Braintree, Multiple Traffic Notices - Temporary Road Closures due to Utility and Infrastructure Works
What is happening?
Essex County Council
(Avenue East, Great Notley) (Temporary Prohibition of Traffic) Order 2025
Notice is hereby given that the Essex County Council intends, not less than seven days from the date of this notice, to make the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order: To temporarily close that length of Avenue East, Great Notley in the District of Braintree, from the junctions with Business Park Road Roundabout to the junctions with Queenborough Lane Roundabout a distance of approximately 100m.
The closure is scheduled to commence on 26th May 2025 for 6 days, or where stated on a valid permit (YN12321437-PGN-PO – T Mobile Ltd). The scheduled dates may vary for these works with appropriate signs showing and/or displayed on one.network. The closure is required for the safety of the public and workforce while pole installation works are undertaken by T Mobile Ltd.
An alternative route is available via Business Park Link, Garden Village Way Roundabout, A131 – Panners Roundabout, Pods Brook Road, Springwood Roundabout, Rayne Road, The Street, Gore Road, Queenborough Lane, Braintree Green, Queenborough Lane and vice versa.
The Order will come into effect on 8th May 2025 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
(Lanham Green Road/Lanham Green, Cressing) (Temporary Prohibition of Traffic) Order 2025
Notice is hereby given that the Essex County Council intends, not less than seven days from the date of this notice, to make the above Order under section 14(1) of the Road Traffic Regulation Act 1984.
Effect of the order: To temporarily close that length of Lanham Green Road/Lanham Green, Cressing in the District of Braintree, from a point approximately 80m south west of the junction with Lanham Farm Road for a distance of approximately 70m in a south westerly direction. The closure is scheduled to commence on 28th May 2025 for 38 days, or where stated on a valid permit (AD01465218727/2 – Anglian Water). The scheduled dates may vary for these works with appropriate signs showing and/or displayed on one.network. The closure is required for the safety of the public and workforce while mains replacement works are undertaken by Anglian Water.
An alternative route is available via A120, Galley Roundabout, A120 J B1018 Roundabout, Long Green, Ashes Road, Lanham Green Road and vice versa (with access only into Lanham Green, Withies Green and Lanham Green Road). For Boars Tye Road please use The Street, Polecat Road, Witham Road and Temple Lane.
The Order will come into effect on 8th May 2025 and may continue in force for 18 months or until the works have been completed, whichever is the earlier.
DATED: 1ST MAY 2025
Need to publish a public notice?