Brookshill, Temporary Road Closure Due To Traffic Scheme Works
What is happening?
Section 14(1)(A) Road Traffic Regulation Act 1984 As Amended By The Road Traffic
(Temporary Restrictions) Act 1991 Temporary Road Closure - Brookshill
THE COUNCIL OF THE LONDON BOROUGH OF HARROW HEREBY GIVE NOTICE that they intend to make a Temporary Traffic Management order under the provisions of Section 14 (1) (a) of the Road Traffic Regulation Act 1984 as amended by the Road Traffic (Temporary Restrictions) Act 1991. This is to facilitate traffic scheme works.
1. The order may be cited as The Harrow (Brookshill) Temporary Traffic Order 2024, and shall be operational between 08:00hrs and 17:00hrs on 16th May 2024 and shall remain in effect until 3rd August 2024 or until the completion of the works, whichever is the sooner. It is anticipated that all of the work should be complete by 23rd May 2024.
2. Vehicles shall be prohibited from travelling in a southbound direction on Brookshill, between a point opposite the extended southern kerb-line of Harrow College and its junction with Uxbridge Road, Harrow Weald.
3. Nothing in paragraph 2 above shall apply to:-
(a) any vehicle being used for ambulance, fire brigade or police purposes;
(b) anything done with the permission or at the direction of a police constable in uniform or a civil enforcement officer;
(c) any person who causes any vehicle to proceed in accordance with any restriction or requirement indicated by traffic signs placed pursuant to Section 66 or Section 67 of the Road Traffic Regulation Act 1984;
(d) any vehicles used in connection with the traffic scheme works;
(e) any vehicles needing to gain access to properties in the closed extents as far as is practicably possible.
4. The provisions of the order will not have effect unless all the signs in accordance with the provisions of the Traffic Signs Regulations and General Directions 2016 are displayed, removed or covered, or unless at the direction of a police constable in uniform or a civil enforcement officer.
5. Diversion route; via Clamp Hill and Uxbridge Road, Harrow Weald.
Dated 16th May 2024
Ian Slaney
Head of Service - Parking & Network Management
Place Directorate, Environmental Servicers, London Borough of Harrow, Forward Drive, Harrow, HA3 8FL
How long will it take?
Planned start
16-May-2024
Estimated end
23-May-2024