Norfolk County Council

TEMPORARY TRAFFIC REGULATION ORDERS 2025

Road Traffic Regulation Act, 1984

Norfolk County Council in exercise of its powers under Section 14(1) of the Road Traffic Regulation Act 1984, hereby give notice that:

THEY PROPOSE TO MAKE Temporary Traffic Regulation Orders in respect of the following roads:

BEESTON REGIS – 1) Holt Road from its junction with A148 Holt Road for 150m north eastwards to facilitate foot way reconstruction. The works are expected to take place between 29th April to 2nd May 2025, then again from 14th to 16th May 2025 and 21st and 22nd May between 800 and 1600.

2) Holt Road from A148 Holt Road for 130m south westwards to facilitate road widening and carriageway resurfacing works. Alternative route via: A148 Holt Road, A149 Cromer Road / Holt Road, A140 Cromer Road / Roughton Road / Church Street / Mundesley Road / Station Road / A149 High Street / Cromer Road / Hall Road, West Street / Holt Road (East Beckham, Beeston Regis, the works promoter is Norfolk County Council).

BODHAM – The Street from its junction with Holt Lane to its junction with Sheringham Road to facilitate critical pole replacement works between 0800 and 1800 on 28th April 2025 (may continue up until 6th June 2025). Alternative route via: The Street, Cromer Road, Holt Road, Sheringham Road (Upper Sheringham, West Beckham, Bodham). The works promoter is UK Power Networks.

BODHAM – Kett’s Road from 190m west of its junction with New Road for 30m westwards to facilitate works for new water connection on 28th to 30th April 2025 (may continue until 11th June 2025). Alternative route via: Red Barn Lane, Long Lane, Ings Lane, Sheringham Road, Holt Road, Cromer Road, Connors Road, Cedar Grove, Leeder Street, Bridge Road, High Village, Upper Sheringham, West Beckham, Bodham). The works promoter is Anglian Water.

BURGH CASTLE – Mill Road from its junction with Market Road for 100m northwards to facilitate ducting installation works on 28th to 29th April 2025 (may continue until 10th June 2025). Alternative route via: Mill Road, Butt Lane, Belton New Road, Stepshort, A143 Beccles Road, Church Road, Mill Road, Market Road (Burgh Castle, Belton, Bradwell).

2) Mill Road from 50m south west of its junction with Market Road to 100m southwards to facilitate pole testing and cutting between works 0900 and 1500 on 6th June 2025. Alternative route via: Mill Road, Church Road, Belton New Road, Butt Lane, Mill Road (Burgh Castle, Belton). The works promoter is UK Power Networks.

CAWSTON – B1145 Holt Road from its junction with the B1145/4039 Holt Road Roundabout for 150m westwards to facilitate essential carriageway resurfacing and lining works from 13th to 17th May 2025.

2) B1145 Holt Road from its junction with B1145 Holt Road Roundabout for 150m westwards to facilitate essential carriageway resurfacing and lining works from 13th to 17th May 2025. Alternative route via: B1145 Church Street, Aylsham Road, The Street, Reepham Road, Station Road, Cawston Road, Holt Road, Church Street, Market Street, High Street, Holt Road, Norwich Road, Reepham Road, B1145 Holt Road, B1145/4039 Holt Road Roundabout (Cawston, Reepham, Bawdeswell, Swanton Morley, Dereham).

CROMER – High Street from 10m east of its junction with Garden Street for 25m westwards to facilitate new gas connection works. The works are expected to be completed in two phases:

Phase 1 is between 0700 and 1900 from 30th April to 1st May.

Phase 2 is between 1900 and 0500 from 6th to 10th May.

Phase 3 is between 0900 and 1600 from 12th to 14th May.

Phase 4 is between 1900 and 0500 from 5th to 6th June.

CROMER – 1) Harbour Road from 10m west of its junction with Saddlebow Road for 25m westwards and 2) Saddlebow Road from 10m south of its junction with Harbour Road for 20m southwards to facilitate critical pole replacement works from 28th April to 7th May 2025.

Alternative route is via: Harbour Road, Runton Road, Station Road, Louden Road, Alfred Road, St. Swithin Road, Harbord Road. The works promoter is UK Power Networks.

DICKLEBURGH – The Street from its junction with Harvey Lane for 25m eastwards to facilitate a new water connection on 1st to 2nd May 2025 (may continue until 13th June 2025). Alternative route via: A140 Ipswich Road, A143 Church Road, The Street (Dickleburgh and Rushall, Scole). The works promoter is Anglian Water.

FAKENHAM – Queen’s Road from its junction with Whitehorse Street for 15m westwards to facilitate new development works on 28th to 30th April 2025.

Alternative route is via: Queen’s Road, Oak Street, Bridge Street, Oliver Way, White Horse Street (Fakenham). The works promoter is UK Power Networks.

FAKENHAM – Oak Street from 10m east of its junction with Bridge Street to its junction with White Horse Street to facilitate works to allow the safe installation of the cycle lane infrastructure and carriageway widening works. The works will be completed in two phases between 0900 and 1700 on 30th April 2025.

FELTHORPE – 1) Felthorpe Restricted Byway 19 from its junction with Haverscroft Road for 112m southwards and

2) Horsford Restricted Byway 1 from its junction with Haverscroft Road for 121m southwards to facilitate construction works of park and wider cycle and highway improvement works from 30th April to 20th October 2025.

An alternative route will be constructed on site. The works promoter is Norfolk County Council.

GORLESTON-ON-SEA – Waltham Road from its junction with Queen’s Crescent for 15m southwards to facilitate footway replacement and pedestrian crossing installation works from 28th to 30th May 2025 (may continue until 30th November 2025).

Alternative route is via: St Hugh’s Green, Somerville Avenue, Queen’s Crescent. The works promoter is Norfolk County Council.

GREAT YARMOUTH – Regent Street from its junction with Howard Street South for 65m southwards to Hallplain to resurface various works from 30th April to 1st May 2025 (may continue until 6th June 2025).

Alternative route is via: Howard Street South, King Street, Regent Street, The Conge, North Quay. The works promoter is Norfolk County Council.

GREAT YARMOUTH – 1) South Market Road from its junction with Temple Road for 186m westwards and

2) Temple Road from its junction with Alexandra Road for 20m southwards and

3) Alexandra Road from its junction with Temple Road for 15m eastwards and

4) Trafalgar Road from its junction with Albion Road for 85m westwards and

5) Trafalgar Road from its junction with Albion Road for 65m eastwards and

6) Beevor Street from its junction with Admiralty Road for 65m southwards to facilitate carriageway resurfacing works from 28th to 30th April 2025 (may continue until 11th June 2025).

Alternative route via: Queen’s Road, King Street, Nelson Road Central, Marine Parade, Euston Road, Admiralty Road (Great Yarmouth). The works promoter is Norfolk County Council.

HORSHAM WITH ST FAITH/HELLINGHAM – Stanninghall Road for 210m northeast of its junction with Bell Road to facilitate pole replacement works from 28th to 29th April.

Alternative route is via: Stanninghall Road, Buxton Road, 1st Main Road, Church Lane, Norwich Road, Quay Road, The Street, Old Church Road, Stanninghall Road.

The works promoter is UK Power Networks.

HETHERSETT – Unnamed road from its junction with Great Melton Road for 100m westwards to facilitate footway and drainage works from 5th to 7th May 2025.

Alternative route via: Great Melton Road, Colney Lane, Watton Road, Earlham Road, Newmarket Road, B1172 Norwich Road, Churchfields, Queen’s Road (Hethersett).

The works promoter is Norfolk County Council.

SOUTHWOOD – The Street for 120m from 225m northeast of its junction with The Street for 50m westwards to facilitate drainage survey works from 5th to 7th May 2025 (may continue until 13th June 2025).

Alternative route is via: The Street, A47 Trunk Road, Southwood Road. The works promoter is Norfolk County Council.

SEA PALLING – New Road from 10m north of its junction with Clink Lane for 100m northwards to facilitate drainage investigation works.

The works are expected to be carried out in two phases between:

Phase 1: 29th April to 2nd May 2025,

Phase 2: 3rd to 6th June 2025.

Alternative route is via: Church Road, Stalham Road, Old Norwich Road, New Road, Ingham Road, Waxham Road, Beach Road, Beach Road (Sea Palling).

The works promoter is BT.

SPOONER ROW – B1172 Norwich Road from its junction with Station Lane for 100m westwards to facilitate carriageway resurfacing works from 6th to 8th May 2025.

Alternative route is via: B1172 Harts Farm Road, Silfield Road, A11 Trunk Road, Station Lane (Wymondham, Spooner Row). The works promoter is Norfolk County Council.

SWAFFHAM – Brandon Road from its junction with Buxton Road to its junction with Giles Road to facilitate carriageway resurfacing works from 30th April to 2nd May 2025 (may continue until 11th June 2025).

Alternative route is via: Brandon Road, A1065 Brandon Road, A1065 Castle Acre Road, West Acre Road, Sporle Road, Redlands Road, Buxton Road, Arthur Road, Southend (Swaffham).

The works promoter is Norfolk County Council.

TAVERHAM – Sandy Lane from 40m north of its junction with Fir Lane for 20m northwards to facilitate urgent carriageway patching works from 30th April to 1st May 2025.

Alternative route is via: Fir Lane, Sandy Lane (Taverham).

The works promoter is Norfolk County Council.

WRENINGHAM – Unnamed road from its junction with Wymondham Road to its junction with Top Row for 300m westwards to facilitate the upgrade of BT infrastructure from 29th April to 2nd May 2025 (may continue until 13th June 2025).

Alternative route is via: Wymondham Road, Ashwellthorpe Road, The Street, Mill Lane, Wymondham Road, Low Road (Ashwellthorpe and Fundenhall, Wreningham).

The works promoter is BT.

THURTON – A146 Loddon Road from its junction with George Lane to 170m southwards to facilitate drainage works from 29th April to 2nd May 2025.

Alternative route is via: A146 Loddon Road, B1136 Yarmouth Road, B1136 The Street, Mundham Road, A143 Mill Road, A143 Bungay Road, A143 Yarmouth Road, A146 Loddon Road.

The works promoter is Norfolk County Council.

WACTON – The Street from its junction with Common Road for 20m southwards to facilitate new water connection works from 30th April to 2nd May 2025.

Alternative route is via: The Street, Church Road, Long Stratton Road, Hempnall Road, Mill Road (Wacton).

The works promoter is Anglian Water.

WEST WALTON – Unnamed road from its junction with Walton Road for 25m westwards to facilitate carriageway resurfacing works from 6th to 8th May 2025.

Alternative route is via: Walton Road, Low Road, School Road, St Paul’s Road South, St Paul’s Road (West Walton).

The works promoter is Norfolk County Council.

THORPE ST. ANDREW – Thorpe Avenue from its junction with A1042 Ring Road for 30m northwards to facilitate mains lining works from 28th to 30th April 2025 (may continue until 11th June 2025).

Alternative route is via: A1042 Ring Road, Thunder Lane, Spinney Road.

There are none. The works promoter is Anglian Water.

THURSFORD – B1354 Holt Road from its junction with Brick Kiln Road to its junction with Snoring Road to facilitate carriageway resurfacing and surface dressing preparation works.

While this section is in use a five day notice will run from 1st June 2025.

The road will be closed from 2nd June to 6th June 2025.

Alternative route via: B1354 Thursford Road, Thursford Green, The Street, Holt Road, Briston Road, B1110 Reepham Road, B1149 Holt Road, Melton Road, Briston Road, B1110 Foulsham Road, Reepham Road, Guist Bottom Road, B1110 Reepham Road, B1110 Fakenham Road, Foulsham Road, Briston Road to Field Dalling, Thursford, Sharrington, Littlethorncroft with Gifford, Briningham, Thornage, Binham, Holt, Thursford, Stody, Letheringsett and Glandford. The works promoter is Norfolk County Council.

WEST LYNN/KING’S LYNN – St Peter’s Road from its junction with St Peter’s Close and Edward Benefer Way to its junction with A148 London Road to facilitate footway resurfacing works from 28th April to 2nd May 2025.

Alternative route via: St Peter’s Road, Edward Benefer Way, Gaywood Road, Tennyson Avenue, A148 London Road.

The works promoter is Norfolk County Council.

WEST WINCH – A10 from 40m southeast of its junction with Setchey Lane to 40m northwest of its junction with A148 Saddlebow Road to facilitate junction improvement and traffic signal works from 28th April to 2nd May 2025.

Alternative route is via: A148 Saddlebow Road, Edward Benefer Way, Tennyson Avenue, Gaywood Road, Queen Mary Road, Columbia Way, Southgate Street, London Road, Wisbech Road (King’s Lynn, West Winch).

The works promoter is Norfolk County Council.

WITTON AND RIDLINGTON (NORTH WALSHAM) – The Street from 20m north of its junction with Old Lane for 170m northwards to facilitate the creation of a new carriageway access between 24th April to 2nd May 2025 (may continue until 2nd November 2025).

Alternative route is via: The Street, North Walsham Road, Ridlington Road, North Walsham Road, B1151 Stalham Road, Old Lane, The Street (North Walsham, Witton, Walcott).

The works promoter is Norfolk County Council.

The time detailing when regulations start at Norfolk County Council is North Westworks.

BARTON AND WALSHINGHAM – Church Lane from its junction with Back Lane for 45m southwestwards to facilitate duct laying works on 28th to 1st May 2025 (may continue until 12th June 2025).

Alternative route via: Church Lane, Cock Street, New Road, Newgate Green, Hindringham Road, Field Dalling Road, Briston Road, Bale Road (Barsham, Barston, Wighton, Cockthorpe & Foulton).

The works promoter is Anglian Water.

COUXKR & POUNDING NORTON – B1146 Hempton Road from its junction with C235 Fakenham Road for 14m to its junction with C236 Fakenham Road to facilitate carriageway reconstruction and resurfacing works from 28th to 2nd May 2025.

Alternative route is via: B1146 Hempton Road, B1146 Dereham Road to junction with C235 Fakenham Road (westbound only), and C235 Fakenham Road (northbound to B1146 Dereham Road to junction with A1065 to facilitate carriageway improvements on the main B1146 between the hours of 0730 to 1800 from 28th to 2nd May 2025.

The works promoter is Norfolk County Council.

CROMER – B1436 Holt Road from 35m west of its junction with Hall Road for 30m westwards to facilitate duct laying and new chamber installation works from 28th April to 2nd May 2025 (may continue until 12th June 2025).

Alternative route is via: Hall Road, A149 Holt Road, Norwich Road, West Street, Church Street, Station Road, B1436 Holt Road (Cromer).

The works promoter is Openreach.

DISS – 1) Denmark Street from its junction with Victoria Road to its junction with Shelfanger Road,

2) Victoria Road from its junction with Denmark Street to its junction with Louies Lane,

3) Shelfanger Road from its junction with Victoria Road to its junction with Factory Lane,

4) Factory Lane from its junction with Shelfanger Road to its junction with Vinces Road,

5) Vinces Road from its junction with Factory Lane to its junction with Gilray Road

to facilitate carriageway patching and micro surfacing works from 28th April to 2nd May 2025.

Alternative route is via: B1077 Denmark Street, Victoria Road, Shelfanger Road, Factory Lane, Vinces Road, Gilray Road (Diss).

The works promoter is Norfolk County Council.

DERSINGHAM – B1440 Lynn Road from its junction with Station Road to 35m eastwards to facilitate water connection works from 28th April to 2nd May 2025.

Alternative route is via: Station Road, Station Approach, Centre Vale, Post Office Road, Sandringham Road (Dersingham).

The works promoter is Anglian Water.

FIRMHAM/HINGHAM – B1108 Attleborough Road from 25m north of its junction with Dereham Road for 25m northwards to facilitate pole replacement works from 28th April to 1st May 2025.

Alternative route is via: Dereham Road, B1108 Attleborough Road, Market Place, Watton Road, B1135 Deopham Road (Hingham, Wicklewood, Deopham).

The works promoter is UK Power Networks.

GARSYESTONE, NEWTONSTON AND THURTON – 251014 Martham Road from 573m southwest of its junction with Litcham-Bradfield Green for 150m southeastwards to facilitate pole installation works between 0900 and 1800 on 28th April to 2nd May 2025 (may continue until 10th June 2025).

Alternative route is via: 251015 Bradfield Green Road, 251026 Bracknell Lane and Sandpit Road.

The works promoter is UK Power Networks.

GOODERSTONE – Clarkes Lane from its junction with Swaffham Road for 50m southwards to facilitate water installation works from 28th to 30th April 2025 (may continue until 11th June 2025).

Alternative route is via: Church View, The Street, Gooderstone Road, Swaffham Road (Oxborough, Gooderstone).

The works promoter is Anglian Water.

LODDON – C305 Church Road 150m northwards to its junction with C295 Mundham Road for 50m westwards to facilitate repair works from 28th April to 2nd May 2025 (may continue until 11th June 2025).

Alternative route is via: Church Road, Beccles Road, Loddon Road, Mundham Road (Mundham, Loddon, Sisland).

The works promoter is Norfolk County Council.

MOORCROFT – C113 Heath Road for 120m south of its junction with C493 Stone Road to its junction with C395 Bee Street to facilitate pole testing works between 0830 and 1530 on 28th to 29th April 2025 (may continue until 12th June 2025).

Alternative route is via: Stone Road, Green Road, Sand Lane, Earsham Road, A47, C517 The Street and B1518 (Honingham, Hethersett, Wreningham, Little Tuddenham).

The works promoter is BT.

ROCKLAND ST MARY WITH HELLINGATON – C202 Bramerton Lane for 100m northwest of its junction with U78121 Cross Lane for 40m westwards to facilitate pole safety testing works between 0830 and 1530 on 28th to 29th April 2025 (may continue until 11th June 2025).

Alternative route is via: Cross Lane, Rockland Road, Bramerton Road, Bramerton Common, Ferry Road, Langley Road, Bramerton Road, Surlingham Road, Rockland Road (Rockland St Mary, Claxton, Langley, Kirby Bedon, Hellington, Bramerton).

The works promoter is BT.

ROUGHTON – Felbrigg Road from its junction with Hall Road for 50m westwards to facilitate water works from 28th to 30th April 2025 (may continue until 11th June 2025).

Alternative route is via: Hall Road, Hall Close, Hall Road, Sandpit Lane, Felbrigg Road (Roughton).

The works promoter is Anglian Water.

SHARRINGTON – Bale Road from 50m south of its junction with Back Street to 100m north of its junction with Briston Road to facilitate carriageway repair works from 28th April to 2nd May 2025 (may continue until 12th June 2025).

Alternative route is via: Back Street, Holt Road, Briston Road, Bale Road (Sharrington).

The works promoter is Norfolk County Council.

SOUTHWOLD – The Street from its junction with Common Road for 50m westwards to facilitate pole works between 0830 and 1530 on 28th April to 2nd May 2025 (may continue until 12th June 2025).

Alternative route is via: Common Road, The Street, Southwold Road, Southwold Common, Southwold Road, The Street (Flixton, Bungay, Southwold).

The works promoter is BT.

SPARHAM – C224 Lyng Road from its junction with U5282 Mile Close for 225m eastwards to facilitate verge works from 28th April to 2nd May 2025 (may continue until 12th June 2025).

Alternative route is via: C224 Lyng Road, Mile Close, C204 Market Road, Lyng Road (Lyng, Sparham).

The works promoter is Norfolk County Council.

SWANTON MORLEY – Woodgate Lane from its junction with Church Road for 80m southeastwards to facilitate pole testing works between 0830 and 1530 on 28th April to 2nd May 2025 (may continue until 12th June 2025).

Alternative route is via: Woodgate Lane, Low Road, Elsing Lane, Greengate, Woodgate Lane (Swanton Morley).

The works promoter is BT.

THETFORD – Raymond Street from its junction with Chase Road to its junction with Croxton Road to facilitate pole testing works between 0830 and 1530 on 28th to 29th April 2025 (may continue until 12th June 2025).

Alternative route is via: Croxton Road, Norwich Road, London Road, Bury Road, Raymond Street (Thetford).

The works promoter is BT.

WATTON – B1108 Brandon Road from 150m north of B1113 Mill Lane for 125m northwards to facilitate pole works between 0830 and 1530 on 28th to 29th April 2025 (may continue until 12th June 2025).

Alternative route is via: Griston Lane, Swaffham Lane, Swainsthorpe Lane, Thompson Road, Norwich Road, School Road, Millhead, Mundford Road (Watton, Thompson, Griston, Ashill).

The works promoter is BT.

WORLINGHAM – Lowestoft Road from 80m southeast of its junction with B1123 Marsh Lane for 100m southeastwards to facilitate pole safety testing between 0830 and 1530 on 28th April to 1st May 2025 (may continue until 12th June 2025).

Alternative route is via: Lowestoft Road, Ellough Road, London Road, B1123 Garden Lane, Beccles Road, Station Road, Woodlands, Poplar Road, Shadingfield Road, Barsham Road (Worlingham).

The works promoter is BT.

THETFORD – Cycle Path Between 3 and 5 Stanford Road To Tottington Close from its junction with Stanford Road for 15m north-eastwards to facilitate mains exchange works on 1st May 2025 (may continue until 11th June 2025).

Alternative route is via: Stanford Road, Croxton Road, Richard Easten Road.

The works promoter is Anglian Water.

THETFORD – 1) Minstergate Lane to junction with Station Road to facilitate sewer replacement works.

The junction with Minstergate Street and Station Road will be closed, and the pavement works. The road will be temporarily closed and the road shall be subject to the suspension of the one-way system to allow for the safe passage of traffic between 28th April to 2nd May 2025 (may continue until 11th June 2025).

Alternative route is via: Station Road, London Road, St Nicholas Street, Minstergate Lane.

The works promoter is Anglian Water.

THETFORD – College Heath Road southwards from 25m north of 2 College Heath Road for 25m southwards to facilitate sewer repair works between 28th to 30th April 2025 (may continue until 11th June 2025).

Alternative route via: Kilverstone Road, Norwich Road, Hamond Road, Bungay Road, Augusta Road, Mary Lane, Barning Road, Topcroft Street (Rougham, Hepmnalhall).

The works promoter is Norfolk County Council.

WATTON – C121 Saham Road junction from B1108 High Street/Brandon Road for 25m north on the northwards and

C121 Saham Road from north of its junction with B1108 High Street/Brandon Road for 15m northwards and

C121 Saham Road from its junction with B1108 High Street/Brandon Road for 12m northeastwards and

C121 Saham Road from 130m north of its junction with B1108 High Street/Brandon Road for 125m northwards

and C121 Saham Road from 400m north of its junction with B1108 High Street/Brandon Road for 200m northwards to facilitate mains supply works.

The road is closed from 29th April to 1st May 2025 (may continue until 11th June 2025).

This road may be closed in sections on these dates and during the working days.

Alternative route is via: The Broadway, C122 Plough Lane, C119 Plough Lane, C118 North Road, C121 Fields Road, B1108 Brandon Road, B1108 Brandon Road (Watton, Saham Toney).

The works promoter is UK Power Networks.

WATTON – U33489 Harvey Street from its junction with B1108 High Street for 60m north-eastwards and

U33489 Harvey Street from north-eastwards to its junction with B1108 High Street for 117m eastwards and

U33488 Harvey Street from 70m northeast of its junction with B1108 High Street for 117m eastwards and

U33490 Deans Road from 28m north of its junction with B1108 High Street for 18m south of its junction with B1108 High Street to facilitate mains supply works.

The road will be temporarily closed.

Traffic on the roads may be subject to alternative routes via: B1108 High Street, Brandon Road, Carbrooke Road, Deans Road, Harvey Street, Harvey Street, U33488 Deans Road (Watton).

The works promoter is UK Power Networks.

WORTHINGHAM – U7845 Colville Road from its junction with U7847 Warwicks Drive for 10m eastwards to facilitate pole replacement works between 28th to 30th April 2025 (may continue until 11th June 2025).

Alternative route is via: Sheffield Road, Lime Tree Avenue, Turtles Lane.

The works promoter is UK Power Networks.

DOWNHAM MARKET – Various locations in South Southwold, Downham Market to facilitate street lighting patrols from 28th April to 1st May 2025 (may continue until 11th June 2025).

The works promoter is Norfolk County Council.

DOWNHAM MARKET – Paradise Road from its junction with Railway Road for 81m westwards to facilitate street lighting patrols from 28th April to 1st May 2025 (may continue until 11th June 2025).

Alternative route is via: Paradise Road, Paradise Parade, Paradise Road, Priory Road, Park Avenue, Priory Road, Railway Road.

The works promoter is Norfolk County Council.

EAST WINCH – 1) Stone Close from its junction with Main Road for 30m eastwards to facilitate long term carriageway widening works from 28th April to 2nd May 2025 (may continue until 11th June 2025).

Alternative route is via: Main Road, Town Lane, Station Road, School Road, Ashwicken Road, Mill Hill Road, School Road, Mill Lane (East Winch, West Winch, Pentney, Ashwicken).

The works promoter is Norfolk County Council.

KING’S LYNN – Somerfield Road from 25m north of its junction with Windsor Road to its junction with Windsor Road to facilitate footway works from 28th April to 1st May 2025 (may continue until 11th June 2025).

Alternative route is via: William Booth Road, Mulberry Road, Millow Way, Windsor Church Hill.

The works promoter is Norfolk County Council.

KING’S LYNN – Gladstone Road from 20m north of its junction with The Friars for 20m northwards to facilitate stop tap replacement works from 30th April to 2nd May 2025 (may continue until the 13th June 2025).

Alternative route is via: Ethel Terrace, Friars Street.

The works promoter is Anglian Water.

KING’S LYNN – Blackfriars Road from its junction with Wellesley Street to its junction with Austin Street to facilitate carriageway resurfacing works between 19:00 and 06:00 from 27th to 28th April to 1st May 2025 (may continue until the 10th June 2025).

Alternative route is via: Wellesley Street, Railway Road, Norfolk Street, John Kennedy Road, Austin Street, Littleport Street, Old Sunway, Tower Street, Surrey Street, Goodwins Road, Tennyson Avenue, South Gates Road, London Road, St. James Road.

The works promoter is Norfolk County Council.

KING’S LYNN – Tennyson Avenue from its junction with Gaywood Road to its junction with the Southgates roundabout to facilitate carriageway resurfacing works.

The Road will be subject to the temporary suspension of the 7.5-tonne weight restriction between 19:00 and 06:00 from 27th April to 1st May (may continue until 10th June 2025).

The works promoter is Norfolk County Council.

NB: Please note the suspension is not in place on Sundays.

SHOULTHAM – Wades Close Street from 20m north of its junction with Lynn Road for 50m northwards to facilitate stop tap replacement works from 29th April to 1st May 2025 (may continue until the 13th June 2025).

Alternative route is via: Lynn Road, Lynn Road, Church Lane, Westgate Street, Fakenham Road, New Road, Eastgate Street, The Green.

The works promoter is Anglian Water.

TERRINGTON ST JOHN – Old Church Road from 30m west of its junction with School Road for 30m westwards to facilitate water works from 30th April to 2nd May 2025 (may continue until 13th June 2025).

Alternative route is via: School Road, Old Church Road, School Road, Church Road.

The works promoter is Anglian Water.

THETFORD – London Road from its junction with St Barnabas Close to 25m southwards to facilitate drainage works from 29th April to 1st May 2025 (may continue until 11th June 2025).

Alternative route is via: St Barnabas Close, London Road.

The works promoter is Anglian Water.

THETFORD – London Road – Junction with London Road and Station Lane to facilitate carriageway resurfacing works between 20:00 and 06:00 from 28th to 30th April 2025.

Alternative route is via: A134 Brandon Road, A11 Trunk Road, A1065 Mundford Road, A1065 Thetford Road, A1065 Norwich Road, A1065 London Road, London Road, Croxton Road, Mundford Road, London Road.

The works promoter is Norfolk County Council.

THOMPSON – College Road from 50m south of its junction with Butters Hall Lane for 30m southwards to facilitate drainage works between 30th April and 1st May 2025 (may continue until 13th June 2025).

Alternative route is via: College Road, Thompson Road, Hall Lane.

The works promoter is Anglian Water.

THURTON – Loddon Road from 60m west of its junction with Ashby Road to 60m eastwards to facilitate verge maintenance works from 30th April to 1st May 2025.

The works promoter is Norfolk County Council.

TROWSE WITH NEWTON – White Horse Lane from its junction with The Street for 15m westwards to facilitate a service box lid exchange works between 09:30 and 15:30 on 2nd May 2025 (may continue until 13th June 2025).

Alternative route is via: The Street, Newton Close, White Horse Lane, Dell Wellington Road, Dunham Road (Trowse, Intwood, Keswick).

The works promoter is Anglian Water.

WAINFORD – Wainford Road from its junction with Bixley Drive to its junction with Bates Drive to facilitate verge maintenance works.

The road will be temporarily subject to a stop and go restriction from 28th to 29th April 2025 (may continue to be restricted until 10th June 2025).

Alternative route is via: N/A.

The works promoter is Norfolk County Council.

WRETTON – Field Lane from its junction with Lynn Road for 33m south westwards to facilitate carriageway patching works from 29th to 30th April 2025 (may continue until 11th June 2025).

Alternative route is via: Field Lane, Church Road, Low Road, Wretton Road, Lynn Road, Stoke Ferry, Wretton.

The works promoter is Norfolk County Council.

The following details are updates to Norfolk County Council’s West Streetworks.

AYLMERTON – Tower Road from its junction with Sandy Lane to junction with A148 Holt Road at Sandy Lane from its junction with Tower Road to its junction with A148 Holt Road to facilitate carriageway patching works between 22nd to 24th April 2025.

The road shall be temporarily subject to the suspension of the one-way weight restriction and shall be made available in both directions.

Alternative route is via: Holt Road, Sandy Lane, Station Road, Church Road, Roughton Road, Mill Road, Norwich Road, New Road, Runton Common, Station Road, Cromer Road, East Runton Common, Station Road, Cromer Road, Hobray Road, The Street (Sheringham, East Beckham, Aylmerton, Upper Sheringham, Runton, Beeston Regis).

The works promoter is Norfolk County Council.

AYLSHAM – Buckenham Road from 50m north of its junction with Palmerston Way for 35m northwards to facilitate water connection works from 22nd to 24th April 2025 (may continue until 11th June 2025).

Alternative route is via: Buckenham Road, Elvin Glazier Drive, Palmerston Way, Palmerston Way.

The works promoter is Anglian Water.

BEESTON REGIS – Esgors Lane from 30m north of its junction with Regis Avenue for 180m south westwards to facilitate pole works on 21st to 25th April 2025 (may continue until 6th June 2025).

Alternative route is via: Beehive Lane, Cromer Road, Headley Road, The Street, Sheringham, East Beckham, Upper Sheringham, Beeston Regis.

The works promoter is Openreach.

BRUNDALL – Postwick Lane from 180m west of its junction with West End Avenue for 45m westwards to facilitate pole replacement works from 21st to 24th April 2025 (may continue until 5th June 2025).

Alternative route is via: Postwick Lane, B1140 Blofield Road, Ternouth Road, South Burlingham, Norhway, A47, Cucumber Lane, Norwich Road, Brundall.

The works promoter is UK Power Networks.

BURGH AND TUTTINGTON – Burgh Road from its junction with Wood Lane for 250m north westwards to facilitate ducting installation works from 21st April to 2nd May 2025 (may continue until 11th June 2025).

Alternative route is via: The Street, Aylsham Road, Church Road, Wood Lane, Tuttington Road.

Alternative route is via: The Street, Aylsham Road, Church Road, Wood Lane, Tuttington Road, Red Beck Lane, Norwich Road, Mill Road, Aylsham Road, Burgh and Tuttington.

The works promoter is Norfolk County Council.

CROMER – From a point 97m south of its junction with A149 Cromer Road for 37m northwards to facilitate drainage works between 21st and 26th April 2025 (may continue until 5th June 2025).

Alternative route is via: A149 Cromer Road, Station Road, C292 Cabbell Road, Garden Street, Mount Street, Church Street, Jetty Street, Garden Street, New Parade, Mount Street.

The works promoter is Norfolk County Council.

DICKLEBURGH – The Street from 40m north of its junction with Rectory Road for 40m northwards to facilitate pole replacement works between 21st and 24th April 2025 (may continue until 5th June 2025).

Alternative route is via: Rectory Road, Mill Lane, High Road, Rectory Road, Crown Green Road, Harvey Lane, Hall Lane, Rectory Road.

The works promoter is UK Power Networks.

GREAT WITCHINGHAM – 1) Heath Lane from its junction with Heath Road to its junction with Church Farm Lane and

2) Church Farm Lane from its junction with Heath Lane to its junction with Church Road to facilitate new cabling works from 21st to 25th April 2025 (may continue until 5th June 2025).

Alternative route is via: Heath Lane, Church Farm Lane, Norwich Road, The Moor, Nowhere Road, The Moor Road, B1145 Station Road (Reepham), School Road, The Moor Road, Norwich Road, Reepham Road, Heath Road (Felthorpe, Great Witchingham, Little Witchingham).

The works promoter is UK Power Networks.

HELLESDON – Hellesdon Park from its junction with Wood Road for 160m south westwards to facilitate drainage installation works between 21st and 25th April 2025 (may continue until 11th June 2025).

Alternative route is via: Woodcock Road, Phyllis Road, Hellesdon Park Road, Reepham Road, Hellesdon.

The works promoter is Norfolk County Council.

HOLT – Albert Street from its junction with High Street to its junction with Bull Street to facilitate installation of cycle lane infrastructure and carriageway patching works between 21st to 25th April 2025 (may continue until 5th June 2025).

Alternative route is via: High Street, White Lion Street, Bull Street, Market Place, New Street, Fish Hill, Albert Street.

The works promoter is Norfolk County Council.

HONINGHAM – The Street from its junction with Colton Road for 110m westwards to facilitate highway investigation works on 25th to 26th April 2025 (may continue until 5th June 2025).

Alternative route is via: The Street, Dereham Road, Rectory Road, Colton Road (Honingham, East Tuddenham).

The works promoter is Norfolk County Council.

LINGWOOD AND BURLINGHAM – Buckenham Road from its junction with Acle/Beighton Lane for 30m eastwards to facilitate new water connection works from 22nd to 26th April 2025 (may continue until 5th June 2025).

Alternative route is via: Buckenham Road, Main Road, Buckenham Road, Long Lane, Stone Road, Low Road, Wood Lane, Hassingham Road, Thrumpton Road (Lingwood and Burlingham).

The works promoter is Anglian Water.

MARTHAM – FP4 Martham from 80m north-east of its junction with FP2 Martham for 81m north-eastwards to facilitate construction of a replacement pumping station from 24th April 2025 to 28th October 2025.

Alternative route is via: N/A.

The works promoter is BAM Nuttall.

NORTH WALSHAM – Lyngate Road from 30m east of its junction with Bradfield Road to its junction with A149 Cromer Road to facilitate drainage and cabling works from 22nd April to 26th April 2025 (may continue until 10th November 2025).

Alternative route is via: Lyngate Road, Bradfield Road, Field Lane, Paston Road, Bradfield Road, Lyngate Road (North Walsham).

The works promoter is Norfolk County Council.

NORTH WALSHAM – Cromer Road from its junction with North Walsham Road to its junction with Morton Close to allow safety camera installation.

The works are expected to take place from 22nd April to 29th April 2025 (may continue until 30th April 2025).

Previously used as TTRO No. 21, 2021.

The works promoter is Norfolk County Council.

GREAT YARMOUTH ST MARGARET WITH SCARBAY – Yarmouth Road 20m west of its junction with New Scotia Road for 110m eastwards to facilitate electrical connection works from 22nd to 26th April 2025 (may continue until 5th June 2025).

Alternative route is via: Yarmouth Road, North Road, Scarborough Road, North Road, Yarmouth Road, Station Road, Station Road, Station Road, Yarmouth Road.

The works promoter is UK Power Networks.

SHERINGHAM – Morris Street from its junction with The Street for 25m to facilitate new water connection works from 24th to 26th April 2025 (may continue until 5th June 2025).

Alternative route is via: Augusta Street, Church Street, Church Road, Holt Road, Redferns Road, Redfords Road, South Street, Sheringham Road, Grove Street, Augusta Street.

The works promoter is Anglian Water.

SHERINGHAM – Augusta Street from 30m north of its junction with Church Road for 30m northwards to facilitate new water connection works on 24th April 2025 (may continue until 5th June 2025).

Alternative route is via: Augusta Street, Redfords Road, Redfords Road, Redfords Road, Lucien Road, West Street, Holt Road, Holt Road, Holt Road (Sheringham, East Beckham, Upper Sheringham, Beeston Regis).

The works promoter is Anglian Water.

SOMERTON – Horsey Road from its junction with The Street for 25m eastwards to facilitate drainage works on 24th to 26th April 2025 (may continue until 5th June 2025).

Alternative route is via: Horsey Road, West Somerton Road, Winterton Road, West Somerton Road, The Grange, Kingway, Winterton Road, Buller Lane, Somerton Road, Winterton Road, Park Lane, East Somerton, Somerton, Winterton-on-Sea.

The works promoter is Norfolk County Council.

WELLS-NEXT-THE-SEA – Marsh Lane from its junction with Polka Road for 50m south-eastwards to facilitate stop tap works from 22nd to 24th April 2025 (may continue until 5th June 2025).

Alternative route is via: Mill Road, Aldeburgh Road, East Quay.

The works promoter is Anglian Water.

The following details are updates to Norfolk County Council’s North Streetworks.

HALLS GREEN – High Street from 25m south of its junction with The Street for 40m northwards to facilitate stop tap works from 24th to 26th April 2025 (may continue until 5th June 2025).

Alternative route is via: High Street, Valence Road, South Lane.

The works promoter is UK Power Networks.

DICKLEBURGH AND RUSHALL – Harvey Lane from its junction with C592 The Street for 25m eastwards to facilitate pipe repair works from 23rd to 25th April 2025 (may continue until 5th June 2025).

Alternative route is via: Harvey Lane, Hall Lane, Common Road, Ipswich Road, The Street.

The works promoter is Anglian Water.

Need to publish a public notice?

If you need to publish a public notice, please contact Eastern Daily Press directly at:

ec.publicnotices@localiq.co.uk

01603 772636

About Us

The Public Notice Portal is owned and operated by the News Media Association, the voice of UK national, regional, and local newspapers in all their print and digital forms. NMA members include nearly 900 local and regional news titles which reach 40 million people across the length and breadth of the country each month.

Public Notice PortalNews Media Association