New Kings Road - Temporary Prohibition of Traffic
What is happening?
LONDON BOROUGH OF HAMMERSMITH AND FULHAM
ROAD TRAFFIC REGULATION ACT 1984 SECTION 14(1) (NEW KINGS ROAD) TEMPORARY PROHIBITION OF TRAFFIC
1. The Council of the London Borough of Hammersmith and Fulham hereby gives notice that in order to facilitate water supply works in the above-named location; it intends to make an Order the effect of which temporarily prohibit traffic and introduce “at any time” waiting restrictions in a section of the above-named road.
2. Whilst works are in progress, or whilst the authorised traffic signs are displayed, no person shall cause or permit any vehicle to proceed in a northeast direction in New Kings Road from the junction of Harwood Terrace to No. 12 New Kings Road
3. An alternative route for traffic in article 2 shall be provided via Harwood Road, Fulham Road, Edith Grove and Kings Road.
4. Exemptions would be provided in the Order to permit reasonable access to premises, so far as it is practical without interference with the execution of the said work and for works vehicles, any vehicle being used in connection with police, fire or ambulance purposes and anything done with the permission or at the direction of a police constable in uniform.
5. The Order would come into operation on the 24th May 2025 and would be valid for a maximum period of 18 months or until works are completed, whichever is the sooner.
6. Works would be expected to commence on Saturday 24th February 2025 and last until 25th February 2025.
The dates specified are for guidance and informative purposes only and works may extend outside these dates.
Dated this 17th day of April 2025
John Galsworthy Director of Climate Change and Transport Public Realm