Flintshire, Stopping Up Of Public Footpath To Facilitate Development
What is happening?
Deddf Cynllunio Gwlad a Thref 1990 (Fel y’i Diwygwyd)
GORCHYMYN CAU PRIFFYRDD (LLWYBR TROED O FEWN GWAITH SMENT PADESWOOD, CHESTER ROAD, YR WYDDGRUG, SIR Y FFLINT) 2025
Mae Gweinidogion Cymru wedi gwneud Gorchymyn o dan adran 247 o Ddeddf Cynllunio Gwlad a Thref 1990 ("Deddf 1990") i awdurdodi cau darn o briffordd a ddisgrifir yn Atodlen 1 i’r Hysbysiad hwn a ddangosir ar y cerbydwr clwm â’r Gorchymyn fel y’i hysbysebir. Nid yw awdurdodi’r cau’r briffordd o dan y ffurf y mae’r Gorchymyn yn ei chael ar hyn o bryd yn cael ei roi oni bai fod ar ran 3 o Ddeddf 1990 gan Weinidogion Cymru ar 4/4/2025 o dan y cyfeirnod DNS-CAS-02009-W1R127 a ddisgrifir yn Atodlen 3 i’r Hysbysiad hwn.
Bydd Gorchymyn Cau Priffyrdd (Llwybr Troed o fewn Gwaith Sment Padeswood, Chester Road, yr Wyddgrug, Sir y Fflint) 2025 (“y Gorchymyn”), os caiff ei wneud, yn peidio â chael effaith os daw’r caniatâd cynllunio mewn cysylltiad â’r datblygiad i ben neu os caiff ei diddymu.
Gellir edrych ar gopi o’r Gorchymyn ar fap a enwir o dan ac am ddim yn:
Flintshire County Council, Ty Dewi Sant, St. Davids Park, Ewloe CH5 3FF
Mae dogfennau’r cais i’w gweld ar y wefan:
https://planningcasework.service.gov.wales/ - a chwiliwch am CAS-02009-W1R127
Caiff unrhyw berson a dramgwyddir gan y Gorchymyn, ar y sail:
a. nad yw o fewn pwerau Deddf 1990; neu
b. na chydymffurfir ag un o ofynion gweinyddu’r Ddeddf 1990;
ofyn i Weinidogion ar 4/4/2025, wneud cais i’r Uchel Lys y tu
dolen hwnnw.
Caiff ceisiadau o’r goruchaf i’w gwneud i’r Uchel Lys yng Nghymru gan:
Administrative Court at Cardiff Civil Justice Centre, 2 Park Street, Cardiff CF10 1ET
Ers cofrestru: Isabel Nethell, Pennaeth Gweithrediadau
Dyddiad: 04/04/2025
ATODLEN 1
(Darn ac yn bob mesur)
Y darn o briffordd sydd i’w gau
Darn o lwybr troed i’r de o Waith Sment Padeswood, a elwir yn PROW 301/56/20 yn yr Wyddgrug, Sir y Fflint, sy’n 437.7 o fetrau y’n man hiraf ac yn 2 fetrau yn man lleiaf, sy’n ymestyn o bwyntiau A i B a ddangosir ar y planiau a anedwyd.
ATODLEN 2
(Darn ac yn pob mesur)
Y darn o briffordd newydd sydd i’w ddarparu
Darn o lwybr troed i’r de o Waith Sment Padeswood, Chester Road, yr Wyddgrug, Sir y Fflint sy’n 385.3 o fetrau yn man hiraf ac yn 2 fetrau yn man lleiaf, sy’n ymestyn o bwyntiau D i C a ddangosir ar y planiau a anedwyd.
Mae’n debyg y bydd carbon ôl-hylosgi ynni’r safle gwares a phwer cyfleu’n cael ei ddefnyddio mewn cysylltiad erbyn nagl Waith Sment Padeswood, Chester Road, yr Wyddgrug, Sir y Fflint.
Town and Country Planning Act 1990 (As Amended)
THE STOPPING UP OF HIGHWAYS (FOOTPATH WITHIN PADESWOOD CEMENT WORKS, CHESTER ROAD, MOLD, FLINTSHIRE) ORDER 2025
The Welsh Ministers have made an Order under section 247 of the Town and Country Planning Act 1990 (“the 1990 Act”) to authorise the stopping up of the lengths of highway described in Schedule 1 to this Notice and to provide for the lengths of new highway described in Schedule 2 to this Notice. The stopping up will be authorised only in order to enable the development to be carried out in accordance with planning permission granted under Part 3 of the 1990 Act on 4/4/2025 with reference number DNS CAS-02009-W1R127, as described in Schedule 3.
The Stopping Up of Highways (Footpath within Padeswood Cement Works, Chester Road, Mold, Flintshire) Order 2025 (“the Order”), will cease to have effect if planning permission in respect of the development expires or is revoked.
Copies of the Order and the deposited plan may be inspected free of charge at:
Flintshire County Council, Ty Dewi Sant, St. Davids Park, Ewloe CH5 3FF
or may be viewed online via the planning casework portal: https://planningcasework.service.gov.wales/ - Search for CAS-02009-W1R127
If a person is aggrieved by the Order, on the grounds that:
a. it is not within the powers of the 1990 Act; or
b. a procedural requirement of the 1990 Act has not been complied with;
that person may, within 6 weeks of 04/04/2025 make an application for the Order to be quashed in the High Court.
Further advice about making a High Court challenge in Wales can be obtained from:
Administrative Court at Cardiff Civil Justice Centre, 2 Park Street, Cardiff CF10 1ET
Signed: Isabel Nethell, Head of Operations
Date: 04/04/2025
SCHEDULE 1
(All measurements are approximate)
Length of highway to be stopped up
A length of footpath that is located to the south of Padeswood Cement Works, known as PROW 301/56/20 in Mold, Flintshire, with a maximum length of 437.7 metres and a maximum width of 2 metres, which extends from points A to B as shown on the deposited plans.
SCHEDULE 2
(All measurements are approximate)
Length of highway to be provided
A length of footpath located to the south of Padeswood Cement Works, Chester Road, Mold Flintshire with a maximum length of 385.3 metres and a minimum width of 2 metres, extending from points D to C shown on the deposited plans.
SCHEDULE 3
The development
The erection of a post combustion carbon capture plant, together with a combined heat and power plant and other associated plant and structures at Padeswood Cement Works, Chester Road, Mold, Flintshire.
How long will it take?
Planned start
4-Apr-2025
Estimated end
16-May-2025