Southend-on-Sea - Temporary Traffic Restrictions and Speed Limit Restrictions due to Gas Main Works

SS1 2LUPublished 13/03/25Expired
Basildon Echo • 

What is happening?

SOUTHEND-ON-SEA CITY COUNCIL

ROAD TRAFFIC REGULATION ACT 1984 – SECTION 14(1)

TEMPORARY PROHIBITION OF 40-MPH SPEED LIMIT,

SUSPENSION OF ONE-WAY TRAFFIC,

TRAFFIC RESTRICTIONS, PARKING, STOPPING, WAITING,

LOADING AND UNLOADING ORDER 2025

QUEENSWAY (A1160), SOUTHCHURCH ROAD (A13),

TYRREL DRIVE, WHITEGATE ROAD & WARRIOR SQUARE

SOUTHEND-ON-SEA

Notice is hereby given Southend-on-Sea City Council intends, no less than seven days from the date of this notice, to make the above Order under Section 14(1) of the Road Traffic Regulation Act 1984.

These works will be undertaken in phases

The effect of the Order will be to prohibit any vehicle from the following:

Phase 1

  1. Speed reduction from 40MPH to 30MPH on Queensway (A1160) from its junction with Portland Avenue to its junction with Queensway Slip Road Southwest and from its junction with Queensway Slip Road Northeast to its junction with Quebec Close.

Phase 2

  1. Proceeding along Southchurch Road (A13) from Porters Grange Roundabout to Tyrrel Drive and Sutton Road, and vice versa.
  2. Turning left from Tyrrel Drive onto Southchurch Road (A13).

Phase 3

  1. Entering and exiting Whitegate Road at both ends, from Queensway (A1160) and Chichester Road.
  2. Suspension of one-way traffic on Whitegate Road from its junction with Chichester Road to Queensway (A1160) – applicable to residents only.
  3. Parking, stopping, waiting, loading and unloading will be prohibited on Whitegate Road from outside No. 17 (north side) to Queensway (A1160).

Residents with a valid parking permit for Whitegate Road will be permitted to park in Warrior Square Car Park for the duration of these works only.

Phase 4

  1. Parking, stopping, waiting, loading and unloading will be prohibited on Warrior Square from outside No. 69 to outside No. 75.

The order is scheduled to commence from 09:30am on the 24th March 2025 or where appropriate signs are showing and weather permitting.

The alternative routes during the phases of work are:

  • Phase 2: Bournemouth Park Road, Eastern Avenue, Sutton Road or Southchurch Avenue and Queensway and vice versa.
  • Phase 3: Chichester Road, Tylers Avenue, Quebec Avenue and Queensway or Queensway, Southchurch Road and Chichester Road.

The Order will come into effect on 24th March 2025 and may continue in force for up to 18 months or until the works have been completed, whichever is the earlier.

The closure is required for the safety of the public and workforce whilst Cadent undertake Gas Main replacement works.

Access for emergency vehicles, residents and pedestrians will be maintained at all times during the closures.

The prohibitions or restrictions will only apply during such time and to such extent as indicated by traffic signs prescribed by the Traffic Signs Regulations and General Directions 2016.

Any vehicle waiting or parked in contravention of any restriction/prohibition imposed by this Notice may be issued with a Penalty Charge Notice and removed under the provisions of the Traffic Management Act 2004.

Director of Infrastructure & Environment

Southend-on-Sea City Council

Contact: TRO@southend.gov.uk

Permit Ref: AZ5021001413651

Dated: 13th March 2025

How long will it take?

Planned start

24-Mar-2025

Estimated end

24-Sept-2026

Need to publish a public notice?

If you need to publish a public notice, please contact Basildon Echo directly at:

se-sales@localiq.co.uk

01268 522792

About Us

The Public Notice Portal is owned and operated by the News Media Association, the voice of UK national, regional, and local newspapers in all their print and digital forms. NMA members include nearly 900 local and regional news titles which reach 40 million people across the length and breadth of the country each month.

Public Notice PortalNews Media Association