A14 Trunk Road (Thrapston, Northamptonshire to Brampton, Cambridgeshire) - Temporary Restrictions for Maintenance Works

NN14Published 23/01/25Expired
Northamptonshire Telegraph • 

What is happening?

ROAD TRAFFIC REGULATION ACT 1984 – SECTION 14(1)(A) AND (7)

THE A14 TRUNK ROAD (JUNCTION 13 THRAPSTON, NORTHAMPTONSHIRE TO JUNCTION 22 BRAMPTON, CAMBRIDGESHIRE)

(TEMPORARY RESTRICTION AND PROHIBITION OF TRAFFIC) ORDER 2025

NOTICE IS HEREBY GIVEN that National Highways Limited(a) has made an Order on the A14 Trunk Road (“the A14”) in the Counties of Northamptonshire and Cambridgeshire to allow for drainage improvement works, carriageway reconstruction and resurfacing, renewal of road markings and studs and safety barrier replacements to be carried out in safety.

The works are expected to start on, or after, Monday 3 February 2025 and last for approximately 14 weeks. There will be some full weekend closures (8pm Friday to 6am Monday) starting on or after Friday 7 February 2025.

The closures and speed restrictions will be applied only to the extent that is necessary for particular works to be undertaken and will only apply during such times and to such extent as shall be indicated by traffic signs. The effect of the Order on the A14 will be to –

1.   impose, for 24 hours daily, in conjunction with narrow lanes, a speed limit of 40 miles per hour or 50 miles per hour, with no overtaking, on the eastbound and westbound carriageways from Bythorn accommodation overbridge to Belton’s Hill Overbridge, Spaldwick.

2.   Close, alternately, the A14 -

•     eastbound carriageway from the exit slip road at Junction 13 Thrapston Interchange to the entry slip road at Junction 22 Brampton Interchange, including all entry and exit slip roads, and

•     westbound carriageway from the exit slip road at Junction 22, Brampton Interchange to the entry slip road at Junction 13 Thrapston Interchange, including all entry and exit slip roads.

During the carriageway closures eastbound traffic will be diverted at J13 via the A605, A1(M) southbound at J17 and A1 to re-join the A14 at Brampton Hut Interchange; Non-motorway traffic will follow this diversion but at A1(M) J17 continue via A1139 Fletton Parkway, A1260, A15, B1043 and A1 southbound to re-join the A14 at Brampton Hut Interchange; vice versa for westbound traffic.

During the slip road closures at J16 local traffic wishing to enter the A14 will be diverted via the B660 and B662 to join the diversion route above. Traffic wishing to exit will continue to the next open junction to exit,  then return via the opposite carriageway back to J16 and continue  their journey.

During any other slip road closures traffic will be diverted via junctions of the A14 and local roads.

Access to or from the A14 from various side roads adjacent to the length of A14 described at 2 above will be restricted at times and local diversions will be in place. Access to properties fronting the A14 will be maintained at all times by escort during the works.

All laybys adjacent to, and all gaps located within the central reservation of, the carriageway described at 2 above will be closed for 24 hours daily for the duration of the works.

A vehicle width restriction of 2.1 metres (6’ 9”) will be imposed in the outside lane of the length of carriageway described at 1 above when narrow lanes are in operation.

The temporary mandatory speed limits (which will not apply to emergency service or special force vehicles), closures (which will not apply to emergency service, traffic officer, works or winter maintenance vehicles) and diversion routes will be clearly indicated by traffic signs.

The Order will come into force on 27 January 2025 and may continue in force until the works detailed above have been completed, or for a maximum duration of eighteen months, whichever is the earlier.

L Walton, National Highways Limited (a) Registered in England and Wales under company no. 9346363. Registered Office: Bridge House, Walnut Tree Close, Guildford, Surrey, GU1 4LZ.

General Enquiries relating to this notice may be made in writing to  Rachel Harley at National Highways Limited, Woodlands, Manton Lane, Bedford, MK41 7LW by telephoning 07927 578607 or email  rachel.harley@nationalhighways.co.uk

How long will it take?

Planned start

3-Feb-2025

Estimated end

12-May-2025

Need to publish a public notice?

If you need to publish a public notice, please contact Northamptonshire Telegraph directly at:

publicnotices@nationalworld.com

02070237931

About Us

The Public Notice Portal is owned and operated by the News Media Association, the voice of UK national, regional, and local newspapers in all their print and digital forms. NMA members include nearly 900 local and regional news titles which reach 40 million people across the length and breadth of the country each month.

Public Notice PortalNews Media Association