A1 Heugh Head, Southwest of Cairncross -Environmental Impact Assessment - Carrieageway Resurfacing.

G1 2ADPublished 23/10/24Expired
The Scotsman • 

What is happening?

TRANSPORT SCOTLAND

A1 HEUGH HEAD, 

SOUTH WEST OF CAIRNCROSS ENVIRONMENTAL IMPACT ASSESSMENT DETERMINATION UNDER SECTION 55a OF THE ROADS (SCOTLAND) ACT 1984

The Scottish Ministers give notice that they have determined that the project to undertake carriageway resurfacing on the A1 to the south west of Cairncross is a relevant project within the meaning of section 55A of the Roads (Scotland) Act 1984 (“the 1984 Act”) as the works fall within Annex II of Directive 2011/92/EU on the assessment of certain public and private projects on the environment,  but that having regard to –

a)  the selection criteria contained in Annex III of that Directive, namely

(i)      the use of natural resources, in particular land, soil, water and biodiversity;

(ii)     the production of waste;

(iii)    pollution and nuisances;

(iv)    the risks to human health  (for example due to water contamination or air pollution),

(b)    the results of the Environmental Screening Assessment under section55A(2) of the 1984 Act,

(c)     the information set out in the Record of Determination dated 2 September 2024, available at https://www. transport.gov.scot/transportnetwork/roads/road-orders-andrecords-of-determination/#63527, 

        the project does not require an Environmental Impact  Assessment. The main reasons for the conclusion that no Environmental Impact Assessment is required are:

(a)     The works are restricted to like-for-like replacement of worn/damaged road surface, with all works restricted to made ground on the A1 carriageway;

(b)    The works are not situated in whole or in part in a “sensitive area” as listed under regulation 2 (1) of the Environmental Impact Assessment (Scotland) Regulations 1999 (as amended); and

(c)     Any potential impacts of the works are expected to be temporary,  short-term, non-significant, and limited to the construction phase. The features of the project which are envisaged to avoid or prevent significant adverse effects on the environment are:

(a)     Mitigation measures and best practice will be implemented to ensure no short-term or long-term significant negative impacts on the environment;

(b)    Containment measures of the working area will be in place to prevent debris or pollutants from entering the surrounding environment; and

(c)     Measures will be in place to ensure appropriate removal and disposal  of waste.

T WAASER

A member of the staff of  the Scottish Ministers

Transport scotland

George House

36 North Hanover Street

Glasgow G1 2AD

Need to publish a public notice?

If you need to publish a public notice, please contact The Scotsman directly at:

publicnotices@nationalworld.com

02070237931

About Us

The Public Notice Portal is owned and operated by the News Media Association, the voice of UK national, regional, and local newspapers in all their print and digital forms. NMA members include nearly 900 local and regional news titles which reach 40 million people across the length and breadth of the country each month.

Public Notice PortalNews Media Association