Henfield: Hollands Lane - Temporary Closure
What is happening?
West Sussex County Council
Henfield: Hollands Lane
(Temporary Closure) Order 2025
NOTICE is hereby given that WSCC made an Order under the Road Traffic Regulation Act 1984, the effect of which will be to close Hollands Lane between Station Road and Hollands Road.
The Order is necessary to protect public safety whilst new power connections are made.
The Order will come into effect on 2 June 2025 and will last for 18 months or until the proposed works are completed, whichever is earlier. It is anticipated the works will commence on or after 2 June 2025 and will take 10 days to complete. Any queries about the works to take place should be directed to Sunbelt Rentals, telephone number 03700 500792.
Any queries about the effect of the Order on vehicles using the highway should be directed to WSCC, telephone number 01243 642105.
Date 29 May 2025
Director of Law & Assurance, County Hall, Chichester.
How long will it take?
Planned start
2-Jun-2025
Estimated end
2-Dec-2026
Need to publish a public notice?
If you need to publish a public notice, please contact Sussex World directly at: