Regulations and General Directions 2016.
Ali Ataie,
Corporate Head of Highways and Transport (Interim)
Dated: 27th May 2025.
How long will it take?
Planned start
30-Jun-2025
Estimated end
21-Jul-2025