Worcestershire, Multiple Roads, Temporary Prohibitions & Restrictions
What is happening?
WORCESTERSHIRE COUNTY COUNCIL
PUBLIC NOTICE
Road Traffic Regulation Act 1984
(U23410 Wilmore Lane, Wythall) (Temporary Closure) Order 2025
Order made: To close that part of U23410 Wilmore Lane from its junction with U23409 Wilmore Lane to its junction with C2040 Middle Lane Roundabout.
Reason: Carriageway patching by WCC.
Alternative route: C2040 Middle Lane, C2036 Silver Street, U23409 Wilmore Lane and vice versa.
Maximum duration: 18 Months. Anticipated duration: 1 day between 12 February 2025 and 28 February 2025.
(U23613 Alderhanger Lane, Beoley) (Layby Closure Only) (Temporary Closure) Order 2025
Order made: To close that part of U23613 Alderhanger Lane from its junction with A435 Alcester Road for its entire length.
Reason: Large air valve installation by Severn Trent Water.
Alternative route: No diversion route available, layby closure only.
Maximum duration: 18 Months. Anticipated duration: 5 days. Commencing: 7 February 2025.
(U23403 Batemans Lane, Hollywood) (Temporary Closure) Order 2025
Order made: To close that part of U23403 Batemans Lane from its junction with U23402 Packhorse Lane to its junction with C2036 Silver Street.
Reason: Carriageway resurfacing by WCC.
Alternative route: U23402 Packhorse Lane, C2180 Alcester Road, C2036 Silver Street and vice versa.
Maximum duration: 18 Months. Anticipated duration: 1 day between 12 February 2025 and 28 February 2025.
(U23403 Baccabox Lane, Hollywood) (Temporary Closure) Order 2025
Order made: To close that part of U23403 Baccabox Lane from its junction with C2171 Dark Lane to its junction with U23402 Packhorse Lane.
Reason: Carriageway patching for surface dressing over multiple phases by WCC.
Alternative route: U23402 Packhorse Lane, C2180 Alcester Road, C2171 Dark Lane and vice versa.
Maximum duration: 18 Months. Anticipated duration: 1 day between 12 February 2025 and 28 February 2025.
(A435 Alcester Road, Wythall) (Temporary Closure) Order 2025
Proposed Order: To close that part of A435 Alcester Road from its junction with A435 Alcester Road to its junction with C2042 Watery Lane.
Reason: Manhole cover replacement by Severn Trent Water.
Alternative route: A435 Alcester Road (part), C2001 Hill Lane, C2042 Watery Lane and vice versa.
Maximum duration: 18 Months. Anticipated duration: 1 day. Commencing: 27 February 2025.
(B4090 Alcester Road, Feckenham) (Temporary Closure) Order 2025
Order made: To close that part of B4090 Alcester Road from its junction with C2038 High Street to its junction with U30012 Moors Lane.
Reason: New customer connection by Cadent Gas.
Alternative route: B4090 Alcester Road (part), B4090 Droitwich Road, B4090 Feckenham Road, B4090 Droitwich Road, B4090 Hanbury Road, B4090 Salt Way, B4090 Worcester Road, A38 Worcester Road, A38 Droitwich Road,A4538 Pershore Lane, A4538 Pershore Roundabout, A4538 Pershore Lane, A422 Alcester Road, A422 Worcester Road, B4092 Alcester Road to Mile Post Lane, B4092 Mile Post Lane To Edgiock Cross Roads, B4090 Salt Way, B4090 The Saltway and vice versa.
Maximum duration: 18 Months. Anticipated duration: 5 days. Commencing: 10 February 2025.
(C2171 Dark Lane, Hollywood) (Temporary Closure) Order 2025
Order made: To close that part of C2171 Dark Lane from its junction with C2040 Middle Lane to its junction with C2180 Alcester Road.
Reason: Carriageway patching by WCC.
Alternative route: C2040 Middle Lane, C2036 Silver Street, C2180 Alcester Road and vice versa.
Maximum duration: 18 Months. Anticipated duration: 2 days between 12 February 2025 and 28 February 2025.
(U23406 Headley Heath Lane, Headley Heath) (Temporary Closure) Order 2025
Proposed Order: To close that part of U23406 Headley Heath Lane from its junction with C2170 Icknield Street to its junction with U23408 Bell Green Lane.
Reason: Carriageway patching for surface dressing over multiple phases by WCC.
Alternative route: C2170 Icknield Street, U23408 Bell Green Lane and vice versa.
Maximum duration: 18 Months. Anticipated duration: 1 day between 3 March 2025 and 19 March 2025.
(B4090 Salt Way, Astwood Bank) (Temporary Closure) Order 2025
Proposed Order: To close that part of B4090 Salt Way from its junction with Brandheath Lane (NSG ref. 45400164) for a distance of 150 metres in a westerly direction.
Reason: New customer connection by Severn Trent Water.
Alternative route: B4090 Salt Way (part), A441 The Ridgeway, B4092 Edgioake Lane, B4090 Salt Way (part) and vice versa.
Maximum duration: 18 Months. Anticipated duration: 3 days. Commencing: 4 March 2025.
(U30022 Foregate Street, Astwood Bank) (Temporary Closure) and The Redditch Urban District Council (Foregate Street) (One Way) Experimental Traffic Order 1965 (Temporary Suspension) Order 2025
Proposed Order: To close that part of U30022 Foregate Street from its junction with Dewsbury Close (NSG Ref31101396) to its junction with U30023 Butler Street and to temporarily suspend The Redditch Urban District Council (Foregate Street) (One Way) Experimental Traffic Order 1965 to allow two-way traffic to be able to access residents and businesses for the duration of the Order.
Reason: Remedial works by Severn Trent Water.
Alternative route: U30022 Retreat Street, A441 Evesham Road, C2038 Feckenham Road and vice versa.
Maximum duration: 18 Months. Anticipated duration: 2 days. Commencing: 3 March 2025.
(U30018 New Road, Astwood Bank) (Temporary Closure) Order 2025
Proposed Order: To close that part of U30018 New Road from its junction with U30015 Avenue Road to its junction with A441 Evesham Road.
Reason: Dropped kerb for new vehicle crossing by WCC.
Alternative route: U30018 New Road (part), U30015 Avenue Road, A441 Evesham Road, U30018 New Road (part) and vice versa.
Maximum duration: 18 Months. Anticipated duration: 3 days. Commencing: 4 March 2025.
(U33417 Harport Road, Redditch) (Temporary Closure) Order 2025
Order made: To close that part of U33417 Harport Road from its junction with U33416 Oakenshaw Road for its entire length.
Reason: Carriageway patching by WCC.
Alternative route: U33416 Oakenshaw Road and vice versa.
Maximum duration: 18 Months. Anticipated duration: 2 days between 11 February 2025 and 21 February 2025.
U23606 Carpenters Hill, Beoley) (Temporary Closure) Order 2025
Order made: To close that part of U23606 Carpenters Hill from its junction with C2175 Seafield Lane to its junction with B4101 Beoley Lane.
Reason: Resurfacing and patching works by WCC.
Alternative route: C2175 Seafield Lane, B4101 Beoley Lane and vice versa.
Maximum duration: 18 Months. Anticipated duration: 2 days between 10 February 2025 and 24 February 2025.
EXEMPTIONS: TO PERMIT ACCESS TO ANY LAND OR PREMISES FRONTING THE HIGHWAY AFFECTED WHERE THERE IS NO OTHER FORM OF ACCESS; AND TO ALLOW THE WORKS TO BE UNDERTAKEN.
THOMAS POLLOCK, Head of Commercial Law, (Legal and Governance) Services, County Hall, Spetchley Road, Worcester WR5 2NP
5 February 2025
Need to publish a public notice?