U2005 Adderstone Grange Junction to Outchester Junction - Temporary Road Closure
What is happening?
NORTHUMBERLAND COUNTY COUNCIL
ROAD TRAFFIC REGULATION ACT 1984 - SECTION 14(1)
U2005 ADDERSTONE GRANGE JUNCTION
TO OUTCHESTER JUNCTION BELFORD
(TEMPORARY ROAD CLOSURE) ORDER 2025
NOTICE IS HEREBY GIVEN that Northumberland County Council intends to make an Order to prohibit the use by vehicular traffic on the U2005 Adderstone Grange Junction to Outchester Junction Belford from its junction with U2008 Bradford Junction to Humbleton Hill Junction heading southwards for a distance of 1725 metres in the County of Northumberland.
The Order is to be effective from the 3rd March 2025 until the 21st March 2025.
It is expected that the road will only be closed from the 3rd March 2025 until the 14th March 2025 between the hours of 08:00 and 18:00 during this period; however, the order will remain in place until 21st March 2025.
An alternative route will be available for use whilst the TTRO is in force being via the U2008, B1341, C63, C65, U2014, C62 and vice-versa. Should the need arise changes may be made to the alternative routes, where possible these changes will be signposted accordingly.
Enquiries should be made to Northumberland County Council’s Contact Centre 0345 600 6400 or at https://one.network (enter the road number and road name). – Ref:141612623
The closure has been requested by Go Fibre to carry out mole ploughing and box installation for the installation of fibre cabling. In order to minimise future disruption, other contractors may be undertaking works throughout the duration of this Order.
Dated this 13th day of February 2025.
How long will it take?
Planned start
3-Mar-2025
Estimated end
14-Mar-2025
Need to publish a public notice?
If you need to publish a public notice, please contact Northumberland Gazette directly at: