Curraghinalt, Gortin – Planning Enforcement Appeals

BT79 7SFPublished 16/10/25
Impartial Reporter • 

What is planned?

Planning Appeals Commission

Enforcement Appeal

www.pacni.gov.uk

The following appeals have been received. Any person wishing to make representations about the appeal should do so in writing to the Planning Appeals Commission at 4th Floor, 92 Ann Street, Belfast BT1 3HH. Representations must be received within 14 days to ensure participation in the appeal process. Copies of such representations will be sent to the parties involved.

Appeal Ref No Appellant Name Development and Location
2025/E0048 Dalradian Gold Limited Alleged (1) Failure to comply with condition 5 of K/2014/0387/F in that site decommissioning has not been carried out in accordance with the approved Site Decommissioning Method Statement (Appendix 2) in the following respects: (i) Removal of explosives store building and concrete slab, access track extension and hardstanding in accordance with the approved details and timescale has not been carried out; (ii) Removal of temporary protective fencing gates and CCTV in accordance with the approved details and timescale has not been carried out; (iii) Removal of temporary protective housing around existing ventilation raise in accordance with the approved details and timescale has not been carried out; (iv) Removal of culverts and headwalls in accordance with the approved details and timescale has not been carried out. (2) Failure to comply with condition 6 of K/2014/0387/F in that the implementation of the site restoration in accordance with conditions 5 and 7 has not been completed within the timeframe stipulated.
Lands approx. 600m southwest of No 45 Camcosy Road, Curraghinalt, Gortin, Co. Tyrone, BT79 7SF
2025/E0049 Dalradian Gold Limited

Alleged (1) Failure to comply with condition 39 of K/2014/0246/F in that site decommissioning has not been carried out in accordance with the approved Site Decommissioning Method Statement (Appendix 2) in the following respects:

(i) Removal of office/welfare containers in accordance with the approved details and timescale has not been carried out;

(ii) Removal of warehouse buildings in accordance with the approved details and timescale has not been carried out;

(iii) Removal of building foundations in accordance with the approved details and timescale has not been carried out;

(iv) Removal of the water treatment plant in accordance with the approved details and timescale has not been carried out;

(v) Removal of yard area hardstanding in accordance with the approved details and timescale has not been carried out;

(vi) Removal of berms in accordance with the approved details and timescale has not been carried out;

(vii) Removal of security hut in accordance with the approved details and timescale has not been carried out;

(viii) Removal of perimeter/security fencing, gates and CCTV in accordance with the approved details and timescale has not been carried out.

(2) Failure to comply with condition 40 of K/2014/0246/F in that site restoration has not been carried out in accordance with the approved Restoration Method Statement (Appendix 3) in the following respects:

(i) Removal of office/welfare containers in accordance with the approved details and timescale has not been carried out;

(ii) Removal of warehouse buildings in accordance with the approved details and timescale has not been carried out;

(iii) Removal of building foundations in accordance with the approved details and timescale has not been carried out;

(iv) Removal of the water treatment plant in accordance with the approved details and timescale has not been carried out;

(v) Removal of yard area hardstanding in accordance with the approved details and timescale has not been carried out;

(vi) Removal of berms in accordance with the approved details and timescale has not been carried out;

(vii) Removal of security hut in accordance with the approved details and timescale has not been carried out;

(viii) Removal of perimeter/security fencing, gates and CCTV in accordance with the approved details and timescale has not been carried out.

(3) Failure to comply with condition 41 of K/2014/0246/F in that the implementation of the restoration of the site in accordance with Drawing Number 14 (approved under K/2013/0072/F) (Appendix 4) and in accordance with conditions numbered 39 and 40 of K/2014/0246/F was not completed on or before three years from the date of commencement

Lands approx. 165m west of 45 Camcosy Road, Curraghinalt, Gortin

2025/E0050 Richard Hawkes

Alleged unauthorised vehicular access and hardcore laneway being development carried out without the benefit of planning permission so required

Land at immediately south west of 60 Moylagh Road, Beragh

Need to publish a public notice?

If you need to publish a public notice, please contact Impartial Reporter directly at:

advertising@impartialreporter.com

028 66 324425

About Us

The Public Notice Portal is owned and operated by the News Media Association, the voice of UK national, regional, and local newspapers in all their print and digital forms. NMA members include nearly 900 local and regional news titles which reach 42 million people across the length and breadth of the country each month.

Public Notice PortalNews Media Association