Warwickshire - Road closed to vehicular traffic multiple notices
What is happening?
ROAD TRAFFIC REGULATION ACT 1984 Warwickshire County Council has made the following Temporary Traffic Orders:
B4085 HONEYBOURNE ROAD, BIDFORD ON AVON Order Effect: Road closed to vehicular traffic. Reason for Order: To avoid the likelihood of danger to the public because of the severe damage to the river bridge. Order Commences: 1 September 2024 for up to 18 months. Anticipated Completion: 17 November 2024. Access & Diversion: Cleeve Road, B4085 Main Street, Blackminster, B4035 Badsey Road, A46, B439 Salford Road, B4085, High Street. Access will be maintained to adjacent properties and for emergency services only. No access will be maintained over the bridge. Contractor: Balfour Beatty, Tel: 03452 415 302.
BARTON ROAD, WELFORD ON AVON Order Effect: Road closed to vehicular traffic. Reason for Order: To enable works for 4 new water connections. Order Commences: 3 September 2024 for up to 18 months. Anticipated Completion: 5 September 2024. Access & Diversion: Barton Road, Long Marston Road, Welford Road, Main Street, Pear Tree Close, Dorsington Road and vice versa. Contractor: For STW, Go Traffic Management, Tel: 01589 658 32.
CHAPEL STREET, WELFORD-ON-AVON Order Effect: Road closed to vehicular traffic. Reason for Order: Works in carriageway for new supply. Order Commences: 2 September 2024 for up to 18 months. Anticipated Completion: 6 September 2024. Access & Diversion: Millers Close, High Street, Chapel Street and vice versa. Contractor: Doocey Traffic Management, Tel: 03309 000 365.
C72 ETTINGTON ROAD AND C72 CHESTNUT SQUARE (BRIDGE STREET), WELLESBOURNE Order Effect: Road closed to vehicular traffic between Walton Road and Chapel Street/Church Walk. Reason for Order: Footway reconstruction and associated works, 09.30hrs-15.30hrs weekdays only. Order Commences: 2 September 2024 for up to 18 months. Anticipated Completion: 20 September 2024. Access & Diversion: Ettington Road, A429 Wellesbourne Bypass, Charlecote Road, Warwick Road, Bridge Street and vice versa. There will be no access/egress to/from Stratford Road and Loxley Close via Ettington Road whilst works are in progress. Contractor: Balfour Beatty, Tel: 03452 415 302.
D6677 ASCOTT ROAD (WHICHFORD ROAD), ASCOTT Order Effect: Road closed between Ascott Hill and Traitor’s Ford Lane. Reason for Order: Footway reconstruction works, closed 09.00hrs- 15.30 hrs weekdays only. Order Commences: 2 September 2024 for up to 18 months. Anticipated Completion: 9 September 2024. Access & Diversion: Green Lane, Whichford Hill, Ascott Hill and vice versa. Access/Egress to be maintained where possible to businesses and residents only. Contractor: Balfour Beatty, Tel: 03452 415 302.
OSSETTS HOLE LANE, CLAVERDON Order Effect: Road closed to vehicular traffic. Reason for Order: Works to replace jointbox frame and cover in verge. Order Commences: 2 September 2024 for up to 18 months. Anticipated Completion: 6 September 2024. Access & Diversion: Common Lane, Lye Green, Lye Green Road, The Green, Henley Road, Ossetts Hole Lane and vice versa. Contractor: Conley Utilities, Tel: 01675 446 285.
VICARAGE ROAD, WHATCOTE Order Effect: Road closed to vehicular traffic. Reason for Order: Boundary box renewal works. Order Commences: 2 September 2024 for up to 18 months. Anticipated Completion: 4 September 2024. Warwickshire County Council Access & Diversion: Whatcote Road, Brailes Road, Shipston Fields, Shipston Road, Main Street, Oxhill Road, Tysoe Road, Green Lane, The Leys, Vicarage Road and vice versa. Contractor: Chevron Traffic Management Ltd, Tel: 03300 080 820.
WEST GREEN DRIVE, STRATFORD-UPON-AVON Order Effect: Road closed between Alcester Road and Hathaway Green Lane. Reason for Order: Construct new entrance into housing development. Order Commences: 2 September 2024 for up to 18 months. Anticipated Completion: 4 October 2024. Access & Diversion: West Green Drive, Hathaway Green Lane, Alcester Road and vice versa. Contractor: Headway Traffic Management, Tel: 07593 917 813.
WEST STREET, SHIPSTON-ON-STOUR Order Effect: Road closed to vehicular traffic. Reason for Order: Full width reinstatement in carriageway. Order Commences: 2 September 2024 for up to 18 months. Anticipated Completion: 4 September 2024. Access & Diversion: West Street, Church Street, Telegraph Street, Stratford Road, Shipston Road, Fosse Way, Campden Road, Norgren Crescent and vice versa. Contractor: WMC, Tel: 07711 252 592.
Warwickshire County Council proposes to make the following Temporary Traffic Orders: 3400 NEW STREET, SHIPSTON ON STOUR Order Effect: Road closed to vehicular traffic between its junctions with Mill Street (Gyratory) and Old Road. Reason for Order: Carriageway resurfacing and associated works, 0800-1730hrs on 2 consecutive Sundays. Order Commences: 15 September 2024 for up to 18 months. Anticipated Completion: 22 September 2024. Access & Diversion: A3400, A44, A429, A3400 and vice versa. Contractor: Balfour Beatty, Tel:03452 415 302.
ARMSCOTE ROAD, ILMINGTON Order Effect: Road closed to vehicular traffic. Reason for Order: Install new water connection from mains to connection point. Order Commences: 16 September 2024 for up to 18 months. Anticipated Completion: 18 September 2024 Access & Diversion: Armscote Road, Darlingscote Road, Featherbed Lane, Washbrook Place, Front Street, Windmill Close and vice versa. Contractor: Network Plus, Tel: 01332 820 920.
A3400 BIRMINGHAM ROAD, STRATFORD UPON AVON Order Effect: One Way Traffic — All traffic will be prohibited from travelling in a northerly direction towards the Stratford Northern Bypass between Maybird island and A46 Bishopton island. Reason for Order: To enable cycleway construction works. Order Commences: 16 September 2024 for up to 18 months. Anticipated Completion: 17 November 2024. Access & Diversion: Birmingham Road, Guild Street, Warwick Road, Stratford Northern Bypass (A46). Contractor: Balfour Beatty, Tel: 03452 415 302.
BACK LANE, OXHILL Order Effect: Road closed to vehicular traffic. Reason for Order: To safely enable excavation works. Order Commences: 17 September 2024 for up to 18 months. Anticipated Completion: 18 September 2024. Access & Diversion: Back Lane, Beech Road, Main Street and vice versa. Contractor: Chevron Traffic Management Ltd, Tel: 03300 080 820.
BORDON PLACE, STRATFORD UPON AVON Order Effect: Road closed to vehicular traffic. Reason for Order: To enable works for installation of a long comm pipe. Order Commences: 16 September 2024 for up to 18 months. Anticipated Completion: 19 September 2024. Access & Diversion: Bordon Place, Evesham Road and vice versa. Contractor: For STW, GTM (Network plus), Tel: 07435 540 278.
CHURCH LANE, ALVESTON, STRATFORD UPON AVON Order Effect: Road closed to vehicular traffic. Reason for Order: Work to abandon and replace, new connections supply renewals, backfill, reinstate and clear site. Order Commences: 16 September 2024 for up to 18 months. Anticipated Completion: 27 September 2024. Access & Diversion: Kissing Tree Way, Kissing Tree Lane, The Rookery and vice versa. Contractor: Sapphire Utility Solutions, Tel: 07946 004 378.
DASSETT ROAD, AVON DASSETT Order Effect: Road closed to vehicular traffic from Lower End junction with B4100 to Lower End Water treatment plant. Reason for Order: To enable works for Bridge joint replacement. Order Commences: 16 September 2024 for up to 18 months. Anticipated Completion: 23 September 2024. Access & Diversion: Dassett Road, Lower End, Church Hill, Avon Dassett Road, Bridge Street, Northend Road, Blacksmiths Lane, Bottom Street, Village Road, Banbury Road and vice versa. Contractor: Thames Rail Ltd, Tel: 07515 067 749.
ROGERS LANE, ETTINGTON Order Effect: Road closed to vehicular traffic. Reason for Order: Works for boundary box renewal. Order Commences: 17 September 2024 for up to 18 months. Anticipated Completion: 18 September 2024 Access & Diversion: Rogers Lane, Banbury Road, Church Lane, Halford Road and vice versa. Contractor: Chevron Traffic Management Ltd, Tel: 03300 080 820.
SCHOOL LANE, COMBROOK Order Effect: Road closed to vehicular traffic. Reason for Order: To enable works for boundary box and meter installation. Order Commences: 11 September 2024 for up to 18 months. Anticipated Completion: 13 September 2024 Access & Diversion: There is no available diversion. Contractor: For STW, Chevron TM Ltd, Tel: 03300 080 820.
TELEGRAPH STREET, SHIPSTON ON STOUR Order Effect: Road closed to vehicular traffic. Reason for Order: To enable works for installation of a pipe. Order Commences: 16 September 2024 for up to 18 months. Anticipated Completion: 18 September 2024 Access & Diversion: Telegraph Street, Church Street, Station Road, The Driftway and vice versa. Contractor: For STW, Chevron TM Ltd, Tel: 03300 080 820.
TANKARDS HILL, STRETTON ON FOSSE Order Effect: Road closed to vehicular traffic from its junction with Harolds Orchard. Reason for Order: To enable works for a pipe renewal. Order Commences: 17 September 2024 for up to 18 months. Anticipated Completion: 19 September 2024. Access & Diversion: Tankards Hill, The Sharries, The Green, Church Lane, Main Street, Fosse Way, Horseley Farm Road, Campden Road and vice versa. Access for resident, commercial & pedestrians will be maintained where safe to do so. Contractor: For STW, Chevron TM Ltd, Tel: 03300 080 820.
WAWENSMERE ROAD, WOOTTON WAWEN Order Effect: Road closed to vehicular traffic. Reason for Order: To enable new supply works. Order Commences: 16 September 2024 for up to 18 months. Anticipated Completion: 20 September 2024. Access & Diversion: Wawensmere Road, Alcester Road, Stratford Road, Mayswood Road, Mays Hill, Hunger Hill, Henley Road, Oldberrow Lane, Oldberrow Road, Redditch Road, Morton Bagot Road, Wootton Wawen Road and vice versa. Contractor: For National Grid, Network Plus, Tel: 08081 642 252.
For all of the above temporary orders, pedestrian access to and egress from properties and land situated adjacent to the length of road to be closed will be maintained at all times. Vehicular access will be maintained where possible.
To report any problems with these works or for further details of our current & planned roadworks visit our website warwickshire.gov.uk/roadworksmap or call us 01926 412515.
THE WARWICKSHIRE COUNTY COUNCIL (VARIOUS STREETS, STRATFORD-UPON-AVON TOWN CENTRE) (20 MPH SPEED LIMIT) ORDER 2024 Warwickshire County Council has made the above-named Order, pursuant to the Road Traffic Regulation Act 1984, the effect of which will be to introduce a 20 mph speed limit on the lengths of road within Stratford-upon-Avon as described in the Schedule below. The Order commences on 5 September 2024. A copy of the Order, together with a plan showing the lengths of road affected and a statement of the Council’s reasons for making the Order may be inspected at the Main Reception, Shire Hall, Market Place, Warwick during usual opening hours, or online at https://www.warwickshire.gov.uk/news/20209/stratford-avon-district. Any enquiries relating to the Order may be made to Graham Stanley, County Highways Minor Works via email to pmc@warwickshire.gov.uk using the subject heading “Stratford 20mph’. Any person who desires to question the validity of the Order or of any provision contained therein on the grounds that it is not within the powers conferred by the Road Traffic Regulation Act 1984, or on the grounds that any requirement of that Act or of any instrument made under it has not been complied with in relation to the Order may within six weeks from the date of the making of the Order apply to the High Court for this purpose.
SCHEDULE (20 MPH SPEED LIMIT) The entire lengths of the following roads within Stratford-upon-Avon: Avon Meadow Close, Bridge Street, Broad Street, Broad Walk, Bull Street, Chapel Lane, Chapel Street, Cherry Street, Chestnut Walk, Church Street, College Lane, College Mews, College Street, Ely Street, Greenhill Street, Henley Street, High Street, Holtom Street, Mansell Street, Meer Street, Mill Lane, Narrow Lane, New Broad Street, New Street, Old Town, Rother Street, Ryland Street, Saffron Meadow, Saffron Walk, Sanctus Drive, Sanctus Street, Scholars Lane, Sheep Street, Southern Lane, Trinity Street, Union Street, Waterside, West Street, Windsor Street and Wood Street.
THE WARWICKSHIRE COUNTY COUNCIL (KNIGHTS LANE, TIDDINGTON) (30 & 40 MPH SPEED LIMIT) ORDER 2024 (LOXLEY ROAD/STRATFORD ROAD, LOXLEY LANE, KNIGHTS LANE, PIMLICO LANE, CHURCH LANE ALVESTON, KISSING TREE LANE ALVESTON, ALVESTON HILL, HUNSCOTE LANE AND CHARLECOTE ROAD) (50 MPH SPEED LIMIT) (ORDER 2012) (VARIATION NO.2) ORDER 2024 Warwickshire County Council has made the above-named Orders, pursuant to the Road Traffic Regulation Act 1984, the effect of which will be to replace the existing 50 mph speed limit with 40 mph and 30 mph speed limits on the lengths of road described in Schedules 1 and 2 below. The Orders commence on 4 September 2024. A copy of the Orders, together with a copy of the Order being varied, a plan showing the length of road affected and a statement of the Council’s reasons for making the Orders may be inspected at the Main Reception, Shire Hall, Market Place, Warwick during usual opening hours, or online at https:/Awww.warwickshire.gov.uk/news/20209/stratford- avon-district Any person who desires to question the validity of the Orders or of any provision contained therein on the grounds that it is not within the powers conferred by the Road Traffic Regulation Act 1984, or on the grounds that any requirement of that Act or of any instrument made under it has not been complied with in relation to the Orders may within six weeks from the date of the making of the Orders apply to the High Court for this purpose.
SCHEDULE 1 (40MPH SPEED LIMIT) Knights Lane, Tiddington From its junction with Loxley Road, northwards to a point 17 metres south of its centreline junction with Townsend Road.
SCHEDULE 2 (30 MPH SPEED LIMIT) Knights Lane, Tiddington From the centreline of its junction with Townsend Road, southwards for a distance of 17 metres (to the first street lighting column where the 30 mph speed limit then continues by virtue of street lighting). S Duxbury, Director of Strategy, Planning & Governance, Shire Hall, Warwick CV34 4RL Date 29 Aug 2024
How long will it take?
Planned start
29-Aug-2024
Estimated end
17-Nov-2024
Open to feedback
From
29-Aug-2024
To
17-Nov-2024