NOTICE OF INTENTION TO EXECUTE GENERAL VESTING DECLARATION

THE NATIONAL GRID (HINKLEY POINT C CONNECTION PROJECT) ORDER 2016

Notice is hereby given in accordance with section 3 of the Compulsory Purchase (Vesting Declarations) Act 1981 of the intention of National Grid Electricity Transmission Pic ('the Company') to acquire rights and impose restrictions over any of the land described in the Schedule to Part 1 of this notice by execution of one or more general vesting declarations.

PART 1

STATEMENT OF EFFECT OF PARTS II AND III OF THE COMPULSORY PURCHASE (VESTING DECLARATIONS) ACT 1981

Power to make general vesting declaration

1. The Company may acquire rights, and impose restrictions, over any of the land described in the Schedule below by making a general vesting declaration under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981. This has the effect, subject to paragraph 4 below, of vesting the rights and the benefit of the restrictions in the Company at the end of the period mentioned in paragraph 2 below. A declaration may not be made before the end of a period of two months from the first publication of a notice which includes this statement except with the consent in writing of every occupier of the land affected.

Notices concerning general vesting declaration

2. As soon as may be after the Company make a general vesting declaration, they must serve notice of it on every occupier of any of the land specified in the declaration (except land where there is one of the tenancies described in paragraph 3) and on every person who gives them information relating to the land in pursuance of the invitation contained in any notice. When service of notices of the general vesting declaration is completed, a further period begins to run. This period, which must not be less than 28 days, will be specified in the declaration. On the first day after the end o1 this period ('the vesting date') the rights and the benefit of the restrictions over land described in the declaration will, subject to what is said in paragraph 4, vest in the Company together with the right to enter on the land and exercise the rights or enforce the restrictions. Every person on whom the Company could have served a notice to treat in respect of his interest in the land (other than a tenant under one of the tenancies described in paragraph 3) will be entitled to claim compensation for the acquisition of rights or the imposition of restrictions over the land, with interest on the compensation from the vesting date.

Modifications with respect to certain tenancies

3. In the case of certain tenancies, the position stated above is subject to modifications. The modifications apply where the tenancy is either a 'minor tenancy', i.e. a tenancy for a year or a yearly tenancy or a lesser interest, or 'a long tenancy which is about to expire'. The latter expression means a tenancy granted for an interest greater than a minor tenancy but having on the vesting date a period still to run which is not more than the period specified in the declaration for this purpose (which must be more than a year). In calculating how long a tenancy has still to run, where any option to renew or to terminate it is available to either party, it shall be assumed that the landlord will take every opportunity open to him to terminate the tenancy while the tenant will use every opportunity to retain or renew his interest.

4. The modifications are that the Company may not exercise the right of entry referred to in paragraph 2 in respect of land subject to a tenancy described in paragraph 3 unless they first serve notice to treat in respect of the tenancy and then serve every occupier of the land with a notice of their intention to enter and exercise the rights or enforce the restrictions after the period (not less than 14 days from the service of the notice) specified in the notice. The right of entry will be exercisable at the end of that period. The vesting of the rights and the benefit of the restrictions will be subject to the tenancy until the end of that period or until the tenancy comes to an end, whichever happens first.

SCHEDULE

1 Plot Number - 101

2 Plot Description - Approximately 30.91 sqm of highway, verge and access splay known as Lampley Road

102 Approximately 19.68 sqm of highway and verge known as Nailsea Wall Lane

103 Approximately 32.69 sqm of verge and access splay west of Whitehouse Lane

104 Approximately 132.55 sqm of highway and verge known as Whitehouse Lane

Every person who, if a general vesting declaration were executed in respect of all the land comprised in the Schedule above (other than land in respect of which notice to treat has been served), would be entitled to claim compensation in respect of any such land, is invited to give information to the authority making the declaration in the prescribed form with respect to his name and address and the land in question. The relevant prescribed form is set out below.

A copy of all the plans associated with this notice can be found on the following website: https://www.nationalgrid.com/electricity-transmission/GVD

NGET North SUGVD

PART 2

FORM FOR GIVING INFORMATION

THE NATIONAL GRID (HINKLEY POINT C CONNECTION PROJECT) ORDER 2016

To: National Grid Electricity Transmission PLC, c/o Bruton Knowles Limited, Olympus House, Olympus Park, Quedgeley, Gloucester GL2 4NF

[I] [We] being [a person] [persons] who, if a general vesting declaration were made under section 4 of the Compulsory Purchase (Vesting Declarations) Act 1981 in respect of all the land comprised in the development consent order cited above in respect of which notice to treat has not been given, would be entitled to claim compensation in respect of [all] [part of] that land, give you the following information, pursuant to the provisions of section 3 of that Act.

(1) Name and address of informant(s)(i)

……………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………..

(2) Land in which an interest is held by informant(s)(ii)

………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………

(3) Nature of interest(iii)

………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………………

Signed........................................................................

[on behalf of].............................................................

Date...........................................................................

Notes

(i) In the case of a joint interest insert the names and addresses of all the informants.

(ii) The land should be described concisely.

(iii) If the interest is leasehold, the date of commencement and length of term should be given. If the land is subject to a mortgage or other incumbrance, details should be given, e.g. name of building society and roll number.

Bruton Knowles Limited, Olympus House, Olympus Park, Quedgeley, Gloucester GL2 4NF Agents acting for National Grid Electricity Transmission Plc

DATE: 8th November 2023

Open to feedback

From

8-Nov-2023

To

22-Nov-2023

Need to publish a public notice?

If you need to publish a public notice, please contact North Somerset Times directly at:

swpublic.notices@localiq.co.uk

01392 888400

About Us

The Public Notice Portal is owned and operated by the News Media Association, the voice of UK national, regional, and local newspapers in all their print and digital forms. NMA members include nearly 900 local and regional news titles which reach 40 million people across the length and breadth of the country each month.

Public Notice PortalNews Media Association