Warwickshire County Council ROAD TRAFFIC REGULATION ACT 1984
What is happening?
Warwickshire County Council has made the following Temporary Traffic Orders:
MILL LANE, BROOM
Order Effect: Road closed to vehicular traffic.
Reason for Order: Works to repair/replace manhole frame and cover.
Order Commences: 24 January 2025 for up to 18 months.
Anticipated Completion: 24 January 2025.
Access & Diversion: Mill Lane, Bidford Road, High Street and vice versa.
Contractor: Customer Solutions Plus, Tel: 07918 298 599.
NEW ROAD, STUDLEY
Order Effect: Road Closed to vehicular traffic.
Reason for Order: To enable installation of a Boundary Box.
Order Commences: 22 January 2025 for up to 18 months.
Anticipated Completion: 23 January 2025.
Access & Diversion: New Road, Toms Town Lane, Alcester Road and vice versa.
Contractor: Chevron Traffic Management Ltd, Tel: 03300 080 820.
SHERWELL DRIVE, ALCESTER
Order Effect: Road Closed to vehicular traffic.
Reason for Order: To enable works to clear blockage.
Order Commences: 20 January 2025 for up to 18 months.
Anticipated Completion: 25 January 2025.
Access & Diversion: No Diversion available.
Contractor: OCU Group, Tel: 07341 784 057.
SPERNAL LANE, SPERNALL
Order Effect: Road closed to vehicular traffic.
Reason for Order: Works for electricity supply alteration and reinforcement.
Order Commences: 20 January 2025 for up to 18 months.
Anticipated Completion: 31 January 2025.
Access & Diversion: Spernal Lane, Spernall Lane, School Road, Captains Hill, Kinwarton Road, Kinwarton Farm Road, Tything Road West, Arden Road, Birmingham Road, Willoughby Close, Coughton Hill, Haydon Way and vice versa.
Contractor: Doocey Group, Tel: 07989 700 548.
Warwickshire County Council proposes to make the following Temporary Traffic Orders:
ALLIMORE LANE, ALCESTER
Order Effect: Road closed to vehicular traffic.
Reason for Order: To safely enable works for water pipe renewal.
Order Commences: 3 February 2025 for up to 18 months.
Anticipated Completion: 5 February 2025.
Access & Diversion: No diversion available.
Contractor: Chevron Traffic Management, Tel: 03300 080 820.
MEETING LANE, ALCESTER
Order Effect: Road closed to vehicular traffic.
Reason for Order: Works to renew boundary box, closed 08.00hrs-17.00hrs.
Order Commences: 5 February 2025 for up to 18 months.
Anticipated Completion: 5 February 2025.
Access & Diversion: No diversion available.
Contractor: Chevron Traffic Management Ltd, Tel: 03300 080 820.
For all of the above temporary orders, pedestrian access to and egress from properties and land situated adjacent to the length of road to be closed will be maintained at all times. Vehicular access will be maintained where possible.
To report any problems with these works or for further details of our current & planned roadworks visit our website warwickshire.gov. uk/roadworksmap or call us 01926 412515.
THE WARWICKSHIRE COUNTY COUNCIL ULLENHALL LANE, ULLENHALL, STRATFORD- UPON-AVON
Warwickshire County Council proposes, under section 90A of the Highways Act 1980, to install one road hump on Ullenhall Lane, Ullenhall as described in the Schedule below.
A plan showing the location of the proposed hump together with a statement of the Council’s reasons for this proposal, may be inspected at Shire Hall, Warwick or online at https:/Awww.warwickshire. gov.uk/news/20209/stratford-avon-district.
Any objections or representations to the proposal, which must be in writing and specify the grounds on which they are made, should be addressed to Graham Stanley, Communities, Shire Hall Post Room, Rear of Shire Hall, Northgate Street, Warwick, CV34 4RL, or sent by email to grahamstaniey@
warwickshire.gov.uk. (Objections, representations, and the name of the objector or person making a representation, will normally be treated as public information, and may be published. For further information on how Warwickshire County Council processes personal data please refer to the Customer Privacy Notice which is available at
https://www.warwickshire.gov.uk/privacy). Objections and representations must be sent so as to be received by 7 February 2025.
SCHEDULE
Ullenhall Lane, Ullenhall
1 x raised road hump feature to be positioned on Ullenhall Lane, approximately 125 metres west of its junction with Forde Hall Lane, measuring approximately 5.5 metres (length) x 6.2 metres (width) x 75mm (height)
S Duxbury, Director of Strategy,
Planning & Governance,
Shire Hall, Warwick CV34 4RL Date 17 Jan 2025