Park Lane - Temporary Prohibition of Driving to Allow for Excavation and New Electricity Connection to Be Installed
What is happening?
CYNGOR BWRDEISTREF SIROL CAERFFILI
Park Lane, Caerffili
Gorchymyn Gwahardd Gyrru Dros Dro 2023
HYSBYSIR drwy hyn fod Cyngor Bwrdeistref Sirol Caerffili, wrth weithredu ei bwerau o dan Ddeddf Rheoleiddio Traffig Ffyrdd 1984 (fel y’i diwygiwyd), wedi gwneud Gorchymyn a fydd â’r effaith o wahardd cerbydau rhag mynd ar hyd:
Park Lane, Caerffili, rhwng y cyffyrdd â Crescent Road a Cardiff Road am bellter o tua 190 metr.
Disgwylir i’r Gorchymyn arfaethedig gychwyn ar 24 Medi 2023 am gyfnod nid yn fwy na deunaw mis neu nes bod y gwaith wedi ei gwblhau, p’un bynnag sydd gynharaf. Disgwylir i’r gwaith gael ei gwblhau erbyn 1 Hydref 2023.
Bydd mynediad ar gael i’r gwasanaethau brys. Ni fydd mynediad ar gael i gerddwyr na phreswylwyr.
Y rheswm dros wneud y Gorchymyn yw caniatáu gwaith cloddio a gosod cysylltiad trydan newydd.
Mae angen y Gorchymyn ar National Grid Electricity Distribution
.
Gellir cael rhagor o wybodaeth gan Simon Marshall ar 01443 219027 neu smarshall@nationalgrid.co.uk yn ystod oriau swyddfa arferol.
Dyddiedig: 22 Medi 2023
Marcus Lloyd, Pennaeth Isadeiledd, Tŷ Tredomen, Parc Tredomen, Ystrad Mynach, Hengoed CF82 7WF
CAERPHILLY COUNTY BOROUGH COUNCIL
Park Lane, Caerphilly
Temporary Prohibition of Driving Order 2023
NOTICE is hereby given that Caerphilly County Borough Council in exercise of its powers under the Road Traffic Regulation Act 1984 (as amended) has made an Order the effect of which will be to prohibit vehicles from proceeding along:
Park Lane, Caerphilly between its junctions with Crescent Road and Cardiff Road for a distance of approx. 190 metres.
The proposed Order is expected to commence on 24 September 2023 for a period not exceeding eighteen months or until the works have been completed, whichever is the earlier.
It is anticipated the works will be completed by 1 October 2023.
Access for emergency services will be maintained. Pedestrian and Resident access will not be maintained.
The reason for making the Order is to allow for excavation and new electricity connection to be installed.
The Order is required by National Grid Electricity Distribution.
Further information can be obtained from Simon Marshall on 01443 219027 or by emailing smarshall@nationalgrid.co.uk during normal office hours.
Dated: 22nd September 2023
Marcus Lloyd, Head of Infrastructure, Tredomen House, Tredomen Park, Ystrad Mynach, Hengoed CF82 7WF