Kingston upon Thames, Multiple Traffic Notices, Temporary Road Closures
What is happening?
ROYAL BOROUGH OF KINGSTON UPON THAMES
ROAD TRAFFIC REGULATION ACT 1984 – SECTION 14(1)
The Council of the Royal Borough of Kingston upon Thames hereby gives notice that in order to facilitate a gas mains replacement and because these works are being executed on or near the carriageway it intends to make an Order the effect of which is summarised in paragraph 3 below.
The Order will come into effect on Monday 19th May 2025 and is expected to take 55 days to complete, however the Order will remain in force for 18 months to be re-introduced should further works be required.
When the works are taking place and the appropriate traffic signs are displayed the Order will temporarily prohibit all vehicular traffic including pedal cycles from entering, exiting, stopping or proceeding in: • Cotsford Avenue at the junction with South Lane.
• Lynton Road at the junction with South Lane.
An alternative route for vehicular traffic whilst the prohibition is in place will be via either; - – South Lane, Thetford Road, Windsor Avenue and vice versa.
– South Lane, Nelson Road, Westbury Road and vice versa.
Vehicles access to properties adjacent to the prohibited length of road will be maintained at all times insofar as access is reasonably practicable without interference with the said works.
The prohibitions specified above apply only during such times and to such extent as indicated by traffic signs prescribed by the Traffic Signs Regulations and General Directions 2016.
Dated: 14th April 2025
ALI ATAIE
Corporate Head of Highways and Transport (Interim)
How long will it take?
Planned start
19-May-2025
Estimated end
13-Jul-2025