Cornhill-On-Tweed Various Roads - Temporary Road Closures
What is happening?
NORTHUMBERLAND COUNTY COUNCIL
ROAD TRAFFIC REGULATION ACT 1984 - SECTION 14(1)
C21 WEST LEARMOUTH JUNCTION TO BARELESS JUNCTION, BRANXTON AND C20 MINDRUM MILL JUNCTION TO CORNHILL JUNCTION, CORNHILL-ON-TWEED
(TEMPORARY ROAD CLOSURE) ORDER 2024
NOTICE IS HEREBY GIVEN that Northumberland County Council intends to make an Order to prohibit the use by vehicular traffic on the following sections of highways in the County of Northumberland.
C21 West Learmouth Junction To Bareless Junction from its junction with A697 Between Milfield and Cornhill heading westwards for a distance of 1710 metres.
The alternative route for vehicular traffic will be via the A697, A698, C20 and vice-versa C20 Mindrum Mill Junction To Cornhill Junction from its junction with C21 West Learmouth Junction To Bareless Junction heading south westwards for a distance of 150 metres.
C20 Mindrum Mill Junction To Cornhill Junction from its eastwards junction with the C23 County Boundary To East Learmouth heading westwards for a distance of 65 metres.
The alternative route for vehicular traffic will be via the C21, U1002, C23 and vice-versa.
C20 Mindrum Mill Junction To Cornhill Junction from its westwards junction with C23 County Boundary To East Learmouth heading southwards for a distance of 2111 metres
The alternative route for vehicular traffic will be via the C20, B6352, C30, C29, C23 and vice-versa.
The Order is to be effective from the 29th November 2024 until the 20th December 2024
It is expected that the road will only be closed from the 29th November 2024 until the 12th December 2024 between the hours of 08:00 and 18:00 during this period; however, the order will remain in place until 20th December 2024.
Only one section of the road closures will be closed at one time.
Enquiries should be made to Northumberland County Council’s Contact Centre 0345 600 6400 or at https://one.network (enter the road number and road name). – Ref:140370947
The closure has been requested by Go Fibre to clear multiple blockages, carry out cabling, splicing and testing. In order to minimise future disruption, other contractors may be undertaking works throughout the duration of this Order.
Dated this 7th day of November 2024.
Need to publish a public notice?
If you need to publish a public notice, please contact Northumberland Gazette directly at: