What is happening?

LONDON BOROUGH OF EALING
NOTICE OF INTENT TO CREATE A TEMPORARY TRAFFIC ORDER FOR PLANNED WORKS AFFECTING: BALFOUR ROAD, ACTON.

Ealing Council intends to make the following temporary traffic order under section 14(1)(a) of the Road Traffic Regulation Act 1984:

Title of order
This order can be referred to as: Temporary traffic order for planned works - TT 4701 Balfour Road, Acton - 2025.

Reason for order
This order is needed to allow for works taking place on or near the road. These works involve

Effect of order

1. This order will close Cloister Road from its junction with Balfour Road to a point outside property number 45 Cloister Road from 18th to 25th May 2025.

2. Balfour Road will be closed between its junctions with Cecil Road & Cloister Road from 26th May to 6th June 2025.

3. The following temporary restrictions on vehicle movements will take effect from 26th May to 6th June 2025.

(a) No entry into the fully closed section(s) of Cloister Road & Balfour Road.

(b) No waiting, loading, or unloading on either side of the carriageway within the fully closed section.

4. The above temporary restrictions and prohibitions will only apply at specified locations where appropriate traffic signs are provided and displayed in accordance with Chapter 8 of the Traffic Signs Manual.

5. While the temporary restrictions are in place, displaced vehicles should follow the diversions displayed in place to reach their destinations and comply with any traffic management measures.

6. This Order does not apply to:

(a) anything done at the direction of a police officer in uniform or a police community support officer (PCSO).

(b) any vehicle being used for police, fire brigade or ambulance.

Date order will come into force.
26th May 2025

Maximum duration of order
This order will expire on 25th November 2026 or, on completion of the works, which is expected to be 6th June 2025, whichever is sooner.

Date: 29th April 2025

Tony Singh
Chief Highways Engineer

Need to publish a public notice?

If you need to publish a public notice, please contact Chronicle & Informer directly at:

publicnoticesteam@reachplc.com

01227 907972

About Us

The Public Notice Portal is owned and operated by the News Media Association, the voice of UK national, regional, and local newspapers in all their print and digital forms. NMA members include nearly 900 local and regional news titles which reach 40 million people across the length and breadth of the country each month.

Public Notice PortalNews Media Association