U66 New Haggerston Junction - Temporary Road Closure
What is happening?
NORTHUMBERLAND COUNTY COUNCIL
ROAD TRAFFIC REGULATION ACT 1984 - SECTION 14(1)
U66 NEW HAGGERSTON JUNCTION
TO HAGGERSTON JUNCTION LOWICK
(TEMPORARY ROAD CLOSURE) ORDER 2025
NOTICE IS HEREBY GIVEN that Northumberland County Council intends to make an Order to prohibit the use by vehicular traffic on that section of the U66 New Haggerston Junction to Haggerston Junction Lowick from its junction with the C17 heading in an easterly direction for a length of 800 metres in the County of Northumberland.
The Order is to be effective from the 12th February 2025 until the 28th April 2025.
It is expected that the road will only be closed from the 12th February 2025 until the 14th March 2025 between the hours of 08:00 until 18:00 during this period; however, the order will remain in place until 28th April 2025.
An alternative route will be available for use whilst the TTRO is in force being C17, A1 and vice-versa and should the need arise changes may be made to the alternative routes, where possible these changes will be signposted accordingly.
Enquiries should be made to Northumberland County Council’s Contact Centre 0345 600 6400 or at https://one.network (enter the road number and road name). – Ref:141749468
The closure has been requested by National Highways to construct a new weather station. In order to minimise future disruption, other contractors may be undertaking works throughout the duration of this Order.
DATED this 23rd day of January 2025.
How long will it take?
Planned start
12-Feb-2025
Estimated end
14-Mar-2025
Need to publish a public notice?
If you need to publish a public notice, please contact Northumberland Gazette directly at: