Denbighshire, Temporary Road Closure Due To Overhead Line Works
What is happening?
RHYBUDD O ORCHYMYN TRAFFIG DROS DRO
CYNGOR SIR DDINBYCH FFORDD DOSBARTH III, EYARTH I HAYMAKERS RHYBUDD O ORCHYMYN GWAHARDD TRAFFIG DROS DRO DEDDF RHEOLEIDDIO TRAFFIG FFYRDD 1984 - ADRAN 14(1)
Mae Cyngor Sir Ddinbych wedi gwneud Gorchymyn, yn gwahardd cerbydau rhag defnyddio’r ffordd Dosbarth III a elwir yn Ffordd Eyarth i Haymakers, Llanfair Dyffryn Clwyd, yn Sir Ddinbych o’i chyffordd â’r A494 i’w chyffordd â’r ffordd Dosbarth III a elwir yn Ffordd Gorsaf Eyarth o Eyarth Bach i’r A525.
Mae angen cau’r ffordd er mwyn i GT Williams wneud gwaith ar yr uwchlinell BT uchodben. Bydd mynediad ar gael i gerddwyr drwy gydol y cyfnod cau.
Bydd arwyddion i ddangos y llwybr arall ar hyd yr A494, A525.
Bydd y Gorchymyn mewn grym am gyfnod o ddeunaw mis neu hyd nes y bydd y gwaith wedi’i gwblhau, pa un bynnag sydd gynharaf. Bydd y ffordd ar gau o 28 Hydref 2024 tan 1 Tachwedd 2024 rhwng 9:30 a 15:30.
Dyddiedig: 23 Hydref 2024.
Catrin Roberts, Pennaeth Gwasanaeth, Gwasanaethau Cymorth Corfforaethol – Pobl, Cyngor Sir Ddinbych, Neuadd y Sir, Ffordd Wynnstay, Rhuthun, Sir Ddinbych.
Rydym yn croesawu gohebaeth yn Gymraeg. Ni fydd unrhyw oedi wrth ymateb i ohebiaeth a dderbynnir yn Gymraeg.
NOTICE OF TEMPORARY TRAFFIC ORDER
DENBIGHSHIRE COUNTY COUNCIL CLASS III ROAD, EYARTH TO HAYMAKERS NOTICE OF TEMPORARY PROHIBITION OF THROUGH TRAFFIC ORDER ROAD TRAFFIC REGULATION ACT 1984
- SECTION 14(1)
Denbighshire County Council has made an Order prohibiting vehicles using the Class III road known as Eyarth to Haymakers Road, Llanfair Dyffryn Clwyd, in the County of Denbigh from its junction with A494 to its junction with the Class III road known as Eyarth Station Road from Eyarth Bach to A525.
The closure is necessary to facilitate overhead line works by GT Williams on behalf of BT. Pedestrian access will be maintained throughout the period of closure.
The signposted alternative route will be via A494, A525.
The Order is effective for an eighteen-month period or the earlier completion of the works whichever is soonest. The period of closure is from 28th October 2024 until 1st November 2024 between the hours of 09:30 – 15:30.
Dated: 23 October 2024.
Catrin Roberts, Head of Service, Corporate Support Services People, Denbighshire County Council, County Hall, Wynnstay Road, Ruthin, Denbighshire.
We welcome correspondence in Welsh. There will be no delay in responding to correspondence received in Welsh.
How long will it take?
Planned start
28-Oct-2024
Estimated end
1-Nov-2024